Balaji Symphony phase 3

by Vinay Agrawal · Panvel, Thane

Possession date of Balaji Symphony phase 3: 30 October 2028, moved from 30 June 2021 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700000973, and currently active. Its completion date has moved from June 2021 to October 2028: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Balaji Symphony phase 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Balaji Symphony phase 3 has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51700009811)

    Reason the builder gave MahaRERA: “Lack of manpower and supplies due to Covid-19 pandemic to finish construction of Phase III comprising of wings B, C and E.”
  3. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51700013232)

    Reason the builder gave MahaRERA:
    “We declare that the work has been 100% completed and the application for OC has been submitted. We will request you grant us an extension until 30th June 2023 under the Power of Authority to enable us to register the pending agreement of th…” Read the full reason“We declare that the work has been 100% completed and the application for OC has been submitted. We will request you grant us an extension until 30th June 2023 under the Power of Authority to enable us to register the pending agreement of the allottees. We hereby assure you that we will acquire the Occupancy Certificate within the given time.”
  4. 30 June 2028

    Extended at the builder's request (MahaRERA application EXT51700017037)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project order no. 40 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project order no. 40 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19”
  5. 30 October 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Balaji Symphony phase 3’s extension records on MahaRERA (P51700000973), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Balaji Symphony phase 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the October 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700000973
Status
Registered and active
Builder
Vinay Agrawal
Location
Panvel, Thane · 410206
Project type
Residential / Group Housing
Registered on
25 Jul 2017
Completion date at registration
June 2021
Latest completion date
October 2028
Delay so far
84 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
430
Sold or booked
100%
Towers
3
Complaints on MahaRERA
3
Court cases listed
0
Appeals at the tribunal
1
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Balaji Symphony phase 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing B100%100%100%100%
Wing C100%100%100%100%
Wing E100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Wing B: covers 2 Basement + Stilth + 4 Podium + 29 Upper Floors
  • Wing C: covers 2 Basement + Stilth + 4 Podium + 29 Upper Floors
  • Wing E: covers 2 Basement + Stilth + 4 Podium + 29 Upper Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Balaji Symphony phase 3 every month.

Balaji Symphony phase 3: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing B (36 floors, 145 units) · Wing C (36 floors, 116 units) · Wing E (36 floors, 169 units)
  • Land: 6,679 sq m (about 1.7 acres) · sanctioned built-up 25,963 sq m · recreational space 2,773 sq m

The builder’s record and reviews

Vinay Agrawal has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 7 months); 2 still being built, 1 past the promised date (typically 48 months late). 69 complaints on MahaRERA across 3 projects.

Read Google reviews of Balaji Symphony phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Balaji Symphony phase 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Balaji Symphony phase 3

What is the possession date of Balaji Symphony phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Balaji Symphony phase 3 in Panvel, Thane is 30 October 2028 — 84 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Balaji Symphony phase 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Balaji Symphony phase 3's builder has filed on MahaRERA, the official one, is 30 October 2028, already 84 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Balaji Symphony phase 3 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Symphony phase 3's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "Lack of manpower and supplies due to Covid-19 pandemic to finish construction of Phase III comprising of wings B, C and E."; to 30 June 2023, giving the reason "We declare that the work has been 100% completed and the application for OC has been submitted. We will request you grant us an extension until 30th June 2023 under the Power of Authority to enable us to register the pending agreement of the allottees. We hereby assure you that we will acquire the Occupancy Certificate within the given time."; to 30 June 2028, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project order no. 40 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Balaji Symphony phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Balaji Symphony phase 3 in Panvel, Thane is P51700000973.

Is Balaji Symphony phase 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Symphony phase 3 is registered as P51700000973 and its status is "Registered and active".

What is the construction status of Balaji Symphony phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Symphony phase 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Balaji Symphony phase 3 have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Balaji Symphony phase 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Symphony phase 3 is registered on MahaRERA as P51700000973, its completion date has moved 84 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Balaji Symphony phase 3 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Balaji Symphony (P52000001043, possession 31 Dec 2018); Balaji Symphony phase 2 (P52000000754, possession 30 Dec 2020); Balaji Symphony phase 4 (P52000029849, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.

How can I get updates if Balaji Symphony phase 3's possession date changes?

The latest dates are on Balaji Symphony phase 3's MahaRERA page (P51700000973). GharKundli's Kundli Watch sends a free WhatsApp update on Balaji Symphony phase 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Balaji Symphony phase 3 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Symphony phase 3 has 3 buildings filed: Wing B with 36 floors and 145 units; Wing C with 36 floors and 116 units; Wing E with 36 floors and 169 units.

How big is the land of Balaji Symphony phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Symphony phase 3 stands on 6,679 sq m of land (about 1.7 acres), with 25,963 sq m of sanctioned built-up area and 2,773 sq m of recreational open space.

What is the track record of Balaji Symphony phase 3's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vinay Agrawal has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 7 months); 2 still being built, 1 past the promised date (typically 48 months late). 69 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Balaji Symphony phase 3?

Google Maps has reviews of Balaji Symphony phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Balaji Symphony phase 3?

Balaji Symphony phase 3 by Vinay Agrawal is in Panvel, Thane (pincode 410206), Maharashtra, and is registered on MahaRERA as P51700000973, per GharKundli's check of MahaRERA records.

How many homes are in Balaji Symphony phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Symphony phase 3 has 430 homes in 3 towers registered on MahaRERA, and 100% of them are sold or booked.

When was Balaji Symphony phase 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Symphony phase 3 was registered on MahaRERA on 25 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Balaji Symphony phase 3?

No court cases are listed for Balaji Symphony phase 3 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Balaji Symphony phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Vinay Agrawal, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2028 in Raigad →

Other projects in pincode 410206

All 2,664 projects in Panvel (410206) →

Other projects by Vinay Agrawal

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.