Possession date of Kripa Jewel (MahaRERA PR1180002601267): 30 April 2030. It has 39 homes (1 BHK, 2 BHK and 3 BHK, 411–2874 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002601267, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002601267, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Kripa Jewel?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kripa Jewel has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kripa Jewel’s extension records on MahaRERA (PR1180002601267), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kripa Jewel

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002601267
Status
Registered and active
Builder
Kripa Oneness Private Limited
Location
Bandra West, Mumbai · 400050
Project type
Residential / Group Housing
Registered on
20 Jul 2026
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
39
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Kripa Jewel, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sale Building0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Sale Building: covers Plinth Level

Latest CC order on MahaRERA: dated 14/07/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kripa Jewel every 1–2 months.

Kripa Jewel: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK906 – 1,33313
4 BHK1,33313
2 BHK756 – 76410
Duplex1,951 – 7,5332
1 BHK411 – 4842
5 BHK2,8741

The builder’s record and reviews

Kripa Oneness has 5 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Kripa Jewel →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kripa Jewel: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kripa Jewel

What is the possession date of Kripa Jewel?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kripa Jewel in Bandra West, Mumbai is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Kripa Jewel?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kripa Jewel's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Kripa Jewel?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kripa Jewel in Bandra West, Mumbai is PR1180002601267.

Is Kripa Jewel registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Jewel is registered as PR1180002601267 and its status is "Registered and active".

What is the current construction status of Kripa Jewel? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Jewel's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sale Building is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Kripa Jewel have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kripa Jewel safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Jewel is registered on MahaRERA as PR1180002601267, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kripa Jewel?

Kripa Jewel is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Kripa Jewel are 411 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kripa Jewel?

For a flat in Kripa Jewel (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Kripa Jewel received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Jewel is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Kripa Jewel a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Jewel is a redevelopment: 22 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Kripa Jewel uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kripa Jewel was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kripa Jewel's possession date changes?

The latest dates are on Kripa Jewel's MahaRERA page (PR1180002601267). GharKundli's Kundli Watch sends a free WhatsApp update on Kripa Jewel every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kripa Jewel have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Jewel has one building filed: Sale Building with 17 floors and 41 units.

What are the flat sizes (carpet area) in Kripa Jewel?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kripa Jewel: 3 BHK: 906 to 1333 sq ft carpet (13 homes); 4 BHK: 1333 sq ft carpet (13 homes); 2 BHK: 756 to 764 sq ft carpet (10 homes); 1 BHK: 411 to 484 sq ft carpet (2 homes); 5 BHK: 2874 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Kripa Jewel have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 148 covered car parking spaces for Kripa Jewel.

How big is the land of Kripa Jewel?

According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Jewel stands on 1,258 sq m of land (about 0.3 acres), with 5,374 sq m of sanctioned built-up area and 98 sq m of recreational open space.

What is the track record of Kripa Jewel's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Oneness has 5 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Kripa Jewel?

Google Maps has reviews of Kripa Jewel written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kripa Jewel?

Kripa Jewel by Kripa Oneness Private Limited is in Bandra West, Mumbai, pincode 400050 (near Khar West, Bandra East, Andheri West), Maharashtra, and is registered on MahaRERA as PR1180002601267, per GharKundli's check of MahaRERA records. Its boundaries filed there include Turner Road. GharKundli lists all 168 MahaRERA projects in Bandra West (400050).

How many flats are in Kripa Jewel, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Jewel has 39 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Kripa Jewel registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kripa Jewel was registered on MahaRERA on 20 July 2026. GharKundli did not find a title report on the land on file there.

Does Kripa Jewel have any legal issues or court cases?

No court cases are listed for Kripa Jewel on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Kripa Jewel?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kripa Oneness Private Limited, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in Bandra West (400050)

All 168 projects in Bandra West (400050) →

Other projects by Kripa Oneness Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.