IRA PEARL
by RONAK BUILDERS & DEVELOPERS · Nerul, ThaneAlso near L&T Seawoods, Ballard Estate
Possession date of IRA PEARL: 31 January 2026, moved from 2 December 2021 (49 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700005549. Status: Lapsed (registration period ended). 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (January 2026) has passed.
What do you want to know about IRA PEARL?
How the possession date of IRA PEARL has moved
2 December 2021
Completion date given when the project was registered
31 January 2026
Extended at the builder's request (MahaRERA application EXT51700019111)
Reason the builder gave MahaRERA:
“Approvals pertaining to project were delayed, hence causing delay in the said project. Also, the project was significantly affected by the COVID-19 pandemic, including lockdowns, supply chain disruptions, labor shortages, and financial chal…” Read the full reason
“Approvals pertaining to project were delayed, hence causing delay in the said project. Also, the project was significantly affected by the COVID-19 pandemic, including lockdowns, supply chain disruptions, labor shortages, and financial challenges. I being the promoter of said project, most respectfully submit that I have discussed the issues causing delay of the project with the Allottees and have acquired 73.33% i.e more than 51.00% of consent from the Allottees and hence applying for extension of the project u/s 7(3). Same has been attached in the application.”
Source: IRA PEARL’s extension records on MahaRERA (P51700005549), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on IRA PEARL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints and 3 court cases, and how it ended
- Construction pace against the January 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700005549
- Status
- Lapsed (registration period ended)
- Builder
- RONAK BUILDERS & DEVELOPERS
- Location
- Nerul, Thane · 400706
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- January 2026
- Delay so far
- 49 months
- Homes
- 23
- Sold or booked
- 70%
- Towers
- 1
- Complaints on MahaRERA
- 6
- Court cases listed
- 3
- Appeals at the tribunal
- 3
- Title report on file
- Not found
Construction progress of IRA PEARL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Ira Pearl | 100% | 70% | 70% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- Ira Pearl: covers 18 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on IRA PEARL every month.
IRA PEARL: buildings, flats and land, as filed on MahaRERA
- Buildings: Ira Pearl (22 floors, 23 units)
- Car parking: 3 covered
- Land: 1,275 sq m (about 0.3 acres) · sanctioned built-up 1,275 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of IRA PEARL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
IRA PEARL: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about IRA PEARL
What is the possession date of IRA PEARL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for IRA PEARL in Nerul, Thane is 31 January 2026 — 49 months later than 2 December 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for IRA PEARL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date IRA PEARL's builder has filed on MahaRERA, the official one, is 31 January 2026, already 49 months later than the 2 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of IRA PEARL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), IRA PEARL's builder applied to MahaRERA to extend the completion date once: to 31 January 2026, giving the reason "Approvals pertaining to project were delayed, hence causing delay in the said project. Also, the project was significantly affected by the COVID-19 pandemic, including lockdowns, supply chain disruptions, labor shortages, and financial challenges. I being the promoter of said project, most respectfully submit that I have discussed the issues causing delay of the project with the Allottees and have acquired 73.33% i.e more than 51.00% of consent from the Allottees and hence applying for extension of the project u/s 7(3). Same has been attached in the application.".
What is the RERA number of IRA PEARL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of IRA PEARL in Nerul, Thane is P51700005549.
Is IRA PEARL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), IRA PEARL is registered as P51700005549 and its status is "Lapsed (registration period ended)".
What is the construction status of IRA PEARL?
According to GharKundli's check of MahaRERA records (updated October 2026), IRA PEARL's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Ira Pearl is 70% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does IRA PEARL have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is IRA PEARL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), IRA PEARL is registered on MahaRERA as P51700005549, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 49 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if IRA PEARL's possession date changes?
The latest dates are on IRA PEARL's MahaRERA page (P51700005549). GharKundli's Kundli Watch sends a free WhatsApp update on IRA PEARL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does IRA PEARL have?
According to GharKundli's check of MahaRERA records (updated October 2026), IRA PEARL has one building filed: Ira Pearl with 22 floors and 23 units.
How much parking does IRA PEARL have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 3 covered car parking spaces for IRA PEARL.
How big is the land of IRA PEARL?
According to GharKundli's check of MahaRERA records (updated October 2026), IRA PEARL stands on 1,275 sq m of land (about 0.3 acres), with 1,275 sq m of sanctioned built-up area.
Where can I read reviews of IRA PEARL?
Google Maps has reviews of IRA PEARL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is IRA PEARL?
IRA PEARL by RONAK BUILDERS & DEVELOPERS is in Nerul, Thane (pincode 400706), near L&T Seawoods, Ballard Estate, Maharashtra, and is registered on MahaRERA as P51700005549, per GharKundli's check of MahaRERA records.
How many homes are in IRA PEARL?
According to GharKundli's check of MahaRERA records (updated October 2026), IRA PEARL has 23 homes in 1 tower registered on MahaRERA, and 70% of them are sold or booked.
When was IRA PEARL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), IRA PEARL was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on IRA PEARL?
3 court cases are listed for IRA PEARL on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of IRA PEARL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RONAK BUILDERS & DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of IRA PEARL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in pincode 400706
- CYBER CODE
- DELTA STELLAR
- PLATINUM ELYSIUM
- GURUKRUPA NITYAM
- E.V.Paradise
- SAI WORLD PYRAMID COMMERCIAL
- Sai World One Residential
- Astha Avana
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.