PENTAGON ENCLAVE

by DAMJI HARI INFRASTRUCTURE PVT LTD · Shahapur, Thane

Possession date of PENTAGON ENCLAVE: 31 December 2025, moved from 31 December 2019 (72 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700010181. Status: Lapsed (registration period ended). 10 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about PENTAGON ENCLAVE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PENTAGON ENCLAVE has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51700005382)

    Reason the builder gave MahaRERA:
    “1) There was a delay in supply of river sand, metal no.2, crush sand and wash sand by the suppliers though the order for the same had been placed in a timely manner by the promoter. 2) The unexpected rains and prolonged monsoons further has…” Read the full reason“1) There was a delay in supply of river sand, metal no.2, crush sand and wash sand by the suppliers though the order for the same had been placed in a timely manner by the promoter. 2) The unexpected rains and prolonged monsoons further has caused a further delay. 3) Due to bankruptcy proceedings against non- banking finance companies like DHFL and Indiabulls,amounts have not been disbursed since the past year. Almost 50% of allotted flats are mortgagedwith these banksfor a home loan.”
  3. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT51700010735)

    Reason the builder gave MahaRERA:
    “1. Unavailability of raw materials due to covid 19 pandemic lockdown: Despite placing purchase orders for the raw materials on time, the same have not been supplied on time by the suppliers due to covid 19 pandemic lockdown. There was a del…” Read the full reason“1. Unavailability of raw materials due to covid 19 pandemic lockdown: Despite placing purchase orders for the raw materials on time, the same have not been supplied on time by the suppliers due to covid 19 pandemic lockdown. There was a delay in supply of cement,flooring tiles,electrical and plumbing materials,river sand, metal no.2, crush sand and wash sand by the suppliers though the order for the same had been placed in a timely manner by the promoter. 2. Labour/Manpower issue due to covid 19 pandemic lockdown : Due to Covid 19 Pandemic, nationwide complete lockdown was declared which ha…”
  4. 30 November 2023

    Extended at the builder's request (MahaRERA application EXT51700013203)

    Reason the builder gave MahaRERA: “Due to certain mitigating circumstances the project is still incomplete”
  5. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT51700018081)

    Reason the builder gave MahaRERA: “Project completion delayed due to certain mitigating circumstances beyond the control of the promoter”
  6. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700027987)

    Reason the builder gave MahaRERA:
    “We just want to inform you that we have obtained part OC for our project but still we want extension for second building and our commercial sector , the reason behind the extension is There are financial difficulties that make it hard for d…” Read the full reason“We just want to inform you that we have obtained part OC for our project but still we want extension for second building and our commercial sector , the reason behind the extension is There are financial difficulties that make it hard for developers to continue construction. Issues like non-payment by buyers, difficulty in securing funding, or lack of working capital which affects delay in construction. The cost of construction materials can fluctuate significantly, which may lead to budget overruns. That’s also delay the project timelines. Sometimes, delays in specific work packages, cause…”

Source: PENTAGON ENCLAVE’s extension records on MahaRERA (P51700010181), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PENTAGON ENCLAVE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 10 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700010181
Status
Lapsed (registration period ended)
Builder
DAMJI HARI INFRASTRUCTURE PVT LTD
Location
Shahapur, Thane · 421601
Project type
Residential / Group Housing
Registered on
24 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2025
Delay so far
72 months
Homes
238
Sold or booked
77%
Towers
3
Complaints on MahaRERA
10
Court cases listed
0
Title report on file
Not found

Construction progress of PENTAGON ENCLAVE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PENTA 1 - TYPE 2100%100%100%0%
PENTA 2 - TYPE 3100%100%80%0%
COMMERCIAL COMPLEX - TYPE 1100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • PENTA 1 - TYPE 2: covers 8 floors
  • PENTA 2 - TYPE 3: covers 8 floors
  • COMMERCIAL COMPLEX - TYPE 1: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PENTAGON ENCLAVE every month.

