Kalpataru Ghantali Sainath Plaza
by KALPATARU ENTERPRISES · Ghantali, Thane 400602Registered on MahaRERA as “GHANTALI SAINATH PLAZA”
What’s in the report? →Possession date of Kalpataru Ghantali Sainath Plaza (MahaRERA P51700005750): 27 June 2027, moved from 10 August 2022 (54 months later). It has 22 homes, 54% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700005750, and currently active. Its completion date has moved from August 2022 to June 2027: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700005750, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Kalpataru Ghantali Sainath Plaza?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Kalpataru Ghantali Sainath Plaza has moved
10 August 2022
Completion date given when the project was registered
10 August 2023
Extended at the builder's request (MahaRERA application EXT51700012778)
Reason the builder gave MahaRERA:
“The Proposed date of completion of the project was 10/08/2022.but there is need to make changes in the proposed date of completion from 11/08/2022 to 10/12/2027 as the constructions are not completed as per our decided schedule due to some…” Read the full reason
“The Proposed date of completion of the project was 10/08/2022.but there is need to make changes in the proposed date of completion from 11/08/2022 to 10/12/2027 as the constructions are not completed as per our decided schedule due to some unavoidable circumstances as stated belowHowever due to technical restriction in section 6 of the RERA Act 2016 requiring to allow the extension at least by one year we are presently filing for extension till 10/08/2023”10 October 2024
Extended at the builder's request (MahaRERA application EXT51700017831)
Reason the builder gave MahaRERA: “Project Extension Required for 1 Year. Since no units have been sold we are uploading a nil consent. Kindly consider our request for project extension and grant us with the same.”
28 February 2026
Extended at the builder's request (MahaRERA application EXT51700025495)
Reason the builder gave MahaRERA: “There was a change in Plans due to which there is a delay in Project we had sold 6 Units so far and obtained a consent for almost 4 of the allottees.”
27 February 2027
Extended at the builder's request (MahaRERA application EA20032620300)
Reason the builder gave MahaRERA:
“The project is currently in the advanced stage of completion, and we are in the process of obtaining the OC along with other required statutory approvals from the concerned authorities. While significant progress has been made, the approval…” Read the full reason
“The project is currently in the advanced stage of completion, and we are in the process of obtaining the OC along with other required statutory approvals from the concerned authorities. While significant progress has been made, the approval process has taken longer than anticipated due to procedural timelines and regulatory requirements.Additionally, the project has faced financial constraints, which have impacted the pace of execution and completion. Despite these challenges, we are actively taking necessary steps to ensure compliance and timely completion of the project.In view of the abo…”27 June 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Kalpataru Ghantali Sainath Plaza’s extension records on MahaRERA (P51700005750), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kalpataru Ghantali Sainath Plaza
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700005750
- Status
- Registered and active
- Builder
- KALPATARU ENTERPRISES
- Location
- Ghantali, Thane · 400602
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- August 2022
- Latest completion date
- June 2027
- Delay so far
- 54 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 22
- Sold or booked
- 54%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Kalpataru Ghantali Sainath Plaza, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GHANTALI SAINATH PLAZA | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- GHANTALI SAINATH PLAZA: covers 9 floors
Latest CC order on MahaRERA: dated 11/03/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kalpataru Ghantali Sainath Plaza every 1–2 months.
Kalpataru Ghantali Sainath Plaza: buildings, flats and land, as filed on MahaRERA
- Buildings: GHANTALI SAINATH PLAZA (9 floors, 24 units)
- Car parking: 10 covered
- Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 2,620 sq m · recreational space 836 sq m
- Land, as filed: TIKA NO.15 CTS NO 13A PT
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Kalpataru Ghantali Sainath Plaza →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kalpataru Ghantali Sainath Plaza: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kalpataru Ghantali Sainath Plaza
What is the possession date of Kalpataru Ghantali Sainath Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kalpataru Ghantali Sainath Plaza in Ghantali, Thane is 27 June 2027 — 54 months later than 10 August 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 54 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Kalpataru Ghantali Sainath Plaza?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kalpataru Ghantali Sainath Plaza's builder has filed on MahaRERA, the official one, is 27 June 2027, already 54 months later than the 10 August 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kalpataru Ghantali Sainath Plaza extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza's builder applied to MahaRERA to extend the completion date 4 times: to 10 August 2023, giving the reason "The Proposed date of completion of the project was 10/08/2022.but there is need to make changes in the proposed date of completion from 11/08/2022 to 10/12/2027 as the constructions are not completed as per our decided schedule due to some unavoidable circumstances as stated belowHowever due to technical restriction in section 6 of the RERA Act 2016 requiring to allow the extension at least by one year we are presently filing for extension till 10/08/2023"; to 10 October 2024, giving the reason "Project Extension Required for 1 Year. Since no units have been sold we are uploading a nil consent. Kindly consider our request for project extension and grant us with the same."; to 28 February 2026, giving the reason "There was a change in Plans due to which there is a delay in Project we had sold 6 Units so far and obtained a consent for almost 4 of the allottees."; to 27 February 2027, giving the reason "The project is currently in the advanced stage of completion, and we are in the process of obtaining the OC along with other required statutory approvals from the concerned authorities. While significant progress has been made, the approval process has taken longer than anticipated due to procedural timelines and regulatory requirements.Additionally, the project has faced financial constraints, which have impacted the pace of execution and completion. Despite these challenges, we are actively taking necessary steps to ensure compliance and timely completion of the project.In view of the abo…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Kalpataru Ghantali Sainath Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kalpataru Ghantali Sainath Plaza in Ghantali, Thane is P51700005750.
