JOLLLY APARTMENT WING A AND B

by RIEL INFRASTRUCTURE PVT LTD · Asan Gaon East, Thane

Possession: JOLLLY APARTMENT WING A AND B is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700010153. Status: Completed. 9 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about JOLLLY APARTMENT WING A AND B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of JOLLLY APARTMENT WING A AND B has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 June 2021

    Extended at the builder's request (MahaRERA application EXT51700008591)

    Reason the builder gave MahaRERA: “SHORTAGE OF MANPOWER AND MATERIAL”
  3. 30 December 2021

    Revised completion date on MahaRERA

Source: JOLLLY APARTMENT WING A AND B’s extension records on MahaRERA (P51700010153), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on JOLLLY APARTMENT WING A AND B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 complaints, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700010153
Status
Completed
Builder
RIEL INFRASTRUCTURE PVT LTD
Location
Asan Gaon East, Thane · 421601
Project type
Residential / Group Housing
Registered on
24 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2021
Delay so far
24 months
Homes
40
Towers
2
Complaints on MahaRERA
9
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of JOLLLY APARTMENT WING A AND B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
JOLLY APARTMENT A WING100%100%100%100%
JOLLY APARTMENT B WING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on JOLLLY APARTMENT WING A AND B every month.

JOLLLY APARTMENT WING A AND B: buildings, flats and land, as filed on MahaRERA

  • Buildings: JOLLY APARTMENT A WING (5 floors) · JOLLY APARTMENT B WING (5 floors)
  • Land: 4,105 sq m (about 1.0 acres) · sanctioned built-up 3,029 sq m · recreational space 415 sq m

The builder’s record and reviews

Riel Infrastructure has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 23 months); 1 still being built, 1 past the promised date (typically 42 months late). 9 complaints on MahaRERA across 1 project.

Read Google reviews of JOLLLY APARTMENT WING A AND B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

JOLLLY APARTMENT WING A AND B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about JOLLLY APARTMENT WING A AND B

What is the possession date of JOLLLY APARTMENT WING A AND B?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for JOLLLY APARTMENT WING A AND B in Asan Gaon East, Thane is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for JOLLLY APARTMENT WING A AND B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date JOLLLY APARTMENT WING A AND B's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of JOLLLY APARTMENT WING A AND B extended?

According to GharKundli's check of MahaRERA records (updated November 2026), JOLLLY APARTMENT WING A AND B's builder applied to MahaRERA to extend the completion date once: to 30 June 2021, giving the reason "SHORTAGE OF MANPOWER AND MATERIAL".

What is the RERA number of JOLLLY APARTMENT WING A AND B?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of JOLLLY APARTMENT WING A AND B in Asan Gaon East, Thane is P51700010153.

Is JOLLLY APARTMENT WING A AND B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), JOLLLY APARTMENT WING A AND B is registered as P51700010153 and its status is "Completed".

What is the construction status of JOLLLY APARTMENT WING A AND B?

According to GharKundli's check of MahaRERA records (updated November 2026), JOLLLY APARTMENT WING A AND B's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does JOLLLY APARTMENT WING A AND B have complaints on MahaRERA?

9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is JOLLLY APARTMENT WING A AND B safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), JOLLLY APARTMENT WING A AND B is registered on MahaRERA as P51700010153, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if JOLLLY APARTMENT WING A AND B's possession date changes?

The latest dates are on JOLLLY APARTMENT WING A AND B's MahaRERA page (P51700010153). GharKundli's Kundli Watch sends a free WhatsApp update on JOLLLY APARTMENT WING A AND B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does JOLLLY APARTMENT WING A AND B have?

According to GharKundli's check of MahaRERA records (updated November 2026), JOLLLY APARTMENT WING A AND B has 2 buildings filed: JOLLY APARTMENT A WING with 5 floors; JOLLY APARTMENT B WING with 5 floors.

How big is the land of JOLLLY APARTMENT WING A AND B?

According to GharKundli's check of MahaRERA records (updated November 2026), JOLLLY APARTMENT WING A AND B stands on 4,105 sq m of land (about 1.0 acres), with 3,029 sq m of sanctioned built-up area and 415 sq m of recreational open space.

What is the track record of JOLLLY APARTMENT WING A AND B's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Riel Infrastructure has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 23 months); 1 still being built, 1 past the promised date (typically 42 months late). 9 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of JOLLLY APARTMENT WING A AND B?

Google Maps has reviews of JOLLLY APARTMENT WING A AND B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is JOLLLY APARTMENT WING A AND B?

JOLLLY APARTMENT WING A AND B by RIEL INFRASTRUCTURE PVT LTD is in Asan Gaon East, Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700010153, per GharKundli's check of MahaRERA records.

How many homes are in JOLLLY APARTMENT WING A AND B?

According to GharKundli's check of MahaRERA records (updated November 2026), JOLLLY APARTMENT WING A AND B has 40 homes in 2 towers registered on MahaRERA.

When was JOLLLY APARTMENT WING A AND B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), JOLLLY APARTMENT WING A AND B was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on JOLLLY APARTMENT WING A AND B?

No court cases are listed for JOLLLY APARTMENT WING A AND B on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of JOLLLY APARTMENT WING A AND B?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RIEL INFRASTRUCTURE PVT LTD, which has 2 other projects registered on MahaRERA.

Other projects in pincode 421601

All 184 projects in Shahapur (421601) →

Other projects by RIEL INFRASTRUCTURE PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.