PENTAGON ENCLAVE: buildings, flats and land, as filed on MahaRERA

  • Buildings: PENTA 1 - TYPE 2 (9 floors, 119 units) · PENTA 2 - TYPE 3 (9 floors, 119 units) · COMMERCIAL COMPLEX - TYPE 1 (3 floors, 8 units)
  • Land: 7,816 sq m (about 1.9 acres) · sanctioned built-up 8,268 sq m
  • Boundaries filed include: NATIONAL HIGHWAY III

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PENTAGON ENCLAVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PENTAGON ENCLAVE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PENTAGON ENCLAVE

What is the possession date of PENTAGON ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PENTAGON ENCLAVE in Shahapur, Thane is 31 December 2025 — 72 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PENTAGON ENCLAVE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PENTAGON ENCLAVE's builder has filed on MahaRERA, the official one, is 31 December 2025, already 72 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PENTAGON ENCLAVE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PENTAGON ENCLAVE's builder applied to MahaRERA to extend the completion date 5 times: to 30 December 2020, giving the reason "1) There was a delay in supply of river sand, metal no.2, crush sand and wash sand by the suppliers though the order for the same had been placed in a timely manner by the promoter. 2) The unexpected rains and prolonged monsoons further has caused a further delay. 3) Due to bankruptcy proceedings against non- banking finance companies like DHFL and Indiabulls,amounts have not been disbursed since the past year. Almost 50% of allotted flats are mortgagedwith these banksfor a home loan."; to 31 December 2022, giving the reason "1. Unavailability of raw materials due to covid 19 pandemic lockdown: Despite placing purchase orders for the raw materials on time, the same have not been supplied on time by the suppliers due to covid 19 pandemic lockdown. There was a delay in supply of cement,flooring tiles,electrical and plumbing materials,river sand, metal no.2, crush sand and wash sand by the suppliers though the order for the same had been placed in a timely manner by the promoter. 2. Labour/Manpower issue due to covid 19 pandemic lockdown : Due to Covid 19 Pandemic, nationwide complete lockdown was declared which ha…"; to 30 November 2023, giving the reason "Due to certain mitigating circumstances the project is still incomplete"; to 30 December 2024, giving the reason "Project completion delayed due to certain mitigating circumstances beyond the control of the promoter"; to 31 December 2025, giving the reason "We just want to inform you that we have obtained part OC for our project but still we want extension for second building and our commercial sector , the reason behind the extension is There are financial difficulties that make it hard for developers to continue construction. Issues like non-payment by buyers, difficulty in securing funding, or lack of working capital which affects delay in construction. The cost of construction materials can fluctuate significantly, which may lead to budget overruns. That’s also delay the project timelines. Sometimes, delays in specific work packages, cause…".

What is the RERA number of PENTAGON ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PENTAGON ENCLAVE in Shahapur, Thane is P51700010181.

Is PENTAGON ENCLAVE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PENTAGON ENCLAVE is registered as P51700010181 and its status is "Lapsed (registration period ended)".

What is the construction status of PENTAGON ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), PENTAGON ENCLAVE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does PENTAGON ENCLAVE have complaints on MahaRERA?

10 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PENTAGON ENCLAVE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PENTAGON ENCLAVE is registered on MahaRERA as P51700010181, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 72 months since registration and 10 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PENTAGON ENCLAVE's possession date changes?

The latest dates are on PENTAGON ENCLAVE's MahaRERA page (P51700010181). GharKundli's Kundli Watch sends a free WhatsApp update on PENTAGON ENCLAVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PENTAGON ENCLAVE have?

According to GharKundli's check of MahaRERA records (updated October 2026), PENTAGON ENCLAVE has 3 buildings filed: PENTA 1 - TYPE 2 with 9 floors and 119 units; PENTA 2 - TYPE 3 with 9 floors and 119 units; COMMERCIAL COMPLEX - TYPE 1 with 3 floors and 8 units.

How big is the land of PENTAGON ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), PENTAGON ENCLAVE stands on 7,816 sq m of land (about 1.9 acres), with 8,268 sq m of sanctioned built-up area.

Where can I read reviews of PENTAGON ENCLAVE?

Google Maps has reviews of PENTAGON ENCLAVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 10 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PENTAGON ENCLAVE?

PENTAGON ENCLAVE by DAMJI HARI INFRASTRUCTURE PVT LTD is in Shahapur, Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700010181, per GharKundli's check of MahaRERA records. Its boundaries filed there include NATIONAL HIGHWAY III.

How many homes are in PENTAGON ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), PENTAGON ENCLAVE has 238 homes in 3 towers registered on MahaRERA, and 77% of them are sold or booked.

When was PENTAGON ENCLAVE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PENTAGON ENCLAVE was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PENTAGON ENCLAVE?

No court cases are listed for PENTAGON ENCLAVE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of PENTAGON ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DAMJI HARI INFRASTRUCTURE PVT LTD.

Other projects in pincode 421601

All 184 projects in Shahapur (421601) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.