by DARVESH PROPERTIES PRIVATE LIMITED · Near Dahisar Check Naka Mira Road East, ThaneAlso near Mahajanwadi

Possession date of Westin Darvesh Horizon: 31 December 2025, moved from 30 June 2021 (54 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700005672. Status: Lapsed (registration period ended). 25 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Westin Darvesh Horizon?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Westin Darvesh Horizon has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51700009888)

    Reason the builder gave MahaRERA:
    “Dear Sir, I/We the Promoters of the Project name Darvesh Horizon registered under project registration no P51700005672. We are thankful to the MahaRERA Authority for giving a six months extension because of Covid 19 to our project which was…” Read the full reason“Dear Sir, I/We the Promoters of the Project name Darvesh Horizon registered under project registration no P51700005672. We are thankful to the MahaRERA Authority for giving a six months extension because of Covid 19 to our project which was valid till 30th June 2021. We would like to bring to your notice that our project is 70% completed. Apart from Co-Promoter’s apartment/units and MMRDA Rehab building, we have a total of 218 apartments ,12 offices (10 & 2), 11 side shops, 6 front shops ( 5 & 1 part ) out of that 145 apartments are sold, 6 offices (5 & 1 part), 11 side shops, 6 front shops…”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700013346)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2025”

Source: Westin Darvesh Horizon’s extension records on MahaRERA (P51700005672), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Westin Darvesh Horizon

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 25 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700005672
Status
Lapsed (registration period ended)
Builder
DARVESH PROPERTIES PRIVATE LIMITED
Location
Near Dahisar Check Naka Mira Road East, Thane · 401104
Project type
Others
Registered on
11 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2025
Delay so far
54 months
Homes
669
Towers
4
Complaints on MahaRERA
25
Court cases listed
0
Appeals at the tribunal
13
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Westin Darvesh Horizon, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1100%40%1%2%
BUILDING NO 2100%30%1%2%
BUILDING NO 3100%63%21%2%
MMRDA100%100%90%10%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Westin Darvesh Horizon every month.

Westin Darvesh Horizon: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 1 (25 floors) · BUILDING NO 2 (22 floors) · BUILDING NO 3 (26 floors) · MMRDA (24 floors)
  • Land: 9,863 sq m (about 2.4 acres) · sanctioned built-up 29,383 sq m · recreational space 874 sq m
  • Boundaries filed include: W E HIGHWAY, PENKAR PADA ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Darvesh Properties (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 lapsed. 27 complaints on MahaRERA across 2 projects.

Read Google reviews of Westin Darvesh Horizon →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Westin Darvesh Horizon: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Westin Darvesh Horizon

What is the possession date of Westin Darvesh Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Westin Darvesh Horizon in Near Dahisar Check Naka Mira Road East, Thane is 31 December 2025 — 54 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Westin Darvesh Horizon?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Westin Darvesh Horizon's builder has filed on MahaRERA, the official one, is 31 December 2025, already 54 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Westin Darvesh Horizon extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Westin Darvesh Horizon's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2022, giving the reason "Dear Sir, I/We the Promoters of the Project name Darvesh Horizon registered under project registration no P51700005672. We are thankful to the MahaRERA Authority for giving a six months extension because of Covid 19 to our project which was valid till 30th June 2021. We would like to bring to your notice that our project is 70% completed. Apart from Co-Promoter’s apartment/units and MMRDA Rehab building, we have a total of 218 apartments ,12 offices (10 & 2), 11 side shops, 6 front shops ( 5 & 1 part ) out of that 145 apartments are sold, 6 offices (5 & 1 part), 11 side shops, 6 front shops…"; to 31 December 2025, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2025".

What is the RERA number of Westin Darvesh Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Westin Darvesh Horizon in Near Dahisar Check Naka Mira Road East, Thane is P51700005672.

Is Westin Darvesh Horizon registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Westin Darvesh Horizon is registered as P51700005672 and its status is "Lapsed (registration period ended)".

What is the construction status of Westin Darvesh Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), Westin Darvesh Horizon's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 30% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Westin Darvesh Horizon have complaints on MahaRERA?

25 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Westin Darvesh Horizon safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Westin Darvesh Horizon is registered on MahaRERA as P51700005672, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and 25 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Westin Darvesh Horizon's possession date changes?

The latest dates are on Westin Darvesh Horizon's MahaRERA page (P51700005672). GharKundli's Kundli Watch sends a free WhatsApp update on Westin Darvesh Horizon every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Westin Darvesh Horizon have?

According to GharKundli's check of MahaRERA records (updated November 2026), Westin Darvesh Horizon has 4 buildings filed: BUILDING NO 1 with 25 floors; BUILDING NO 2 with 22 floors; BUILDING NO 3 with 26 floors; MMRDA with 24 floors.

How big is the land of Westin Darvesh Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), Westin Darvesh Horizon stands on 9,863 sq m of land (about 2.4 acres), with 29,383 sq m of sanctioned built-up area and 874 sq m of recreational open space.

What is the track record of Westin Darvesh Horizon's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Darvesh Properties (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 lapsed. 27 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Westin Darvesh Horizon?

Google Maps has reviews of Westin Darvesh Horizon written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 25 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Westin Darvesh Horizon?

Westin Darvesh Horizon by DARVESH PROPERTIES PRIVATE LIMITED is in Near Dahisar Check Naka Mira Road East, Thane (pincode 401104), near Mahajanwadi, Maharashtra, and is registered on MahaRERA as P51700005672, per GharKundli's check of MahaRERA records. Its boundaries filed there include W E HIGHWAY, PENKAR PADA ROAD.

How many homes are in Westin Darvesh Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), Westin Darvesh Horizon has 669 homes in 4 towers registered on MahaRERA.

When was Westin Darvesh Horizon registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Westin Darvesh Horizon was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Westin Darvesh Horizon?

No court cases are listed for Westin Darvesh Horizon on MahaRERA, and 13 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Westin Darvesh Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DARVESH PROPERTIES PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.

Other projects in Thane

Other projects by DARVESH PROPERTIES PRIVATE LIMITED

All Thane projects with no pincode on MahaRERA →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.