Shanti Luxuria
by RDP Realtores (AUM) · Village Padle, ThaneAlso near Manpada, Vishnunagar
Possession date of Shanti Luxuria: 30 April 2027, moved from 30 June 2022 (54 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700012995, and currently active. Its completion date has moved from June 2022 to April 2027: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued 2 regulatory orders on this project. 66 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Shanti Luxuria?
How the possession date of Shanti Luxuria has moved
30 June 2022
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT51700010768)
Reason the builder gave MahaRERA: “We hereby apply for extension u/s 7 (3) of the registered project bearing vide no P51700012995. As prescribed under circulation no 07/2019 dated 8th Feb 2019, the consent of 51% of the allottees is enclosed herewith.”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51700015118)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, This is in reference to Real Estate Project “Shanti Luxuria” with MahaRERA Project Registration No: P51700012995, whose registration is ending on 30th June 2023. I am writing herewith to kindly request you to grant exte…” Read the full reason
“Respected Sir/Madam, This is in reference to Real Estate Project “Shanti Luxuria” with MahaRERA Project Registration No: P51700012995, whose registration is ending on 30th June 2023. I am writing herewith to kindly request you to grant extension for this project by 18 months thereby extending the registration till December 2024. The aforesaid project was initiated Pre-RERA and had gone into financial difficulties. We partnered with this promoter to revive this lapsed project. In order to ensure financial viability of the project, adjacent land was taken and accordingly, FSI area was increas…”31 December 2025
Extended at the builder's request (MahaRERA application EXT51700024959)
Reason the builder gave MahaRERA:
“As per the Urban Development Control and Promotion Regulations (UDCPR) guidelines, we supposed to provide adequate number of parking to the flat purchasers. We intend to construct tower parking and for that we have already acquired the land…” Read the full reason
“As per the Urban Development Control and Promotion Regulations (UDCPR) guidelines, we supposed to provide adequate number of parking to the flat purchasers. We intend to construct tower parking and for that we have already acquired the land for construction of tower parking. The Corporation granted Commencement Certificate for construction of Tower Parking on 19th September, 2024. However, due to unusually heavy monsoon season, it was not feasible to commence the work. Hence, the Construction work could not be started. Now the monsoon has ended, we are prepared to prioritize the parking wor…”31 December 2026
Extended at the builder's request (MahaRERA application EA12122518660)
Reason the builder gave MahaRERA:
“1) Delay Due to Obstruction of Access Road by Adjacent Land Owner 2) High-tension electrical cables and extensions were laid across the common access route. i) Construction vehicles were unable to enter or exit the project site; ii) Transpo…” Read the full reason
“1) Delay Due to Obstruction of Access Road by Adjacent Land Owner 2) High-tension electrical cables and extensions were laid across the common access route. i) Construction vehicles were unable to enter or exit the project site; ii) Transportation of materials, concrete, machinery, and essential equipment became impossible; iii) Labour movement and access for emergency service vehicles was entirely prevented; and iv) All construction activities from November 2024 to September 2025 were brought to a complete standstill.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shanti Luxuria’s extension records on MahaRERA (P51700012995), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shanti Luxuria
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 66 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700012995
- Status
- Registered and active
- Builder
- RDP Realtores
- Location
- Village Padle, Thane · 421204
- Project type
- Others
- Registered on
- 11 Sep 2017
- Completion date at registration
- June 2022
- Latest completion date
- April 2027
- Delay so far
- 54 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 307
- Sold or booked
- 80%
- Towers
- 1
- Complaints on MahaRERA
- 66
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- MahaRERA regulatory orders
- 2
- Title report on file
- Not found
Construction progress of Shanti Luxuria, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shanti Luxuria | 100% | 100% | 78% | 20% |
Commencement certificate (CC), as filed on MahaRERA
- Shanti Luxuria: covers 32 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shanti Luxuria every month.
Shanti Luxuria: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 351 – 461 | 136 |
| Other | 445 – 557 | 112 |
| 2 BHK | 461 – 639 | 59 |
| Shops | 763 – 2,248 | 8 |
- Buildings: Shanti Luxuria (32 floors, 315 units)
- Car parking: 231 open
- Land: 7,900 sq m (about 2.0 acres) · sanctioned built-up 9,019 sq m · recreational space 1,629 sq m
The builder’s record and reviews
Raunak Corporation (a group of 19 linked companies) has 60 projects on MahaRERA since 2017, this one included. Of the 60 GharKundli has checked: 29 finished, 28 within the promised date and 1 needed more time (typically 5 months); 30 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 162 complaints on MahaRERA across 27 projects.
