Pearls Nature Farm Shahapur Phase I
by PROSPECTIVE EATATE AND REALITY LOGICAL SOLUTIONS PVT LTD · Amboli, Thane 421601
What’s in the report? →Possession date of Pearls Nature Farm Shahapur Phase I (MahaRERA P51700004736): 30 April 2027, moved from 31 March 2019 (93 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700004736, and currently active. Its completion date has moved from March 2019 to April 2027: 93 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700004736, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Pearls Nature Farm Shahapur Phase I?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Pearls Nature Farm Shahapur Phase I has moved
31 March 2019
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT51700016717)
Reason the builder gave MahaRERA: “Covid 19”
31 December 2026
Extended at the builder's request (MahaRERA application EXT51700027298)
Reason the builder gave MahaRERA: “Sale of Plot Pending”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Pearls Nature Farm Shahapur Phase I’s extension records on MahaRERA (P51700004736), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Pearls Nature Farm Shahapur Phase I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700004736
- Status
- Registered and active
- Builder
- PROSPECTIVE EATATE AND REALITY LOGICAL SOLUTIONS PVT LTD
- Location
- Amboli, Thane · 421601
- Project type
- Plotted
- Registered on
- 9 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- April 2027
- Delay so far
- 93 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Pearls Nature Farm Shahapur Phase I: buildings, flats and land, as filed on MahaRERA
- Land: 34,410 sq m (about 8.5 acres) · sanctioned built-up 16,675 sq m · recreational space 4,707 sq m
- Land, as filed: 42/1 42/2 44/1
- Map: Get directions
The builder’s record and reviews
Prospective Eatate AND Reality Logical Solutions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 59 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Pearls Nature Farm Shahapur Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pearls Nature Farm Shahapur Phase I: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Pearls Nature Farm Shahapur Phase I
What is the possession date of Pearls Nature Farm Shahapur Phase I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pearls Nature Farm Shahapur Phase I in Amboli, Thane is 30 April 2027 — 93 months later than 31 March 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 93 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Pearls Nature Farm Shahapur Phase I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pearls Nature Farm Shahapur Phase I's builder has filed on MahaRERA, the official one, is 30 April 2027, already 93 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Pearls Nature Farm Shahapur Phase I extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Pearls Nature Farm Shahapur Phase I's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "Covid 19"; to 31 December 2026, giving the reason "Sale of Plot Pending". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Pearls Nature Farm Shahapur Phase I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pearls Nature Farm Shahapur Phase I in Amboli, Thane is P51700004736.
Is Pearls Nature Farm Shahapur Phase I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pearls Nature Farm Shahapur Phase I is registered as P51700004736 and its status is "Registered and active".
What is the current construction status of Pearls Nature Farm Shahapur Phase I? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Pearls Nature Farm Shahapur Phase I's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does Pearls Nature Farm Shahapur Phase I have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Pearls Nature Farm Shahapur Phase I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Pearls Nature Farm Shahapur Phase I is registered on MahaRERA as P51700004736, its completion date has moved 93 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Pearls Nature Farm Shahapur Phase I?
Pearls Nature Farm Shahapur Phase I is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Pearls Nature Farm Shahapur Phase I?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Pearls Nature Farm Shahapur Phase I: gharkundli.com/tools/property-cost-calculator
Has Pearls Nature Farm Shahapur Phase I received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Pearls Nature Farm Shahapur Phase I is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Pearls Nature Farm Shahapur Phase I uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Pearls Nature Farm Shahapur Phase I was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Pearls Nature Farm Shahapur Phase I's possession date changes?
The latest dates are on Pearls Nature Farm Shahapur Phase I's MahaRERA page (P51700004736). GharKundli's Kundli Watch sends a free WhatsApp update on Pearls Nature Farm Shahapur Phase I every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of Pearls Nature Farm Shahapur Phase I?
According to GharKundli's check of MahaRERA records (updated October 2026), Pearls Nature Farm Shahapur Phase I stands on 34,410 sq m of land (about 8.5 acres), with 16,675 sq m of sanctioned built-up area and 4,707 sq m of recreational open space.
What is the track record of Pearls Nature Farm Shahapur Phase I's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Prospective Eatate AND Reality Logical Solutions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 59 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Pearls Nature Farm Shahapur Phase I?
Google Maps has reviews of Pearls Nature Farm Shahapur Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Pearls Nature Farm Shahapur Phase I?
Pearls Nature Farm Shahapur Phase I by PROSPECTIVE EATATE AND REALITY LOGICAL SOLUTIONS PVT LTD is in Amboli, Thane, pincode 421601, Maharashtra, and is registered on MahaRERA as P51700004736, per GharKundli's check of MahaRERA records. Its land is filed as 42/1 42/2 44/1. GharKundli lists all 184 MahaRERA projects in Shahapur (421601).
When was Pearls Nature Farm Shahapur Phase I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pearls Nature Farm Shahapur Phase I was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Does Pearls Nature Farm Shahapur Phase I have any legal issues or court cases?
No court cases are listed for Pearls Nature Farm Shahapur Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Pearls Nature Farm Shahapur Phase I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PROSPECTIVE EATATE AND REALITY LOGICAL SOLUTIONS PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of Pearls Nature Farm Shahapur Phase I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Shahapur (421601)
- Sai Anand Apartment
- Mirador Utsav Phase 1
- Visava
- Chintamani Habitat (Fortuna Bungalow)
- Chintamani Meadows
- Icon Apartment
- Pitruchhaya Apartment
- Aghav Resideny
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.