Possession date of SHALIMAR CO.OP HSG SOC LTD: 30 October 2027, moved from 30 April 2024 (38 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700027861, and currently active. Its completion date has moved from April 2024 to October 2027: 38 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHALIMAR CO.OP HSG SOC LTD?
How the possession date of SHALIMAR CO.OP HSG SOC LTD has moved
30 April 2024
Completion date given when the project was registered
31 May 2026
Extended at the builder's request (MahaRERA application EXT51700019699)
Reason the builder gave MahaRERA: “Dear Sir, We have got approval of Ancillary FSI from the authority, because of that the 13th floor has been extended to 17th floor. Therefore, We need extra time to complete the project.”
30 June 2027
Extended at the builder's request (MahaRERA application EA28052621143)
Reason the builder gave MahaRERA: “Change of Promoter”
30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHALIMAR CO.OP HSG SOC LTD’s extension records on MahaRERA (P51700027861), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHALIMAR CO.OP HSG SOC LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700027861
- Status
- Registered and active
- Builder
- NEENA SHAILESH PARANJAPE
- Location
- Kopri, Thane · 400603
- Project type
- Others
- Registered on
- 10 Jan 2021
- Completion date at registration
- April 2024
- Latest completion date
- October 2027
- Delay so far
- 38 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 24
- Sold or booked
- 47%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
Construction progress of SHALIMAR CO.OP HSG SOC LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHALIMAR CO OP HSG SOC LTD | 100% | 90% | 20% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHALIMAR CO OP HSG SOC LTD: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHALIMAR CO.OP HSG SOC LTD every month.
SHALIMAR CO.OP HSG SOC LTD: buildings, flats and land, as filed on MahaRERA
- Buildings: SHALIMAR CO OP HSG SOC LTD (14 floors, 37 units)
- Land: 914 sq m (about 0.2 acres) · sanctioned built-up 2,167 sq m · recreational space 1,284 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHALIMAR CO.OP HSG SOC LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHALIMAR CO.OP HSG SOC LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHALIMAR CO.OP HSG SOC LTD
What is the possession date of SHALIMAR CO.OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHALIMAR CO.OP HSG SOC LTD in Kopri, Thane is 30 October 2027 — 38 months later than 30 April 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHALIMAR CO.OP HSG SOC LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHALIMAR CO.OP HSG SOC LTD's builder has filed on MahaRERA, the official one, is 30 October 2027, already 38 months later than the 30 April 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHALIMAR CO.OP HSG SOC LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHALIMAR CO.OP HSG SOC LTD's builder applied to MahaRERA to extend the completion date 2 times: to 31 May 2026, giving the reason "Dear Sir, We have got approval of Ancillary FSI from the authority, because of that the 13th floor has been extended to 17th floor. Therefore, We need extra time to complete the project."; to 30 June 2027, giving the reason "Change of Promoter". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SHALIMAR CO.OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHALIMAR CO.OP HSG SOC LTD in Kopri, Thane is P51700027861.
Is SHALIMAR CO.OP HSG SOC LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHALIMAR CO.OP HSG SOC LTD is registered as P51700027861 and its status is "Registered and active".
What is the construction status of SHALIMAR CO.OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), SHALIMAR CO.OP HSG SOC LTD's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHALIMAR CO OP HSG SOC LTD is 90% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.
Does SHALIMAR CO.OP HSG SOC LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SHALIMAR CO.OP HSG SOC LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHALIMAR CO.OP HSG SOC LTD is registered on MahaRERA as P51700027861, its completion date has moved 38 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHALIMAR CO.OP HSG SOC LTD's possession date changes?
The latest dates are on SHALIMAR CO.OP HSG SOC LTD's MahaRERA page (P51700027861). GharKundli's Kundli Watch sends a free WhatsApp update on SHALIMAR CO.OP HSG SOC LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHALIMAR CO.OP HSG SOC LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHALIMAR CO.OP HSG SOC LTD has one building filed: SHALIMAR CO OP HSG SOC LTD with 14 floors and 37 units.
How big is the land of SHALIMAR CO.OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), SHALIMAR CO.OP HSG SOC LTD stands on 914 sq m of land (about 0.2 acres), with 2,167 sq m of sanctioned built-up area and 1,284 sq m of recreational open space.
Where can I read reviews of SHALIMAR CO.OP HSG SOC LTD?
Google Maps has reviews of SHALIMAR CO.OP HSG SOC LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHALIMAR CO.OP HSG SOC LTD?
SHALIMAR CO.OP HSG SOC LTD by NEENA SHAILESH PARANJAPE is in Kopri, Thane (pincode 400603), near Majiwada, Badlapur, Naupada, Maharashtra, and is registered on MahaRERA as P51700027861, per GharKundli's check of MahaRERA records.
How many homes are in SHALIMAR CO.OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), SHALIMAR CO.OP HSG SOC LTD has 24 homes in 1 tower registered on MahaRERA, and 47% of them are sold or booked.
When was SHALIMAR CO.OP HSG SOC LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHALIMAR CO.OP HSG SOC LTD was registered on MahaRERA on 10 January 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on SHALIMAR CO.OP HSG SOC LTD?
3 court cases are listed for SHALIMAR CO.OP HSG SOC LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHALIMAR CO.OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEENA SHAILESH PARANJAPE.
Check it yourself on MahaRERA
- How to check the possession date of SHALIMAR CO.OP HSG SOC LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 400603
- Self-Redevelopment of Jeevan Smriti CHS Ltd.
- ROYAL HEIGHT - Building B
- Gayatri CHS LTD
- Suprabhat C.H.S. Ltd.
- DATTA SAMARTH
- AMAR PUSHPAKUNJ
- SHREYAS CO-OP HSG. SOC. LTD.
- Dinesh Co Op Hsg Society
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.