THE ELITE
by R R D HEIGHTS AND BUILDERS PVT LTD (Siddharth) · Mulund West, MumbaiAlso near Bhandup West, Chembur West, Nahur
Possession date of THE ELITE: 30 April 2027, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800005901, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 14 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about THE ELITE?
How the possession date of THE ELITE has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800018635)
Reason the builder gave MahaRERA:
“RCC slab work up-to 42 Floors out of 45 Floors is completed in full and for 43rd, 44th and 45th Floor, part slab work of the building is completed and finishing internal work is in progress of the project, as is evidenced by the latest Form…” Read the full reason
“RCC slab work up-to 42 Floors out of 45 Floors is completed in full and for 43rd, 44th and 45th Floor, part slab work of the building is completed and finishing internal work is in progress of the project, as is evidenced by the latest Form 1 that is Architect Certificate dated 2nd January 2024 submitted for the period of 31st December, 2023. In the light of the same we seek extension of one year for due date of completion of the project up-to 29-Dec-2024. Self Declaration dated 12th January 2024 for extension of due date for the project is attached. Duly notarized Affidavit cum declaration…”31 December 2025
Extended at the builder's request (MahaRERA application EXT51800027524)
Reason the builder gave MahaRERA:
“RCC Work of the slab work is at the stage of completion as evidenced by latest Architect Certificate of 95% completion of slab super structure, Finishing work inside the flats is in progress. Ground + 2 Podiums + amenity floor part work is…” Read the full reason
“RCC Work of the slab work is at the stage of completion as evidenced by latest Architect Certificate of 95% completion of slab super structure, Finishing work inside the flats is in progress. Ground + 2 Podiums + amenity floor part work is completed. Further we have duly attached the duly attached consent in Annexure counter signed and stamped by the promoter. Detailed declaration explaining the reasons for which the project got delayed and timeline of the balance work completion within extended period is attached along-with this application. We have uploaded more than 51% allottees consent…”31 December 2026
Extended at the builder's request (MahaRERA application EA06032620123)
Reason the builder gave MahaRERA:
“RCC Work of the slab work is at the stage of completion, finishing work inside the flats is in progress. Ground + Part Podium work + Amenity floor part work is completed. We have uploaded more than 51% allottees consent in Format B duly cou…” Read the full reason
“RCC Work of the slab work is at the stage of completion, finishing work inside the flats is in progress. Ground + Part Podium work + Amenity floor part work is completed. We have uploaded more than 51% allottees consent in Format B duly counter signed and stamped by promoter on each page. We have complied quarterly compliances of Form 1, Form 2 & Form 3 and notarised affidavit in Form B mentioning the extension date and sold inventory disclosure up-to latest quarter ended 31-12-2025 is attached. In light of completion of the pending work we seek extension up-till 31-Dec-2026.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: THE ELITE’s extension records on MahaRERA (P51800005901), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on THE ELITE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 14 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800005901
- Status
- Registered and active
- Builder
- R R D HEIGHTS AND BUILDERS PVT LTD
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 213
- Sold or booked
- 94%
- Towers
- 2
- Complaints on MahaRERA
- 14
- Court cases listed
- 0
- Appeals at the tribunal
- 13
- Title report on file
- Not found
Construction progress of THE ELITE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| THE ELITE - A WING | 100% | 95% | 80% | 10% |
| THE ELITE - B WING | 100% | 95% | 80% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- THE ELITE - A WING: covers 42 floors
- THE ELITE - B WING: covers 42 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE ELITE every month.
THE ELITE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 902 | 112 |
| 3 BHK | 1,363 – 1,812 | 81 |
| 5 BHK | 2,644 | 16 |
| Duplex | 1,781 – 4,872 | 3 |
| Office Space | 222 | 2 |
| 4 BHK | 1,676 | 1 |
- Buildings: THE ELITE - A WING (49 floors, 109 units) · THE ELITE - B WING (49 floors, 106 units)
- Land: 7,179 sq m (about 1.8 acres) · sanctioned built-up 19,768 sq m · recreational space 1,850 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Tridev Realty & Construction (a group of 7 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 12 still being built, 9 past the promised date (typically 22 months late); 1 lapsed. 37 complaints on MahaRERA across 6 projects.
