Possession date of Lodha Sovrano Tower C (MahaRERA PR1180002501764): 30 April 2031. It has 120 homes (Other, 308–2549 sq ft carpet), 25% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002501764, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002501764, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Lodha Sovrano Tower C?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Lodha Sovrano Tower C has moved

  1. 31 December 2030

    Completion date given when the project was registered

  2. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Lodha Sovrano Tower C’s extension records on MahaRERA (PR1180002501764), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Lodha Sovrano Tower C

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
PR1180002501764
Status
Registered and active
Builder
Lodha Developers Limited
Location
Jogeshwari, Mumbai · 400102
Project type
Residential / Group Housing
Registered on
15 Dec 2025
Completion date at registration
December 2030
Latest completion date
April 2031
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
120
Sold or booked
25%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
180

Construction progress of Lodha Sovrano Tower C, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing -3 (Tower -C)0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing -3 (Tower -C): covers 0 floors

Latest CC order on MahaRERA: dated 05/12/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha Sovrano Tower C every 1–2 months.

Lodha Sovrano Tower C: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other308 – 2,549120

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects.

Read Google reviews of Lodha Sovrano Tower C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lodha Sovrano Tower C: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Lodha Sovrano Tower C

What is the possession date of Lodha Sovrano Tower C?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha Sovrano Tower C in Jogeshwari, Mumbai is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Lodha Sovrano Tower C?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha Sovrano Tower C's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Lodha Sovrano Tower C?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha Sovrano Tower C in Jogeshwari, Mumbai is PR1180002501764.

Is Lodha Sovrano Tower C registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Sovrano Tower C is registered as PR1180002501764 and its status is "Registered and active".

What is the current construction status of Lodha Sovrano Tower C? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Sovrano Tower C's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing -3 (Tower -C) is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Lodha Sovrano Tower C have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Lodha Sovrano Tower C safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Sovrano Tower C is registered on MahaRERA as PR1180002501764, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Lodha Sovrano Tower C?

Lodha Sovrano Tower C is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Lodha Sovrano Tower C are 308 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Lodha Sovrano Tower C?

For a flat in Lodha Sovrano Tower C (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Lodha Sovrano Tower C received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Sovrano Tower C is still under construction, with 30 April 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Lodha Sovrano Tower C a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Sovrano Tower C's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has Lodha Sovrano Tower C uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Lodha Sovrano Tower C was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Lodha Sovrano Tower C have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Sovrano Tower-A (PR1180002501771, possession 31 Mar 2031); Sovrano Tower-B (PR1180002501743, possession 30 Apr 2031). Check that your agreement names the registration of your own wing.

How can I get updates if Lodha Sovrano Tower C's possession date changes?

The latest dates are on Lodha Sovrano Tower C's MahaRERA page (PR1180002501764). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha Sovrano Tower C every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lodha Sovrano Tower C have?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Sovrano Tower C has one building filed: Wing -3 (Tower -C) with 32 floors and 120 units.

What are the flat sizes (carpet area) in Lodha Sovrano Tower C?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Lodha Sovrano Tower C: Other: 308 to 2549 sq ft carpet (120 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Lodha Sovrano Tower C have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 202 covered car parking spaces for Lodha Sovrano Tower C.

How big is the land of Lodha Sovrano Tower C?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Sovrano Tower C stands on 13,392 sq m of land (about 3.3 acres), with 14,713 sq m of sanctioned built-up area and 1,348 sq m of recreational open space.

What is the track record of Lodha Sovrano Tower C's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Lodha Sovrano Tower C?

Google Maps has reviews of Lodha Sovrano Tower C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Lodha Sovrano Tower C?

Lodha Sovrano Tower C by Lodha Developers Limited is in Jogeshwari, Mumbai, pincode 400102 (near Goregaon West, Oshiwara, Andheri West), Maharashtra, and is registered on MahaRERA as PR1180002501764, per GharKundli's check of MahaRERA records. GharKundli lists all 117 MahaRERA projects in Jogeshwari West (400102).

How many flats are in Lodha Sovrano Tower C, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Sovrano Tower C has 120 homes in 1 tower registered on MahaRERA, and 25% of them are sold or booked.

When was Lodha Sovrano Tower C registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Sovrano Tower C was registered on MahaRERA on 15 December 2025. GharKundli did not find a title report on the land on file there.

Does Lodha Sovrano Tower C have any legal issues or court cases?

No court cases are listed for Lodha Sovrano Tower C on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Lodha Sovrano Tower C?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.

All projects with possession due in 2031 in Mumbai Suburban →

Other projects in Jogeshwari West (400102)

All 117 projects in Jogeshwari West (400102) →

Other projects by Lodha Developers Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.