LA PROMENADE BAYWALK
by AADI DEVELOPERS · Kalyan, Thane
Possession date of LA PROMENADE BAYWALK: 30 June 2026, moved from 30 June 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700003336. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about LA PROMENADE BAYWALK?
How the possession date of LA PROMENADE BAYWALK has moved
30 June 2019
Completion date given when the project was registered
29 June 2020
Extended at the builder's request (MahaRERA application EXT51700002096)
Reason the builder gave MahaRERA:
“The work has got delayed because of the implication of GST rules, which made the billing and accounts procedure slower because of the lack of proper understanding, thus affecting the work flow. Addition to this, demonetisation have slowed t…” Read the full reason
“The work has got delayed because of the implication of GST rules, which made the billing and accounts procedure slower because of the lack of proper understanding, thus affecting the work flow. Addition to this, demonetisation have slowed the payment resulting in the delay of work. Further, there was also a shortage of the material and labour in the project vicinity area. Thus, we request you to kindly grant us the extension for a period of 12 months. Also, we hereby declare that, the work won’t be delayed thereafter and we ensure to provide the possession within the revised date of complet…”31 December 2021
Extended at the builder's request (MahaRERA application EXT51700008471)
Reason the builder gave MahaRERA:
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We had already completed 80% of the construction work before Lockdown and are hopeful that once we receive project extension of only one year, we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects”30 September 2023
Extended at the builder's request (MahaRERA application EXT51700012053)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for an extension of our project u/s 7(3). The project was delayed for reasons beyond our control on account of various reasons and more particularly on the account of the pandemic of Covid-…” Read the full reason
“In accordance with circular no 28, we hereby apply for an extension of our project u/s 7(3). The project was delayed for reasons beyond our control on account of various reasons and more particularly on the account of the pandemic of Covid-19. We have the consent of 51.85% of allottees for purpose of extension of the RERA registration period of the said project.”30 September 2025
Extended at the builder's request (MahaRERA application EXT51700017564)
Reason the builder gave MahaRERA: “In accordance with Oder no 40 dated 27/12/2022 we are applying for Extension without majority consents of the allotees. The project is has completed 90% of the work, we require extension for smooth functioning of the project.”
30 June 2026
Extended at the builder's request (MahaRERA application EA18102518155)
Reason the builder gave MahaRERA:
“The reason for this extension request is to account for unforeseen delays in construction, which have impacted our timeline, as well as the time needed to finalize regulatory approvals. Also, we are yet to apply for the Occupancy Certificat…” Read the full reason
“The reason for this extension request is to account for unforeseen delays in construction, which have impacted our timeline, as well as the time needed to finalize regulatory approvals. Also, we are yet to apply for the Occupancy Certificate (OC), and based on the current progress, we expect to receive the OC by March 2026. To accommodate these delays and ensure full compliance with all MahaRERA requirements, we are requesting this extension as a buffer period, allowing us to complete all formalities in a timely and orderly manner.”
Source: LA PROMENADE BAYWALK’s extension records on MahaRERA (P51700003336), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on LA PROMENADE BAYWALK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints and 1 court case, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700003336
- Status
- Lapsed (registration period ended)
- Builder
- AADI DEVELOPERS
- Location
- Kalyan, Thane · 421102
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2017
- Completion date at registration
- June 2019
- Latest completion date
- June 2026
- Delay so far
- 84 months
- Homes
- 140
- Sold or booked
- 69%
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 1
- Appeals at the tribunal
- 3
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of LA PROMENADE BAYWALK, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BAYWALK | 100% | 100% | 98% | 25% |
Commencement certificate (CC), as filed on MahaRERA
- BAYWALK: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on LA PROMENADE BAYWALK every month.
LA PROMENADE BAYWALK: buildings, flats and land, as filed on MahaRERA
- Buildings: BAYWALK (14 floors, 140 units)
- Land: 1,871 sq m (about 0.5 acres) · sanctioned built-up 11,666 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of LA PROMENADE BAYWALK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
LA PROMENADE BAYWALK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LA PROMENADE BAYWALK
What is the possession date of LA PROMENADE BAYWALK?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LA PROMENADE BAYWALK in Kalyan, Thane is 30 June 2026 — 84 months later than 30 June 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for LA PROMENADE BAYWALK?
Builders and listing sites often quote an earlier "target" date for handover. The completion date LA PROMENADE BAYWALK's builder has filed on MahaRERA, the official one, is 30 June 2026, already 84 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of LA PROMENADE BAYWALK extended?
