Headway Signia
by Headway Believe Realty LLP · Ambivali, Mumbai 400053Also near Andheri West, Four Bungalows, Versova, Four Bungalow, VersovaRegistered on MahaRERA as “Signia”
What’s in the report? →Possession date of Headway Signia (MahaRERA PR1180002501892): 31 July 2030. It has 26 homes (2 BHK and 3 BHK, 560–923 sq ft carpet), 13% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002501892, and currently active. Its completion date is now July 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1180002501892, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Headway Signia?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Headway Signia has moved
31 March 2030
Completion date given when the project was registered
31 July 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Headway Signia’s extension records on MahaRERA (PR1180002501892), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Headway Signia
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002501892
- Status
- Registered and active
- Builder
- Headway Believe Realty LLP
- Location
- Ambivali, Mumbai · 400053
- Project type
- Residential / Group Housing
- Registered on
- 26 Dec 2025
- Completion date at registration
- March 2030
- Latest completion date
- July 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 26
- Sold or booked
- 13%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Headway Signia, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Signia / A-Wing | 0% | 0% | 0% | 0% |
| Signia / B-Wing | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Signia: covers top of Basement level
- Signia: covers top of Basement level
Latest CC order on MahaRERA: dated 29/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Headway Signia every 1–2 months.
Headway Signia: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 560 – 735 | 18 |
| 3 BHK | 904 – 923 | 8 |
- Buildings: Signia (13 floors, 13 units) · Signia (13 floors, 13 units)
- Car parking: 135 covered
- Land: 1,676 sq m (about 0.4 acres) · sanctioned built-up 2,103 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Headway Signia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Headway Signia: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Headway Signia
What is the possession date of Headway Signia?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Headway Signia in Ambivali, Mumbai is 31 July 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Headway Signia?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Headway Signia's builder has filed on MahaRERA, the official one, is 31 July 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Headway Signia?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Headway Signia in Ambivali, Mumbai is PR1180002501892.
Is Headway Signia registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Headway Signia is registered as PR1180002501892 and its status is "Registered and active".
What is the current construction status of Headway Signia? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Headway Signia's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Headway Signia have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Headway Signia safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Headway Signia is registered on MahaRERA as PR1180002501892, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Headway Signia?
Headway Signia is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Headway Signia are 560 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Headway Signia?
For a flat in Headway Signia (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Headway Signia received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Headway Signia is still under construction, with 31 July 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Headway Signia a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Headway Signia is a redevelopment: 18 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Headway Signia uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Headway Signia was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Headway Signia's possession date changes?
The latest dates are on Headway Signia's MahaRERA page (PR1180002501892). GharKundli's Kundli Watch sends a free WhatsApp update on Headway Signia every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Headway Signia have?
According to GharKundli's check of MahaRERA records (updated October 2026), Headway Signia has 2 buildings filed: Signia with 13 floors and 13 units; Signia with 13 floors and 13 units.
What are the flat sizes (carpet area) in Headway Signia?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Headway Signia: 2 BHK: 560 to 735 sq ft carpet (18 homes); 3 BHK: 904 to 923 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Headway Signia have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 135 covered car parking spaces for Headway Signia.
How big is the land of Headway Signia?
According to GharKundli's check of MahaRERA records (updated October 2026), Headway Signia stands on 1,676 sq m of land (about 0.4 acres), with 2,103 sq m of sanctioned built-up area.
What are the reviews of Headway Signia?
Google Maps has reviews of Headway Signia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Headway Signia?
Headway Signia by Headway Believe Realty LLP is in Ambivali, Mumbai, pincode 400053 (near Andheri West, Four Bungalows, Versova, Four Bungalow, Versova), Maharashtra, and is registered on MahaRERA as PR1180002501892, per GharKundli's check of MahaRERA records. GharKundli lists all 162 MahaRERA projects in Andheri West (400053).
How many flats are in Headway Signia, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Headway Signia has 26 homes in 2 towers registered on MahaRERA, and 13% of them are sold or booked.
When was Headway Signia registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Headway Signia was registered on MahaRERA on 26 December 2025. GharKundli did not find a title report on the land on file there.
Does Headway Signia have any legal issues or court cases?
No court cases are listed for Headway Signia on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Headway Signia?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Headway Believe Realty LLP.
Check it yourself on MahaRERA
- How to check the possession date of Headway Signia
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai Suburban →
Other projects in Andheri West (400053)
- Avira Sai Shreeji Co-operative Housing Society Limited
- Disha Elysium
- Woodshire
- Konark Solitaire - Phase II
- Mangeshi Neptune
- Mangeshi Jupiter
- Shantiniketan 2 CHS LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.