What’s in the report? →Possession date of Rishabraj Avyaana (MahaRERA PM1180002501823): 30 April 2030. It has 90 homes (1 BHK, 2 BHK and 3 BHK, 462–1275 sq ft carpet), 73% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1180002501823, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PM1180002501823, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Rishabraj Avyaana?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Rishabraj Avyaana has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Rishabraj Avyaana’s extension records on MahaRERA (PM1180002501823), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rishabraj Avyaana
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1180002501823
- Status
- Registered and active
- Builder
- RISHABRAJ ESTATE DEVELOPERS PRIVATE LIMITED
- Location
- Goregaon West, Mumbai · 400062
- Project type
- Mixed
- Registered on
- 17 Dec 2025
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 90
- Sold or booked
- 73%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Rishabraj Avyaana, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Rishabraj Avyaana / A Wing | 100% | 10% | 0% | 0% |
| Rishabraj Avyaana / B Wing | 100% | 10% | 0% | 0% |
| Rishabraj Avyaana / C Wing | 100% | 10% | 0% | 0% |
| Rishabraj Avyaana / D Wing | 100% | 10% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Rishabraj Avyaana: covers Upto Plinth Level
- Rishabraj Avyaana: covers Upto Plinth Level
- Rishabraj Avyaana: covers Upto Plinth Level
- Rishabraj Avyaana: covers Upto Plinth Level
Latest CC order on MahaRERA: dated 04/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rishabraj Avyaana every 1–2 months.
Rishabraj Avyaana: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 501 – 778 | 59 |
| Shops | 56 – 871 | 29 |
| 3 BHK | 779 – 1,275 | 26 |
| 1 BHK | 462 | 5 |
- Buildings: Rishabraj Avyaana (11 floors, 37 units) · Rishabraj Avyaana (9 floors, 15 units) · Rishabraj Avyaana (9 floors, 19 units) · Rishabraj Avyaana (11 floors, 48 units)
- Car parking: 440 covered
- Land: 7,354 sq m (about 1.8 acres) · sanctioned built-up 10,586 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Rishabraj Avyaana →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rishabraj Avyaana: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Rishabraj Avyaana
What is the possession date of Rishabraj Avyaana?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rishabraj Avyaana in Goregaon West, Mumbai is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Rishabraj Avyaana?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rishabraj Avyaana's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Rishabraj Avyaana?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rishabraj Avyaana in Goregaon West, Mumbai is PM1180002501823.
Is Rishabraj Avyaana registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rishabraj Avyaana is registered as PM1180002501823 and its status is "Registered and active".
What is the current construction status of Rishabraj Avyaana? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Rishabraj Avyaana's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 10% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Rishabraj Avyaana have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Rishabraj Avyaana safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Rishabraj Avyaana is registered on MahaRERA as PM1180002501823, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Rishabraj Avyaana?
Rishabraj Avyaana is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Rishabraj Avyaana are 462 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Rishabraj Avyaana?
For a flat in Rishabraj Avyaana (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Rishabraj Avyaana received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Rishabraj Avyaana is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Rishabraj Avyaana a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Rishabraj Avyaana is a redevelopment: 82 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Rishabraj Avyaana uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Rishabraj Avyaana was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Rishabraj Avyaana's possession date changes?
The latest dates are on Rishabraj Avyaana's MahaRERA page (PM1180002501823). GharKundli's Kundli Watch sends a free WhatsApp update on Rishabraj Avyaana every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rishabraj Avyaana have?
According to GharKundli's check of MahaRERA records (updated October 2026), Rishabraj Avyaana has 4 buildings filed: Rishabraj Avyaana with 11 floors and 37 units; Rishabraj Avyaana with 9 floors and 15 units; Rishabraj Avyaana with 9 floors and 19 units; Rishabraj Avyaana with 11 floors and 48 units.
What are the flat sizes (carpet area) in Rishabraj Avyaana?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Rishabraj Avyaana: 2 BHK: 501 to 778 sq ft carpet (59 homes); 3 BHK: 779 to 1275 sq ft carpet (26 homes); 1 BHK: 462 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Rishabraj Avyaana have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 440 covered car parking spaces for Rishabraj Avyaana.
How big is the land of Rishabraj Avyaana?
According to GharKundli's check of MahaRERA records (updated October 2026), Rishabraj Avyaana stands on 7,354 sq m of land (about 1.8 acres), with 10,586 sq m of sanctioned built-up area.
What are the reviews of Rishabraj Avyaana?
Google Maps has reviews of Rishabraj Avyaana written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Rishabraj Avyaana?
Rishabraj Avyaana by RISHABRAJ ESTATE DEVELOPERS PRIVATE LIMITED is in Goregaon West, Mumbai, pincode 400062 (near Andheri East, Goregaon East, Bangur Nagar), Maharashtra, and is registered on MahaRERA as PM1180002501823, per GharKundli's check of MahaRERA records.
How many flats are in Rishabraj Avyaana, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Rishabraj Avyaana has 90 homes in 4 towers registered on MahaRERA, and 73% of them are sold or booked.
When was Rishabraj Avyaana registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rishabraj Avyaana was registered on MahaRERA on 17 December 2025. GharKundli did not find a title report on the land on file there.
Does Rishabraj Avyaana have any legal issues or court cases?
No court cases are listed for Rishabraj Avyaana on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Rishabraj Avyaana?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RISHABRAJ ESTATE DEVELOPERS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of Rishabraj Avyaana
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pincode not filed (400062)
All Borivali projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.