AMAR PUSHPAKUNJ
by Avighna Redevelopers · Thane East, ThaneAlso near Naupada, Mulund East, Kopri
Possession date of AMAR PUSHPAKUNJ: 30 April 2028, moved from 31 July 2026 (17 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700054590, and currently active. Its completion date has moved from July 2026 to April 2028: 17 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AMAR PUSHPAKUNJ?
How the possession date of AMAR PUSHPAKUNJ has moved
31 July 2026
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA03082622007)
Reason the builder gave MahaRERA:
“Dear Sir/Ma’am, We, Avighna Redevelopers, hereby declare the following with respect to the project “AMAR PUSHPAKUNJ” bearing registration number P51700054590 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform yo…” Read the full reason
“Dear Sir/Ma’am, We, Avighna Redevelopers, hereby declare the following with respect to the project “AMAR PUSHPAKUNJ” bearing registration number P51700054590 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 85% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the Balance RRC (Reinforced Cement Concrete) Work, finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to comp…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: AMAR PUSHPAKUNJ’s extension records on MahaRERA (P51700054590), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AMAR PUSHPAKUNJ
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700054590
- Status
- Registered and active
- Builder
- Avighna Redevelopers
- Location
- Thane East, Thane · 400603
- Project type
- Residential / Group Housing
- Registered on
- 31 Jan 2024
- Completion date at registration
- July 2026
- Latest completion date
- April 2028
- Delay so far
- 17 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 47
- Sold or booked
- 62%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AMAR PUSHPAKUNJ, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 85% | 47% | 0% |
| WING B | 100% | 85% | 47% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 9 floors
- WING B: covers 9 floors
Latest CC order on MahaRERA: dated 08/07/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AMAR PUSHPAKUNJ every month.
AMAR PUSHPAKUNJ: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (9 floors, 23 units) · WING B (9 floors, 24 units)
- Car parking: 44 covered
- Land: 997 sq m (about 0.2 acres) · sanctioned built-up 4,123 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Avighna Redevelopers Nav Omkar (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project.
Read Google reviews of AMAR PUSHPAKUNJ →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AMAR PUSHPAKUNJ: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AMAR PUSHPAKUNJ
What is the possession date of AMAR PUSHPAKUNJ?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AMAR PUSHPAKUNJ in Thane East, Thane is 30 April 2028 — 17 months later than 31 July 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for AMAR PUSHPAKUNJ?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AMAR PUSHPAKUNJ's builder has filed on MahaRERA, the official one, is 30 April 2028, already 17 months later than the 31 July 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AMAR PUSHPAKUNJ extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AMAR PUSHPAKUNJ's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Dear Sir/Ma’am, We, Avighna Redevelopers, hereby declare the following with respect to the project “AMAR PUSHPAKUNJ” bearing registration number P51700054590 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 85% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the Balance RRC (Reinforced Cement Concrete) Work, finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to comp…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of AMAR PUSHPAKUNJ?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AMAR PUSHPAKUNJ in Thane East, Thane is P51700054590.
Is AMAR PUSHPAKUNJ registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AMAR PUSHPAKUNJ is registered as P51700054590 and its status is "Registered and active".
What is the construction status of AMAR PUSHPAKUNJ?
According to GharKundli's check of MahaRERA records (updated October 2026), AMAR PUSHPAKUNJ's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 85% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does AMAR PUSHPAKUNJ have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is AMAR PUSHPAKUNJ safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AMAR PUSHPAKUNJ is registered on MahaRERA as P51700054590, its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AMAR PUSHPAKUNJ's possession date changes?
The latest dates are on AMAR PUSHPAKUNJ's MahaRERA page (P51700054590). GharKundli's Kundli Watch sends a free WhatsApp update on AMAR PUSHPAKUNJ every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AMAR PUSHPAKUNJ have?
According to GharKundli's check of MahaRERA records (updated October 2026), AMAR PUSHPAKUNJ has 2 buildings filed: WING A with 9 floors and 23 units; WING B with 9 floors and 24 units.
How much parking does AMAR PUSHPAKUNJ have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 44 covered car parking spaces for AMAR PUSHPAKUNJ.
How big is the land of AMAR PUSHPAKUNJ?
According to GharKundli's check of MahaRERA records (updated October 2026), AMAR PUSHPAKUNJ stands on 997 sq m of land (about 0.2 acres), with 4,123 sq m of sanctioned built-up area.
What is the track record of AMAR PUSHPAKUNJ's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Avighna Redevelopers Nav Omkar (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of AMAR PUSHPAKUNJ?
Google Maps has reviews of AMAR PUSHPAKUNJ written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AMAR PUSHPAKUNJ?
AMAR PUSHPAKUNJ by Avighna Redevelopers is in Thane East, Thane (pincode 400603), near Naupada, Mulund East, Kopri, Maharashtra, and is registered on MahaRERA as P51700054590, per GharKundli's check of MahaRERA records.
How many homes are in AMAR PUSHPAKUNJ?
According to GharKundli's check of MahaRERA records (updated October 2026), AMAR PUSHPAKUNJ has 47 homes in 2 towers registered on MahaRERA, and 62% of them are sold or booked.
When was AMAR PUSHPAKUNJ registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AMAR PUSHPAKUNJ was registered on MahaRERA on 31 January 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on AMAR PUSHPAKUNJ?
No court cases are listed for AMAR PUSHPAKUNJ on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AMAR PUSHPAKUNJ?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Avighna Redevelopers.
Check it yourself on MahaRERA
- How to check the possession date of AMAR PUSHPAKUNJ
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in pincode 400603
- Self-Redevelopment of Jeevan Smriti CHS Ltd.
- ROYAL HEIGHT - Building B
- SHALIMAR CO.OP HSG SOC LTD
- Gayatri CHS LTD
- Suprabhat C.H.S. Ltd.
- DATTA SAMARTH
- SHREYAS CO-OP HSG. SOC. LTD.
- Dinesh Co Op Hsg Society
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.