by ROYALE URBANSPACE · Shahapur, Thane

Possession: TULIP P is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700011815. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about TULIP P?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on TULIP P

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

  • TULIP NP51700011791 · possession 31 Dec 2019
MahaRERA registration
P51700011815
Status
Completed
Builder
ROYALE URBANSPACE
Location
Shahapur, Thane · 421601
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2019
Homes
52
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of TULIP P, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TULIP P3100%100%30%0%
TULIP P4100%100%30%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TULIP P every month.

TULIP P: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Royale Urbanspace (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late). 10 complaints on MahaRERA across 3 projects.

Read Google reviews of TULIP P →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TULIP P: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TULIP P

What is the possession date of TULIP P?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TULIP P in Shahapur, Thane is 31 December 2019.

Is the builder's possession date different from the MahaRERA date for TULIP P?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TULIP P's builder has filed on MahaRERA, the official one, is 31 December 2019, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of TULIP P?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TULIP P in Shahapur, Thane is P51700011815.

Is TULIP P registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP P is registered as P51700011815 and its status is "Completed".

What is the construction status of TULIP P?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP P's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does TULIP P have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is TULIP P safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP P is registered on MahaRERA as P51700011815, its MahaRERA status is "Completed", its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does TULIP P have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: TULIP N (P51700011791, possession 31 Dec 2019). Check that your agreement names the registration of your own wing.

How can I get updates if TULIP P's possession date changes?

The latest dates are on TULIP P's MahaRERA page (P51700011815). GharKundli's Kundli Watch sends a free WhatsApp update on TULIP P every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TULIP P have?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP P has 2 buildings filed: TULIP P3 with 6 floors; TULIP P4 with 6 floors.

How big is the land of TULIP P?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP P stands on 370 sq m of land (about 0.1 acres), with 1,598 sq m of sanctioned built-up area.

What is the track record of TULIP P's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Urbanspace (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 6 months late). 10 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of TULIP P?

Google Maps has reviews of TULIP P written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TULIP P?

TULIP P by ROYALE URBANSPACE is in Shahapur, Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700011815, per GharKundli's check of MahaRERA records.

How many homes are in TULIP P?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP P has 52 homes in 2 towers registered on MahaRERA.

When was TULIP P registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TULIP P was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on TULIP P?

No court cases are listed for TULIP P on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of TULIP P?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ROYALE URBANSPACE, which has 3 other projects registered on MahaRERA.

Other projects in pincode 421601

All 184 projects in Shahapur (421601) →

Other projects by ROYALE URBANSPACE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.