Padamavati Sapphire Homes

by Padamavati Realbuild LLP · State/UT, Thane 421302Also near Millat Nagar, ChavindreRegistered on MahaRERA as “Sapphire Homes”

What’s in the report? →

Possession date of Padamavati Sapphire Homes (MahaRERA P51700007467): 31 December 2027, moved from 30 December 2022 (60 months later). It has 172 homes, 92% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700007467, and currently active.

Source: MahaRERA website — records for P51700007467, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Padamavati Sapphire Homes?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Padamavati Sapphire Homes has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51700013440)

    Reason the builder gave MahaRERA:
    “Lockdown Restrictions had disrupted the supply chains, creating a scarcity of raw materials. Also, the migratory labour were not available post unlock, as various Government schemes like MNREGA and PM Gareeb Kalyan Anna Yojana, which provid…” Read the full reason“Lockdown Restrictions had disrupted the supply chains, creating a scarcity of raw materials. Also, the migratory labour were not available post unlock, as various Government schemes like MNREGA and PM Gareeb Kalyan Anna Yojana, which provided minimum assured wages and free essential items at the doorstep respectively, did not let them move out to earn a livelihood for a long period. Also, we had to halt our construction in 2021 (during second and third wave) as a few of our labours were infected with COVID-19. Further, we had to sanitize the entire workspace once the standard quarantine per…”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700019206)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 57.96% allottees for purpose of extension of RERA registration period of the said project.”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EA12022619813)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. We would like to inform you that the major construction activities have already been completed. However, the project has been delayed due to a f…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. We would like to inform you that the major construction activities have already been completed. However, the project has been delayed due to a few minor pending works, primarily internal plastering in certain areas and the installation of some sanitary fittings. These finishing activities, though limited in scope, require additional time to ensure proper quality and compliance with all applicable standards and regulatory requirements. In view of the above, we kindly request an extension of time u…”
  5. 31 December 2027

    Extended at the builder's request (MahaRERA application EA08062621270)

    Reason the builder gave MahaRERA:
    “We, Padamavati Realbuild LLP, the promoter of the project Sapphire Homes (Registration No. P51700007467) under MahaRERA, hereby submit our request for an extension. We would like to inform you that all major construction work of the project…” Read the full reason“We, Padamavati Realbuild LLP, the promoter of the project Sapphire Homes (Registration No. P51700007467) under MahaRERA, hereby submit our request for an extension. We would like to inform you that all major construction work of the project has been completed. At present, only certain internal finishing works and other minor ancillary works remain to be completed. Upon completion of the pending works, we shall proceed with obtaining the Occupancy Certificate (OC) from the competent authority and thereafter undertake the necessary formalities for closure of the project under MahaRERA. In vie…”

Source: Padamavati Sapphire Homes’s extension records on MahaRERA (P51700007467), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Padamavati Sapphire Homes

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700007467
Status
Registered and active
Builder
Padamavati Realbuild LLP
Location
State/UT, Thane · 421302
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2027
Delay so far
60 months
Homes
172
Sold or booked
92%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Padamavati Sapphire Homes, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sapphire Homes100%100%90%50%

Commencement certificate (CC), as filed on MahaRERA

  • Sapphire Homes: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Padamavati Sapphire Homes every 1–2 months.

Padamavati Sapphire Homes: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Padamavati Sapphire Homes →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Padamavati Sapphire Homes: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Padamavati Sapphire Homes

What is the possession date of Padamavati Sapphire Homes?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Padamavati Sapphire Homes in State/UT, Thane is 31 December 2027 — 60 months later than 30 December 2022, the date given at registration.