Is Kalpataru Ghantali Sainath Plaza registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza is registered as P51700005750 and its status is "Registered and active".
What is the current construction status of Kalpataru Ghantali Sainath Plaza? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GHANTALI SAINATH PLAZA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Kalpataru Ghantali Sainath Plaza have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kalpataru Ghantali Sainath Plaza safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza is registered on MahaRERA as P51700005750, its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kalpataru Ghantali Sainath Plaza?
Kalpataru Ghantali Sainath Plaza is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kalpataru Ghantali Sainath Plaza?
For a flat in Kalpataru Ghantali Sainath Plaza (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Kalpataru Ghantali Sainath Plaza received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza is still under construction, with 27 June 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Kalpataru Ghantali Sainath Plaza a redevelopment or SRA project?
Yes. According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza is an SRA scheme: MahaRERA lists the Slum Rehabilitation Authority as its planning authority. In SRA schemes the sale building depends on the rehab building and SRA approvals, a common reason for delays, so check the rehab building's progress too.
Has Kalpataru Ghantali Sainath Plaza uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kalpataru Ghantali Sainath Plaza was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Kalpataru Ghantali Sainath Plaza's possession date changes?
The latest dates are on Kalpataru Ghantali Sainath Plaza's MahaRERA page (P51700005750). GharKundli's Kundli Watch sends a free WhatsApp update on Kalpataru Ghantali Sainath Plaza every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kalpataru Ghantali Sainath Plaza have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza has one building filed: GHANTALI SAINATH PLAZA with 9 floors and 24 units.
How much parking does Kalpataru Ghantali Sainath Plaza have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 covered car parking spaces for Kalpataru Ghantali Sainath Plaza.
How big is the land of Kalpataru Ghantali Sainath Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza stands on 1,000 sq m of land (about 0.2 acres), with 2,620 sq m of sanctioned built-up area and 836 sq m of recreational open space.
What are the reviews of Kalpataru Ghantali Sainath Plaza?
Google Maps has reviews of Kalpataru Ghantali Sainath Plaza written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kalpataru Ghantali Sainath Plaza?
Kalpataru Ghantali Sainath Plaza by KALPATARU ENTERPRISES is in Ghantali, Thane, pincode 400602, Maharashtra, and is registered on MahaRERA as P51700005750, per GharKundli's check of MahaRERA records. Its land is filed as TIKA NO.15 CTS NO 13A PT. GharKundli lists all 258 MahaRERA projects in Naupada (400602).
How many flats are in Kalpataru Ghantali Sainath Plaza, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza has 22 homes in 1 tower registered on MahaRERA, and 54% of them are sold or booked.
When was Kalpataru Ghantali Sainath Plaza registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Ghantali Sainath Plaza was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Does Kalpataru Ghantali Sainath Plaza have any legal issues or court cases?
No court cases are listed for Kalpataru Ghantali Sainath Plaza on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Kalpataru Ghantali Sainath Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KALPATARU ENTERPRISES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kalpataru Ghantali Sainath Plaza
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Thane
- Veer Square (Thane)
- Raj Tattva Phase 1 Commercial
- Mauli Krupa
- Gurukrupa Nityam
- Lotus
- Urban Reserve Wing B
- Asavari Co Op HSG Soc LTD
- Panache
Other projects by KALPATARU ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.