Read Google reviews of THE ELITE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
THE ELITE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about THE ELITE
What is the possession date of THE ELITE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE ELITE in Mulund West, Mumbai is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for THE ELITE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date THE ELITE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of THE ELITE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ELITE's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "RCC slab work up-to 42 Floors out of 45 Floors is completed in full and for 43rd, 44th and 45th Floor, part slab work of the building is completed and finishing internal work is in progress of the project, as is evidenced by the latest Form 1 that is Architect Certificate dated 2nd January 2024 submitted for the period of 31st December, 2023. In the light of the same we seek extension of one year for due date of completion of the project up-to 29-Dec-2024. Self Declaration dated 12th January 2024 for extension of due date for the project is attached. Duly notarized Affidavit cum declaration…"; to 31 December 2025, giving the reason "RCC Work of the slab work is at the stage of completion as evidenced by latest Architect Certificate of 95% completion of slab super structure, Finishing work inside the flats is in progress. Ground + 2 Podiums + amenity floor part work is completed. Further we have duly attached the duly attached consent in Annexure counter signed and stamped by the promoter. Detailed declaration explaining the reasons for which the project got delayed and timeline of the balance work completion within extended period is attached along-with this application. We have uploaded more than 51% allottees consent…"; to 31 December 2026, giving the reason "RCC Work of the slab work is at the stage of completion, finishing work inside the flats is in progress. Ground + Part Podium work + Amenity floor part work is completed. We have uploaded more than 51% allottees consent in Format B duly counter signed and stamped by promoter on each page. We have complied quarterly compliances of Form 1, Form 2 & Form 3 and notarised affidavit in Form B mentioning the extension date and sold inventory disclosure up-to latest quarter ended 31-12-2025 is attached. In light of completion of the pending work we seek extension up-till 31-Dec-2026.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of THE ELITE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE ELITE in Mulund West, Mumbai is P51800005901.
Is THE ELITE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ELITE is registered as P51800005901 and its status is "Registered and active".
What is the construction status of THE ELITE?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ELITE's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 95% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does THE ELITE have complaints on MahaRERA?
14 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is THE ELITE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ELITE is registered on MahaRERA as P51800005901, its completion date has moved 36 months since registration and 14 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if THE ELITE's possession date changes?
The latest dates are on THE ELITE's MahaRERA page (P51800005901). GharKundli's Kundli Watch sends a free WhatsApp update on THE ELITE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does THE ELITE have?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ELITE has 2 buildings filed: THE ELITE - A WING with 49 floors and 109 units; THE ELITE - B WING with 49 floors and 106 units.
What are the flat sizes (carpet area) in THE ELITE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for THE ELITE: 2 BHK: 902 sq ft carpet (112 homes); 3 BHK: 1363 to 1812 sq ft carpet (81 homes); 5 BHK: 2644 sq ft carpet (16 homes); Duplex: 1781 to 4872 sq ft carpet (3 homes); 4 BHK: 1676 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of THE ELITE?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ELITE stands on 7,179 sq m of land (about 1.8 acres), with 19,768 sq m of sanctioned built-up area and 1,850 sq m of recreational open space.
What is the track record of THE ELITE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Realty & Construction (a group of 7 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 12 still being built, 9 past the promised date (typically 22 months late); 1 lapsed. 37 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of THE ELITE?
Google Maps has reviews of THE ELITE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 14 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is THE ELITE?
THE ELITE by R R D HEIGHTS AND BUILDERS PVT LTD (Siddharth) is in Mulund West, Mumbai (pincode 400080), near Bhandup West, Chembur West, Nahur, Maharashtra, and is registered on MahaRERA as P51800005901, per GharKundli's check of MahaRERA records.
How many homes are in THE ELITE?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ELITE has 213 homes in 2 towers registered on MahaRERA, and 94% of them are sold or booked.
When was THE ELITE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ELITE was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on THE ELITE?
No court cases are listed for THE ELITE on MahaRERA, and 13 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of THE ELITE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is R R D HEIGHTS AND BUILDERS PVT LTD, the company Siddharth files this project under.
Check it yourself on MahaRERA
- How to check the possession date of THE ELITE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400080
- OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.
- Keshavpada
- ARIHANT ROYALE
- THE SANCTUARY - TOWER 5
- Dhanraj Tower
- Madhuvan Nivanta
- Shraddha Paradise Enclave
- Malhar Guide
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.