Possession date of CROSSVILLA: 30 December 2022, moved from 30 June 2021 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700005885. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2022) has passed.
What do you want to know about CROSSVILLA?
How the possession date of CROSSVILLA has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51700010224)
Reason the builder gave MahaRERA: “The Extension of 1 year is sought due to the delay in approval of the revised plan and also on account of market conditions affected due to COVID -19 pandemic.”
30 December 2022
Revised completion date on MahaRERA
Source: CROSSVILLA’s extension records on MahaRERA (P51700005885), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CROSSVILLA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700005885
- Status
- Lapsed (registration period ended)
- Builder
- SHREEYA ENTERPRISES
- Location
- Kopri, Thane · 400602
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- December 2022
- Delay so far
- 18 months
- Homes
- 70
- Towers
- 2
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of CROSSVILLA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 75% | 8% | 0% |
| B | 100% | 63% | 11% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CROSSVILLA every month.
CROSSVILLA: buildings, flats and land, as filed on MahaRERA
- Buildings: A (9 floors) · B (8 floors)
- Land: 1,447 sq m (about 0.4 acres) · sanctioned built-up 2,062 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of CROSSVILLA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CROSSVILLA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CROSSVILLA
What is the possession date of CROSSVILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CROSSVILLA in Kopri, Thane is 30 December 2022 — 18 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for CROSSVILLA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CROSSVILLA's builder has filed on MahaRERA, the official one, is 30 December 2022, already 18 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CROSSVILLA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), CROSSVILLA's builder applied to MahaRERA to extend the completion date once: to 30 June 2022, giving the reason "The Extension of 1 year is sought due to the delay in approval of the revised plan and also on account of market conditions affected due to COVID -19 pandemic.".
What is the RERA number of CROSSVILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CROSSVILLA in Kopri, Thane is P51700005885.
Is CROSSVILLA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CROSSVILLA is registered as P51700005885 and its status is "Lapsed (registration period ended)".
What is the construction status of CROSSVILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), CROSSVILLA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 63% to 75% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does CROSSVILLA have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is CROSSVILLA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), CROSSVILLA is registered on MahaRERA as P51700005885, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if CROSSVILLA's possession date changes?
The latest dates are on CROSSVILLA's MahaRERA page (P51700005885). GharKundli's Kundli Watch sends a free WhatsApp update on CROSSVILLA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CROSSVILLA have?
According to GharKundli's check of MahaRERA records (updated November 2026), CROSSVILLA has 2 buildings filed: A with 9 floors; B with 8 floors.
How big is the land of CROSSVILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), CROSSVILLA stands on 1,447 sq m of land (about 0.4 acres), with 2,062 sq m of sanctioned built-up area.
Where can I read reviews of CROSSVILLA?
Google Maps has reviews of CROSSVILLA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CROSSVILLA?
CROSSVILLA by SHREEYA ENTERPRISES is in Kopri, Thane (pincode 400602), Maharashtra, and is registered on MahaRERA as P51700005885, per GharKundli's check of MahaRERA records.
How many homes are in CROSSVILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), CROSSVILLA has 70 homes in 2 towers registered on MahaRERA.
When was CROSSVILLA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CROSSVILLA was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on CROSSVILLA?
No court cases are listed for CROSSVILLA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of CROSSVILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREEYA ENTERPRISES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of CROSSVILLA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kopri
- SHALIMAR CO.OP HSG SOC LTD
- DATTA SAMARTH
- SHIVKRUPA CHSL
- SHREE SWAMI SAMARTH NAGAR WING A
- SADHANA SOCIETY
- SHREE SWAMI SAMARTH NAGAR
Other projects by SHREEYA ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.