The date has already moved 60 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Padamavati Sapphire Homes?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Padamavati Sapphire Homes's builder has filed on MahaRERA, the official one, is 31 December 2027, already 60 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Padamavati Sapphire Homes extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Sapphire Homes's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2024, giving the reason "Lockdown Restrictions had disrupted the supply chains, creating a scarcity of raw materials. Also, the migratory labour were not available post unlock, as various Government schemes like MNREGA and PM Gareeb Kalyan Anna Yojana, which provided minimum assured wages and free essential items at the doorstep respectively, did not let them move out to earn a livelihood for a long period. Also, we had to halt our construction in 2021 (during second and third wave) as a few of our labours were infected with COVID-19. Further, we had to sanitize the entire workspace once the standard quarantine per…"; to 31 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 57.96% allottees for purpose of extension of RERA registration period of the said project."; to 30 June 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. We would like to inform you that the major construction activities have already been completed. However, the project has been delayed due to a few minor pending works, primarily internal plastering in certain areas and the installation of some sanitary fittings. These finishing activities, though limited in scope, require additional time to ensure proper quality and compliance with all applicable standards and regulatory requirements. In view of the above, we kindly request an extension of time u…"; to 31 December 2027, giving the reason "We, Padamavati Realbuild LLP, the promoter of the project Sapphire Homes (Registration No. P51700007467) under MahaRERA, hereby submit our request for an extension. We would like to inform you that all major construction work of the project has been completed. At present, only certain internal finishing works and other minor ancillary works remain to be completed. Upon completion of the pending works, we shall proceed with obtaining the Occupancy Certificate (OC) from the competent authority and thereafter undertake the necessary formalities for closure of the project under MahaRERA. In vie…".

What is the RERA number of Padamavati Sapphire Homes?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Padamavati Sapphire Homes in State/UT, Thane is P51700007467.

Is Padamavati Sapphire Homes registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Sapphire Homes is registered as P51700007467 and its status is "Registered and active".

What is the current construction status of Padamavati Sapphire Homes? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Sapphire Homes's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sapphire Homes is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Padamavati Sapphire Homes have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Padamavati Sapphire Homes safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Sapphire Homes is registered on MahaRERA as P51700007467, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Padamavati Sapphire Homes?

Padamavati Sapphire Homes is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Padamavati Sapphire Homes?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Padamavati Sapphire Homes: gharkundli.com/tools/property-cost-calculator

Has Padamavati Sapphire Homes received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Sapphire Homes is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Padamavati Sapphire Homes uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Padamavati Sapphire Homes was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Padamavati Sapphire Homes's possession date changes?

The latest dates are on Padamavati Sapphire Homes's MahaRERA page (P51700007467). GharKundli's Kundli Watch sends a free WhatsApp update on Padamavati Sapphire Homes every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Padamavati Sapphire Homes have?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Sapphire Homes has one building filed: Sapphire Homes with 19 floors and 186 units.

How much parking does Padamavati Sapphire Homes have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 98 covered car parking spaces for Padamavati Sapphire Homes.

How big is the land of Padamavati Sapphire Homes?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Sapphire Homes stands on 4,370 sq m of land (about 1.1 acres), with 3,555 sq m of sanctioned built-up area and 865 sq m of recreational open space.

What are the reviews of Padamavati Sapphire Homes?

Google Maps has reviews of Padamavati Sapphire Homes written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Padamavati Sapphire Homes?

Padamavati Sapphire Homes by Padamavati Realbuild LLP is in State/UT, Thane, pincode 421302 (near Millat Nagar, Chavindre), Maharashtra, and is registered on MahaRERA as P51700007467, per GharKundli's check of MahaRERA records. Its land is filed as 50P, 1312P1. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Padamavati Sapphire Homes, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Sapphire Homes has 172 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.

When was Padamavati Sapphire Homes registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Padamavati Sapphire Homes was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Does Padamavati Sapphire Homes have any legal issues or court cases?

No court cases are listed for Padamavati Sapphire Homes on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Padamavati Sapphire Homes?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Padamavati Realbuild LLP.

All projects with possession due in 2027 in Thane →

Other projects in Bhiwandi (421302)

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.