OM SHIV SAMARTH CHS
by SHREE SAIBABA CONSTRUCTIONS PRIVATE LIMITED · Mulund West, Thane
Possession date of OM SHIV SAMARTH CHS: 31 August 2022, moved from 31 December 2019 (32 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700012275. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (August 2022) has passed.
What do you want to know about OM SHIV SAMARTH CHS?
How the possession date of OM SHIV SAMARTH CHS has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51700003683)
Reason the builder gave MahaRERA: “We hereby attached the copy of Commencement Certificate and letter for reasons of delay.”
31 August 2022
Extended at the builder's request (MahaRERA application EXT51700010388)
Reason the builder gave MahaRERA:
“The project consist two buildings. i.e. one for Rehab and second for Sale. Rehab Building work is done and we are going to apply for O. C. within 15-20 days. Our Sale building work is done upto 80 % approx., After O.C. of Rehab building we…” Read the full reason
“The project consist two buildings. i.e. one for Rehab and second for Sale. Rehab Building work is done and we are going to apply for O. C. within 15-20 days. Our Sale building work is done upto 80 % approx., After O.C. of Rehab building we will the Sale Blddg. C.C. endorsed, and due to Covid 19 lockdowns by Governments at varours times and as per our earlier letters 13/11/2019 and 15/06/2021”
Source: OM SHIV SAMARTH CHS’s extension records on MahaRERA (P51700012275), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on OM SHIV SAMARTH CHS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the August 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700012275
- Status
- Lapsed (registration period ended)
- Builder
- SHREE SAIBABA CONSTRUCTIONS PRIVATE LIMITED
- Location
- Mulund West, Thane · 400602
- Project type
- Others
- Registered on
- 1 Sep 2017
- Completion date at registration
- December 2019
- Latest completion date
- August 2022
- Delay so far
- 32 months
- Homes
- 203
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of OM SHIV SAMARTH CHS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OM SHIV SAMARTH CHS | 100% | 100% | 100% | 100% |
| PANCHPAKHADI JEWEL | 100% | 87% | 86% | 45% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on OM SHIV SAMARTH CHS every month.
OM SHIV SAMARTH CHS: buildings, flats and land, as filed on MahaRERA
- Buildings: OM SHIV SAMARTH CHS (20 floors) · PANCHPAKHADI JEWEL (29 floors)
- Land: 2,724 sq m (about 0.7 acres) · sanctioned built-up 6,665 sq m · recreational space 908 sq m
The builder’s record and reviews
Shree Saibaba Grihanirmiti (a group of 2 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 23 months); 3 lapsed. 5 complaints on MahaRERA across 5 projects.
Read Google reviews of OM SHIV SAMARTH CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
OM SHIV SAMARTH CHS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about OM SHIV SAMARTH CHS
What is the possession date of OM SHIV SAMARTH CHS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for OM SHIV SAMARTH CHS in Mulund West, Thane is 31 August 2022 — 32 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for OM SHIV SAMARTH CHS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date OM SHIV SAMARTH CHS's builder has filed on MahaRERA, the official one, is 31 August 2022, already 32 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of OM SHIV SAMARTH CHS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SHIV SAMARTH CHS's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "We hereby attached the copy of Commencement Certificate and letter for reasons of delay."; to 31 August 2022, giving the reason "The project consist two buildings. i.e. one for Rehab and second for Sale. Rehab Building work is done and we are going to apply for O. C. within 15-20 days. Our Sale building work is done upto 80 % approx., After O.C. of Rehab building we will the Sale Blddg. C.C. endorsed, and due to Covid 19 lockdowns by Governments at varours times and as per our earlier letters 13/11/2019 and 15/06/2021".
What is the RERA number of OM SHIV SAMARTH CHS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of OM SHIV SAMARTH CHS in Mulund West, Thane is P51700012275.
Is OM SHIV SAMARTH CHS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SHIV SAMARTH CHS is registered as P51700012275 and its status is "Lapsed (registration period ended)".
What is the construction status of OM SHIV SAMARTH CHS?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SHIV SAMARTH CHS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 87% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does OM SHIV SAMARTH CHS have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is OM SHIV SAMARTH CHS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SHIV SAMARTH CHS is registered on MahaRERA as P51700012275, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 32 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if OM SHIV SAMARTH CHS's possession date changes?
The latest dates are on OM SHIV SAMARTH CHS's MahaRERA page (P51700012275). GharKundli's Kundli Watch sends a free WhatsApp update on OM SHIV SAMARTH CHS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does OM SHIV SAMARTH CHS have?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SHIV SAMARTH CHS has 2 buildings filed: OM SHIV SAMARTH CHS with 20 floors; PANCHPAKHADI JEWEL with 29 floors.
How big is the land of OM SHIV SAMARTH CHS?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SHIV SAMARTH CHS stands on 2,724 sq m of land (about 0.7 acres), with 6,665 sq m of sanctioned built-up area and 908 sq m of recreational open space.
What is the track record of OM SHIV SAMARTH CHS's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Saibaba Grihanirmiti (a group of 2 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 23 months); 3 lapsed. 5 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of OM SHIV SAMARTH CHS?
Google Maps has reviews of OM SHIV SAMARTH CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is OM SHIV SAMARTH CHS?
OM SHIV SAMARTH CHS by SHREE SAIBABA CONSTRUCTIONS PRIVATE LIMITED is in Mulund West, Thane (pincode 400602), Maharashtra, and is registered on MahaRERA as P51700012275, per GharKundli's check of MahaRERA records.
How many homes are in OM SHIV SAMARTH CHS?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SHIV SAMARTH CHS has 203 homes in 2 towers registered on MahaRERA.
When was OM SHIV SAMARTH CHS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SHIV SAMARTH CHS was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on OM SHIV SAMARTH CHS?
No court cases are listed for OM SHIV SAMARTH CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of OM SHIV SAMARTH CHS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE SAIBABA CONSTRUCTIONS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of OM SHIV SAMARTH CHS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulund West
- NAHUR GAONTHAN SHIV SHAKTI CHS LTD
- AXIOM GLORIA
- SHRADDHA PRIVA
- Ace and Matchpoint
- AAI SATIDEVI PARADISE
- KULDEEP-ISHCHHAYA CHS LTD
- THE ELITE
- GOVIND SOLITAIRE
Other projects by SHREE SAIBABA CONSTRUCTIONS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.