by STANS BUILDTECH HOUSING · Jogeshwari East, Mumbai 400060Also near Andheri East, Jvlr, Andheri West
What’s in the report? →Possession date of Stans Arize (MahaRERA PR1180002600145): 30 April 2030. It has 258 homes (1 BHK and 2 BHK, 300–556 sq ft carpet), 74% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002600145, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1180002600145, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Stans Arize?
Possession date khiski: ab Apr 2030. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Stans Arize has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Stans Arize’s extension records on MahaRERA (PR1180002600145), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Stans Arize
Ready · October 2026 · 2 filings read
- Risk & trust score, every point explained
- What the title report on MahaRERA says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002600145
- Status
- Registered and active
- Builder
- STANS BUILDTECH HOUSING
- Location
- Jogeshwari East, Mumbai · 400060
- Project type
- Residential / Group Housing
- Registered on
- 17 Apr 2026
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 258
- Sold or booked
- 74%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Yes
- Latest construction certificate
- 6 Aug 2026
Construction progress of Stans Arize, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SIDDHAGURU EKTA SRA CHS | 80% | 0% | 0% | 0% |
| Stans Arize / A-Wing | 80% | 0% | 0% | 0% |
| Stans Arize / B-Wing | 80% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SIDDHAGURU EKTA SRA CHS: covers Plinth
- Stans Arize: covers Plinth
- Stans Arize: covers Plinth
Latest CC order on MahaRERA: dated 10/04/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Stans Arize every 1–2 months.
Stans Arize: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 300 – 398 | 218 |
| 2 BHK | 494 – 556 | 40 |
| Shops | 42 – 375 | 18 |
- Buildings: SIDDHAGURU EKTA SRA CHS (21 floors, 131 units) · Stans Arize (23 floors, 84 units) · Stans Arize (23 floors, 61 units)
- Car parking: 87 covered
- Land: 2,620 sq m (about 0.6 acres) · sanctioned built-up 10,446 sq m · recreational space 150 sq m
- Boundaries filed include: Jogeshwari Gufa BMC School
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Stans Buildtech Housing (a group of 6 linked companies) has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 18 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Stans Arize →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Stans Arize: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
1 watching
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Stans Arize
What is the possession date of Stans Arize?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Stans Arize in Jogeshwari East, Mumbai is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Stans Arize?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Stans Arize's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Stans Arize?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Stans Arize in Jogeshwari East, Mumbai is PR1180002600145.
Is Stans Arize registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Stans Arize is registered as PR1180002600145 and its status is "Registered and active".
What is the current construction status of Stans Arize? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Stans Arize's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. The latest construction certificate the builder filed there is dated 6 August 2026. GharKundli's full report compares construction progress with the deadline.
Does Stans Arize have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Stans Arize safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Stans Arize is registered on MahaRERA as PR1180002600145, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Stans Arize?
Stans Arize is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Stans Arize are 300 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Stans Arize?
For a flat in Stans Arize (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Stans Arize received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Stans Arize is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Stans Arize a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Stans Arize is a redevelopment: 128 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Stans Arize uploaded its title report on MahaRERA?
Yes. According to GharKundli's check of MahaRERA records (updated October 2026), an advocate's title report for Stans Arize is uploaded on MahaRERA. It says who owns the land and whether there's any loan, case or claim on it. GharKundli's full report reads it and lists anything that needs a written answer from the builder.
A loan or claim on the land can hold up your flat or your home loan. See what the title report says →
How can I get updates if Stans Arize's possession date changes?
The latest dates are on Stans Arize's MahaRERA page (PR1180002600145). GharKundli's Kundli Watch sends a free WhatsApp update on Stans Arize every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Stans Arize have?
According to GharKundli's check of MahaRERA records (updated October 2026), Stans Arize has 3 buildings filed: SIDDHAGURU EKTA SRA CHS with 21 floors and 131 units; Stans Arize with 23 floors and 84 units; Stans Arize with 23 floors and 61 units.
What are the flat sizes (carpet area) in Stans Arize?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Stans Arize: 1 BHK: 300 to 398 sq ft carpet (218 homes); 2 BHK: 494 to 556 sq ft carpet (40 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Stans Arize have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 87 covered car parking spaces for Stans Arize.
How big is the land of Stans Arize?
According to GharKundli's check of MahaRERA records (updated October 2026), Stans Arize stands on 2,620 sq m of land (about 0.6 acres), with 10,446 sq m of sanctioned built-up area and 150 sq m of recreational open space.
What is the track record of Stans Arize's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Stans Buildtech Housing (a group of 6 linked companies) has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 18 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Stans Arize?
Google Maps has reviews of Stans Arize written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Stans Arize?
Stans Arize by STANS BUILDTECH HOUSING is in Jogeshwari East, Mumbai, pincode 400060 (near Andheri East, Jvlr, Andheri West), Maharashtra, and is registered on MahaRERA as PR1180002600145, per GharKundli's check of MahaRERA records. Its boundaries filed there include Jogeshwari Gufa BMC School. GharKundli lists all 97 MahaRERA projects in Jogeshwari East (400060).
How many flats are in Stans Arize, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Stans Arize has 258 homes in 3 towers registered on MahaRERA, and 74% of them are sold or booked.
When was Stans Arize registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Stans Arize was registered on MahaRERA on 17 April 2026. A title report on the land is on file there.
Does Stans Arize have any legal issues or court cases?
No court cases are listed for Stans Arize on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Stans Arize?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is STANS BUILDTECH HOUSING.
Check it yourself on MahaRERA
- How to check the possession date of Stans Arize
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai Suburban →
Other projects in Jogeshwari East (400060)
- Avant Heritage - III
- Om Shivalaya CHS Ltd
- Bhawani Heights
- Shraddha West Residency
- Rose Blossom CHSL
- Shivkunj
- Dattaram Tower
- Vraj Bhumi Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.