FENNEL G
by ROYALE URBANSPACE LLP · Shahapur, Thane
Possession date of FENNEL G: 30 April 2027, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700013833, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 7 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about FENNEL G?
How the possession date of FENNEL G has moved
30 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025970)
Reason the builder gave MahaRERA:
“We humbly submit this application seeking an extension of the completion timeline for the Below is a synopsis of the challenges encountered and the reasons project named FENNEL G necessitating this request Cash Flow Challenges: Despite comp…” Read the full reason
“We humbly submit this application seeking an extension of the completion timeline for the Below is a synopsis of the challenges encountered and the reasons project named FENNEL G necessitating this request Cash Flow Challenges: Despite completing RCC work and starting finishing work, the inflow of funds from both existing and new bookings dwindled. Many customers in the Shahapur vicinity were declared NPAs, leading major banks to hait home loans for buyers reasons such as inadequate road maintenance and connectivity issues, further delaying or denying loans. Banks also in the area. Ba cited…”31 December 2026
Extended at the builder's request (MahaRERA application EA20122518874)
Reason the builder gave MahaRERA:
“The Project land requires a proper approach road for movement of construction material, labour, machinery, equipment, and for other related access. The said approach road passes through adjoining land bearing Ghat No. 294 (part). To ensure…” Read the full reason
“The Project land requires a proper approach road for movement of construction material, labour, machinery, equipment, and for other related access. The said approach road passes through adjoining land bearing Ghat No. 294 (part). To ensure lawful access, we executed a Right of Way Agreement on 20/01/2012 with the concerned adjoining landholders at an early stage. Pursuant to the said agreement, we had already started using and developing the access road peacefully and without obstruction for construction-related activities till or around February 2025. Intervention by Authorities and Tempor…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: FENNEL G’s extension records on MahaRERA (P51700013833), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on FENNEL G
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- MahaRERA registration
- P51700013833
- Status
- Registered and active
- Builder
- ROYALE URBANSPACE LLP
- Location
- Shahapur, Thane · 421601
- Project type
- Residential / Group Housing
- Registered on
- 27 Oct 2017
- Completion date at registration
- December 2024
- Latest completion date
- April 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 136
- Sold or booked
- 91%
- Towers
- 1
- Complaints on MahaRERA
- 7
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of FENNEL G, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| FENNEL G | 100% | 100% | 85% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- FENNEL G: covers Ground + 7 Upper Floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on FENNEL G every month.
FENNEL G: buildings, flats and land, as filed on MahaRERA
- Buildings: FENNEL G (8 floors, 136 units)
- Land: 554 sq m (about 0.1 acres) · sanctioned built-up 4,259 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Royale Urbanspace (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late). 10 complaints on MahaRERA across 3 projects.
Read Google reviews of FENNEL G →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
FENNEL G: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about FENNEL G
What is the possession date of FENNEL G?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for FENNEL G in Shahapur, Thane is 30 April 2027 — 24 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for FENNEL G?
Builders and listing sites often quote an earlier "target" date for handover. The completion date FENNEL G's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of FENNEL G extended?
According to GharKundli's check of MahaRERA records (updated October 2026), FENNEL G's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "We humbly submit this application seeking an extension of the completion timeline for the Below is a synopsis of the challenges encountered and the reasons project named FENNEL G necessitating this request Cash Flow Challenges: Despite completing RCC work and starting finishing work, the inflow of funds from both existing and new bookings dwindled. Many customers in the Shahapur vicinity were declared NPAs, leading major banks to hait home loans for buyers reasons such as inadequate road maintenance and connectivity issues, further delaying or denying loans. Banks also in the area. Ba cited…"; to 31 December 2026, giving the reason "The Project land requires a proper approach road for movement of construction material, labour, machinery, equipment, and for other related access. The said approach road passes through adjoining land bearing Ghat No. 294 (part). To ensure lawful access, we executed a Right of Way Agreement on 20/01/2012 with the concerned adjoining landholders at an early stage. Pursuant to the said agreement, we had already started using and developing the access road peacefully and without obstruction for construction-related activities till or around February 2025. Intervention by Authorities and Tempor…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of FENNEL G?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of FENNEL G in Shahapur, Thane is P51700013833.
Is FENNEL G registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), FENNEL G is registered as P51700013833 and its status is "Registered and active".
What is the construction status of FENNEL G?
According to GharKundli's check of MahaRERA records (updated October 2026), FENNEL G's status on MahaRERA is "Registered and active". As filed by the builder, slab work on FENNEL G is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does FENNEL G have complaints on MahaRERA?
7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is FENNEL G safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), FENNEL G is registered on MahaRERA as P51700013833, its completion date has moved 24 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does FENNEL G have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: FENNEL D (P51700005481, possession 31 Dec 2019); FENNEL H (P51700003652, possession 30 Dec 2023). Check that your agreement names the registration of your own wing.
How can I get updates if FENNEL G's possession date changes?
The latest dates are on FENNEL G's MahaRERA page (P51700013833). GharKundli's Kundli Watch sends a free WhatsApp update on FENNEL G every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does FENNEL G have?
According to GharKundli's check of MahaRERA records (updated October 2026), FENNEL G has one building filed: FENNEL G with 8 floors and 136 units.
How big is the land of FENNEL G?
According to GharKundli's check of MahaRERA records (updated October 2026), FENNEL G stands on 554 sq m of land (about 0.1 acres), with 4,259 sq m of sanctioned built-up area.
What is the track record of FENNEL G's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Royale Urbanspace (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late). 10 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of FENNEL G?
Google Maps has reviews of FENNEL G written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is FENNEL G?
FENNEL G by ROYALE URBANSPACE LLP is in Shahapur, Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700013833, per GharKundli's check of MahaRERA records.
How many homes are in FENNEL G?
According to GharKundli's check of MahaRERA records (updated October 2026), FENNEL G has 136 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.
When was FENNEL G registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), FENNEL G was registered on MahaRERA on 27 October 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on FENNEL G?
No court cases are listed for FENNEL G on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of FENNEL G?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ROYALE URBANSPACE LLP, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of FENNEL G
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 421601
- MIRADOR UTSAV PHASE 1
- Aghav Resideny
- CHINTAMANI MEADOWS
- ICON APARTMENT
- Pitruchhaya Apartment
- Visava
- SAI ANAND APARTMENT
- CHINTAMANI HABITAT (FORTUNA BUNGALOW)
Other projects by ROYALE URBANSPACE LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.