According to GharKundli's check of MahaRERA records (updated October 2026), LA PROMENADE BAYWALK's builder applied to MahaRERA to extend the completion date 5 times: to 29 June 2020, giving the reason "The work has got delayed because of the implication of GST rules, which made the billing and accounts procedure slower because of the lack of proper understanding, thus affecting the work flow. Addition to this, demonetisation have slowed the payment resulting in the delay of work. Further, there was also a shortage of the material and labour in the project vicinity area. Thus, we request you to kindly grant us the extension for a period of 12 months. Also, we hereby declare that, the work won’t be delayed thereafter and we ensure to provide the possession within the revised date of complet…"; to 31 December 2021, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We had already completed 80% of the construction work before Lockdown and are hopeful that once we receive project extension of only one year, we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects"; to 30 September 2023, giving the reason "In accordance with circular no 28, we hereby apply for an extension of our project u/s 7(3). The project was delayed for reasons beyond our control on account of various reasons and more particularly on the account of the pandemic of Covid-19. We have the consent of 51.85% of allottees for purpose of extension of the RERA registration period of the said project."; to 30 September 2025, giving the reason "In accordance with Oder no 40 dated 27/12/2022 we are applying for Extension without majority consents of the allotees. The project is has completed 90% of the work, we require extension for smooth functioning of the project."; to 30 June 2026, giving the reason "The reason for this extension request is to account for unforeseen delays in construction, which have impacted our timeline, as well as the time needed to finalize regulatory approvals. Also, we are yet to apply for the Occupancy Certificate (OC), and based on the current progress, we expect to receive the OC by March 2026. To accommodate these delays and ensure full compliance with all MahaRERA requirements, we are requesting this extension as a buffer period, allowing us to complete all formalities in a timely and orderly manner.".
What is the RERA number of LA PROMENADE BAYWALK?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LA PROMENADE BAYWALK in Kalyan, Thane is P51700003336.
Is LA PROMENADE BAYWALK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LA PROMENADE BAYWALK is registered as P51700003336 and its status is "Lapsed (registration period ended)".
What is the construction status of LA PROMENADE BAYWALK?
According to GharKundli's check of MahaRERA records (updated October 2026), LA PROMENADE BAYWALK's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on BAYWALK is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.
Does LA PROMENADE BAYWALK have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is LA PROMENADE BAYWALK safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), LA PROMENADE BAYWALK is registered on MahaRERA as P51700003336, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 84 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if LA PROMENADE BAYWALK's possession date changes?
The latest dates are on LA PROMENADE BAYWALK's MahaRERA page (P51700003336). GharKundli's Kundli Watch sends a free WhatsApp update on LA PROMENADE BAYWALK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does LA PROMENADE BAYWALK have?
According to GharKundli's check of MahaRERA records (updated October 2026), LA PROMENADE BAYWALK has one building filed: BAYWALK with 14 floors and 140 units.
How big is the land of LA PROMENADE BAYWALK?
According to GharKundli's check of MahaRERA records (updated October 2026), LA PROMENADE BAYWALK stands on 1,871 sq m of land (about 0.5 acres), with 11,666 sq m of sanctioned built-up area.
Where can I read reviews of LA PROMENADE BAYWALK?
Google Maps has reviews of LA PROMENADE BAYWALK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is LA PROMENADE BAYWALK?
LA PROMENADE BAYWALK by AADI DEVELOPERS is in Kalyan, Thane (pincode 421102), Maharashtra, and is registered on MahaRERA as P51700003336, per GharKundli's check of MahaRERA records.
How many homes are in LA PROMENADE BAYWALK?
According to GharKundli's check of MahaRERA records (updated October 2026), LA PROMENADE BAYWALK has 140 homes in 1 tower registered on MahaRERA, and 69% of them are sold or booked.
When was LA PROMENADE BAYWALK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LA PROMENADE BAYWALK was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on LA PROMENADE BAYWALK?
1 court case is listed for LA PROMENADE BAYWALK on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of LA PROMENADE BAYWALK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AADI DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of LA PROMENADE BAYWALK
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan
- TANISHQ
- SHREE GAJANAN FORTUNE CITY
- SHANKAR PRASAD PARADISE
- Seasons Mannat
- OM ENCLAVE
- OM SAMAPRIYA COMPLEX BLDG.NO-1
- TRIMURTI GARDEN
- ASHWATHI HEIGHTS
Other projects by AADI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.