What’s in the report? →Possession date of Nandishwar Plaza (MahaRERA P51700009387): 30 April 2028, moved from 10 August 2023 (52 months later). It has 59 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700009387, and currently active. Its completion date has moved from August 2023 to April 2028: 52 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700009387, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Nandishwar Plaza?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Nandishwar Plaza has moved
10 August 2023
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EXT51700015301)
Reason the builder gave MahaRERA:
“Our project does not currently have proper access from DP Road, which is why we have not sold any units to the allottees. Therefore, there is no need for consent for an extension as per Section 7(3). Once we have clarity regarding the acces…” Read the full reason
“Our project does not currently have proper access from DP Road, which is why we have not sold any units to the allottees. Therefore, there is no need for consent for an extension as per Section 7(3). Once we have clarity regarding the access road adjacent to our project, we will begin sales. We have registered the project with MahaRERA solely for compliance purposes.”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Nandishwar Plaza’s extension records on MahaRERA (P51700009387), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nandishwar Plaza
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700009387
- Status
- Registered and active
- Builder
- NANDISHWAR CONS CO
- Location
- Naupada S.O (Thane), Thane · 400602
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- August 2023
- Latest completion date
- April 2028
- Delay so far
- 52 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 59
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Nandishwar Plaza, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NADISHWAR PLAZA | 0% | 41% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nandishwar Plaza every 1–2 months.
Nandishwar Plaza: buildings, flats and land, as filed on MahaRERA
- Buildings: NADISHWAR PLAZA (18 floors)
- Land: 700 sq m (about 0.2 acres) · sanctioned built-up 1,687 sq m · recreational space 700 sq m
- Land, as filed: S NO 13 HISSA NO 4
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Nandishwar Plaza →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nandishwar Plaza: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Nandishwar Plaza
What is the possession date of Nandishwar Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nandishwar Plaza in Naupada S.O (Thane), Thane is 30 April 2028 — 52 months later than 10 August 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 52 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Nandishwar Plaza?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nandishwar Plaza's builder has filed on MahaRERA, the official one, is 30 April 2028, already 52 months later than the 10 August 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Nandishwar Plaza extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Our project does not currently have proper access from DP Road, which is why we have not sold any units to the allottees. Therefore, there is no need for consent for an extension as per Section 7(3). Once we have clarity regarding the access road adjacent to our project, we will begin sales. We have registered the project with MahaRERA solely for compliance purposes.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Nandishwar Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nandishwar Plaza in Naupada S.O (Thane), Thane is P51700009387.
Is Nandishwar Plaza registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza is registered as P51700009387 and its status is "Registered and active".
What is the current construction status of Nandishwar Plaza? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NADISHWAR PLAZA is 41% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Nandishwar Plaza have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Nandishwar Plaza safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza is registered on MahaRERA as P51700009387, its completion date has moved 52 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Nandishwar Plaza?
Nandishwar Plaza is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Nandishwar Plaza?
For a flat in Nandishwar Plaza (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Nandishwar Plaza received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Nandishwar Plaza a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza is a redevelopment: 35 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Nandishwar Plaza uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Nandishwar Plaza was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Nandishwar Plaza's possession date changes?
The latest dates are on Nandishwar Plaza's MahaRERA page (P51700009387). GharKundli's Kundli Watch sends a free WhatsApp update on Nandishwar Plaza every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nandishwar Plaza have?
According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza has one building filed: NADISHWAR PLAZA with 18 floors.
How big is the land of Nandishwar Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza stands on 700 sq m of land (about 0.2 acres), with 1,687 sq m of sanctioned built-up area and 700 sq m of recreational open space.
What are the reviews of Nandishwar Plaza?
Google Maps has reviews of Nandishwar Plaza written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Nandishwar Plaza?
Nandishwar Plaza by NANDISHWAR CONS CO is in Naupada S.O (Thane), Thane, pincode 400602, Maharashtra, and is registered on MahaRERA as P51700009387, per GharKundli's check of MahaRERA records. Its land is filed as S NO 13 HISSA NO 4. GharKundli lists all 258 MahaRERA projects in Naupada (400602).
How many flats are in Nandishwar Plaza, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza has 59 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Nandishwar Plaza registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nandishwar Plaza was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Does Nandishwar Plaza have any legal issues or court cases?
No court cases are listed for Nandishwar Plaza on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Nandishwar Plaza?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NANDISHWAR CONS CO.
Check it yourself on MahaRERA
- How to check the possession date of Nandishwar Plaza
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Naupada (400602)
- Asavari Co Op HSG Soc LTD
- The Lake Corner
- Platinum Square
- Parvati Niwas
- Rivanta
- Ekatva Crescent
- Pitruchhaya
- Navyug Co.Op.Hsg.Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.