Read Google reviews of Shanti Luxuria →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shanti Luxuria: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shanti Luxuria
What is the possession date of Shanti Luxuria?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shanti Luxuria in Village Padle, Thane is 30 April 2027 — 54 months later than 30 June 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shanti Luxuria?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shanti Luxuria's builder has filed on MahaRERA, the official one, is 30 April 2027, already 54 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shanti Luxuria extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shanti Luxuria's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2022, giving the reason "We hereby apply for extension u/s 7 (3) of the registered project bearing vide no P51700012995. As prescribed under circulation no 07/2019 dated 8th Feb 2019, the consent of 51% of the allottees is enclosed herewith."; to 31 December 2024, giving the reason "Respected Sir/Madam, This is in reference to Real Estate Project “Shanti Luxuria” with MahaRERA Project Registration No: P51700012995, whose registration is ending on 30th June 2023. I am writing herewith to kindly request you to grant extension for this project by 18 months thereby extending the registration till December 2024. The aforesaid project was initiated Pre-RERA and had gone into financial difficulties. We partnered with this promoter to revive this lapsed project. In order to ensure financial viability of the project, adjacent land was taken and accordingly, FSI area was increas…"; to 31 December 2025, giving the reason "As per the Urban Development Control and Promotion Regulations (UDCPR) guidelines, we supposed to provide adequate number of parking to the flat purchasers. We intend to construct tower parking and for that we have already acquired the land for construction of tower parking. The Corporation granted Commencement Certificate for construction of Tower Parking on 19th September, 2024. However, due to unusually heavy monsoon season, it was not feasible to commence the work. Hence, the Construction work could not be started. Now the monsoon has ended, we are prepared to prioritize the parking wor…"; to 31 December 2026, giving the reason "1) Delay Due to Obstruction of Access Road by Adjacent Land Owner 2) High-tension electrical cables and extensions were laid across the common access route. i) Construction vehicles were unable to enter or exit the project site; ii) Transportation of materials, concrete, machinery, and essential equipment became impossible; iii) Labour movement and access for emergency service vehicles was entirely prevented; and iv) All construction activities from November 2024 to September 2025 were brought to a complete standstill.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shanti Luxuria?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shanti Luxuria in Village Padle, Thane is P51700012995.
Is Shanti Luxuria registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shanti Luxuria is registered as P51700012995 and its status is "Registered and active".
What is the construction status of Shanti Luxuria?
According to GharKundli's check of MahaRERA records (updated October 2026), Shanti Luxuria's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shanti Luxuria is 100% done and internal work 78%. GharKundli's full report compares construction progress with the deadline.
Does Shanti Luxuria have complaints on MahaRERA?
66 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Shanti Luxuria safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shanti Luxuria is registered on MahaRERA as P51700012995, its completion date has moved 54 months since registration and 66 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shanti Luxuria's possession date changes?
The latest dates are on Shanti Luxuria's MahaRERA page (P51700012995). GharKundli's Kundli Watch sends a free WhatsApp update on Shanti Luxuria every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shanti Luxuria have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shanti Luxuria has one building filed: Shanti Luxuria with 32 floors and 315 units.
What are the flat sizes (carpet area) in Shanti Luxuria?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shanti Luxuria: 1 BHK: 351 to 461 sq ft carpet (136 homes); Other: 445 to 557 sq ft carpet (112 homes); 2 BHK: 461 to 639 sq ft carpet (59 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Shanti Luxuria have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 231 open car parking spaces for Shanti Luxuria.
How big is the land of Shanti Luxuria?
According to GharKundli's check of MahaRERA records (updated October 2026), Shanti Luxuria stands on 7,900 sq m of land (about 2.0 acres), with 9,019 sq m of sanctioned built-up area and 1,629 sq m of recreational open space.
What is the track record of Shanti Luxuria's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Raunak Corporation (a group of 19 linked companies) has 60 projects on MahaRERA since 2017, this one included. Of the 60 GharKundli has checked: 29 finished, 28 within the promised date and 1 needed more time (typically 5 months); 30 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 162 complaints on MahaRERA across 27 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Shanti Luxuria?
Google Maps has reviews of Shanti Luxuria written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 66 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shanti Luxuria?
Shanti Luxuria by RDP Realtores (AUM) is in Village Padle, Thane (pincode 421204), near Manpada, Vishnunagar, Maharashtra, and is registered on MahaRERA as P51700012995, per GharKundli's check of MahaRERA records.
How many homes are in Shanti Luxuria?
According to GharKundli's check of MahaRERA records (updated October 2026), Shanti Luxuria has 307 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.
When was Shanti Luxuria registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shanti Luxuria was registered on MahaRERA on 11 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Shanti Luxuria?
No court cases are listed for Shanti Luxuria on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Shanti Luxuria?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RDP Realtores, the company AUM files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Shanti Luxuria
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 421204
- THE CENNET
- Palava Fresca J-K
- YESU ANAND HEIGHTS
- Runwal Gardens Phase 4 Bldg No. 33-34
- SHREE KRISHNA HEIGHTS
- ARISTA SKYLINE
- Chanakya A wing
- Chanakya C wing
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.