Tarun Yuvak Sangh CHSL

by Ossia developers · Borivali, Mumbai 400066Also near Rajendra Nagar, Magathane, Andheri East

What’s in the report? →

Possession date of Tarun Yuvak Sangh CHSL (MahaRERA PR1180002600368): 30 January 2029. It has 13 homes (1 BHK, 2 BHK and 3 BHK, 448–781 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002600368, and currently active. Its completion date is now January 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002600368, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Tarun Yuvak Sangh CHSL?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Tarun Yuvak Sangh CHSL has moved

  1. 30 September 2028

    Completion date given when the project was registered

  2. 30 January 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Tarun Yuvak Sangh CHSL’s extension records on MahaRERA (PR1180002600368), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Tarun Yuvak Sangh CHSL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002600368
Status
Registered and active
Builder
Ossia developers
Location
Borivali, Mumbai · 400066
Project type
Residential / Group Housing
Registered on
7 May 2026
Completion date at registration
September 2028
Latest completion date
January 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
13
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Tarun Yuvak Sangh CHSL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TARUN YUVAK SANGH CHSL100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • TARUN YUVAK SANGH CHSL: covers CC UP TO PLINTH LEVEL

Latest CC order on MahaRERA: dated 13/03/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tarun Yuvak Sangh CHSL every 1–2 months.

Tarun Yuvak Sangh CHSL: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK540 – 6307
1 BHK448 – 4495
3 BHK7811

The builder’s record and reviews

Ossia Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 8 months); 5 still being built, 1 past the promised date (typically 100 months late); 1 lapsed. 4 complaints on MahaRERA across 2 projects.

Read Google reviews of Tarun Yuvak Sangh CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Tarun Yuvak Sangh CHSL: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Tarun Yuvak Sangh CHSL

What is the possession date of Tarun Yuvak Sangh CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tarun Yuvak Sangh CHSL in Borivali, Mumbai is 30 January 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Tarun Yuvak Sangh CHSL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Tarun Yuvak Sangh CHSL's builder has filed on MahaRERA, the official one, is 30 January 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Tarun Yuvak Sangh CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tarun Yuvak Sangh CHSL in Borivali, Mumbai is PR1180002600368.

Is Tarun Yuvak Sangh CHSL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tarun Yuvak Sangh CHSL is registered as PR1180002600368 and its status is "Registered and active".

What is the current construction status of Tarun Yuvak Sangh CHSL? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Tarun Yuvak Sangh CHSL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TARUN YUVAK SANGH CHSL is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Tarun Yuvak Sangh CHSL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Tarun Yuvak Sangh CHSL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Tarun Yuvak Sangh CHSL is registered on MahaRERA as PR1180002600368, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Tarun Yuvak Sangh CHSL?

Tarun Yuvak Sangh CHSL is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Tarun Yuvak Sangh CHSL are 448 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Tarun Yuvak Sangh CHSL?

For a flat in Tarun Yuvak Sangh CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Tarun Yuvak Sangh CHSL received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tarun Yuvak Sangh CHSL is still under construction, with 30 January 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Tarun Yuvak Sangh CHSL a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Tarun Yuvak Sangh CHSL is a redevelopment: 4 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Tarun Yuvak Sangh CHSL uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tarun Yuvak Sangh CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Tarun Yuvak Sangh CHSL's possession date changes?

The latest dates are on Tarun Yuvak Sangh CHSL's MahaRERA page (PR1180002600368). GharKundli's Kundli Watch sends a free WhatsApp update on Tarun Yuvak Sangh CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Tarun Yuvak Sangh CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), Tarun Yuvak Sangh CHSL has one building filed: TARUN YUVAK SANGH CHSL with 5 floors and 13 units.

What are the flat sizes (carpet area) in Tarun Yuvak Sangh CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Tarun Yuvak Sangh CHSL: 2 BHK: 540 to 630 sq ft carpet (7 homes); 1 BHK: 448 to 449 sq ft carpet (5 homes); 3 BHK: 781 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Tarun Yuvak Sangh CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 27 covered car parking spaces for Tarun Yuvak Sangh CHSL.

How big is the land of Tarun Yuvak Sangh CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), Tarun Yuvak Sangh CHSL stands on 560 sq m of land (about 0.1 acres), with 751 sq m of sanctioned built-up area.

What is the track record of Tarun Yuvak Sangh CHSL's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ossia Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 8 months); 5 still being built, 1 past the promised date (typically 100 months late); 1 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Tarun Yuvak Sangh CHSL?

Google Maps has reviews of Tarun Yuvak Sangh CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Tarun Yuvak Sangh CHSL?

Tarun Yuvak Sangh CHSL by Ossia developers is in Borivali, Mumbai, pincode 400066 (near Rajendra Nagar, Magathane, Andheri East), Maharashtra, and is registered on MahaRERA as PR1180002600368, per GharKundli's check of MahaRERA records. GharKundli lists all 228 MahaRERA projects in Borivali East (400066).

How many flats are in Tarun Yuvak Sangh CHSL, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Tarun Yuvak Sangh CHSL has 13 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Tarun Yuvak Sangh CHSL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tarun Yuvak Sangh CHSL was registered on MahaRERA on 7 May 2026. GharKundli did not find a title report on the land on file there.

Does Tarun Yuvak Sangh CHSL have any legal issues or court cases?

No court cases are listed for Tarun Yuvak Sangh CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Tarun Yuvak Sangh CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ossia developers, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Borivali East (400066)

All 228 projects in Borivali East (400066) →

Other projects by Ossia developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.