Runwal Gardens Phase 4 Bldg No. 33-34
by Runwal Residency Private Limited · Dombivali, ThaneAlso near Kole, Bhiwandi, Vidyashram
Possession date of Runwal Gardens Phase 4 Bldg No. 33-34: 31 May 2027, moved from 30 June 2025 (23 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700030533, and currently active. 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Runwal Gardens Phase 4 Bldg No. 33-34?
How the possession date of Runwal Gardens Phase 4 Bldg No. 33-34 has moved
30 June 2025
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EXT51700024876)
Reason the builder gave MahaRERA:
“There is no deliberate delay in completion of the said Project. The cascading impact of the Covid 19 pandemic and the other issues explained hereinbelow have impacted work completion. The Hon’ble High Court has in paragraphs 106 to 114 of i…” Read the full reason
“There is no deliberate delay in completion of the said Project. The cascading impact of the Covid 19 pandemic and the other issues explained hereinbelow have impacted work completion. The Hon’ble High Court has in paragraphs 106 to 114 of its judgement passed in the case of Neelkamal Realtors and Developers & Anr. Vs Union of India (2017 SCC Online Bom 9302) held that in the event the promoter establishes that there are compelling circumstances and reasons for the promoter in failing to complete the project, the Authority will be entitled to grant an extension and allow the promoter to cont…”31 May 2027
Extended at the builder's request (MahaRERA application EA07072621683)
Reason the builder gave MahaRERA:
“The delay in the completion of the project has primarily occurred due to the persistent non-performance and frequent transitions of multiple civil contractors, beginning with the initial contractor, SAC Paradise, whose consistent failure to…” Read the full reason
“The delay in the completion of the project has primarily occurred due to the persistent non-performance and frequent transitions of multiple civil contractors, beginning with the initial contractor, SAC Paradise, whose consistent failure to meet execution milestones necessitated their de-scoping and caused an unavoidable work stoppage. Furthermore, the project faced successive setbacks with the underperformance and subsequent termination of the replacement contractor, RAK, which required onboarding a third contractor, Nagnechi Construction. The cumulative effect of these frequent transition…”
Source: Runwal Gardens Phase 4 Bldg No. 33-34’s extension records on MahaRERA (P51700030533), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Runwal Gardens Phase 4 Bldg No. 33-34
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 complaints, and how it ended
- Construction pace against the May 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Runwal Gardens Phase 2 Bldg no 13-17P51700025677 · possession 30 Jun 2025
- Runwal Gardens Phase 2 Bldg no 18-23P51700024154 · possession 30 Dec 2024
- Runwal Gardens Phase 3 Bldg no 24-26P51700026228 · possession 30 Jun 2025
- Runwal Gardens Phase 3 Bldg No 27-28P51700026927 · possession 30 Jun 2026
- Runwal Gardens Phase 3 Bldg No 29-30P51700028344 · possession 30 Jun 2026
- Runwal Gardens Phase 4 Bldg No. 31-32P51700029155 · possession 31 Dec 2026
- Runwal Gardens Phase 4 Bldg No. 35-36P51700031319 · possession 30 Mar 2027
- Runwal Gardens Phase 4 Bldg No. 37P51700033206 · possession 30 Jun 2027
- Runwal Gardens Phase 4 Bldg No. 38P51700046550 · possession 30 Dec 2027
- Runwal Gardens Phase 5 Bldg No. 39 to 42P51700031609 · possession 30 Oct 2028
- Runwal Gardens Phase 6A Bldg No. 53-54P51700051346 · possession 2 Jun 2029
- Runwal Gardens Phase 8 Bldg No. 43 and 45P51700052441 · possession 30 Sep 2028
- Runwal Gardens - Phase 8 - Bldg No. 44P51700047512 · possession 31 Dec 2028
- Runwal Gardens Phase IP51700022699 · possession 30 Jun 2025
- MahaRERA registration
- P51700030533
- Status
- Registered and active
- Builder
- Runwal Residency Private Limited
- Location
- Dombivali, Thane · 421204
- Project type
- Residential / Group Housing
- Registered on
- 30 Aug 2021
- Completion date at registration
- June 2025
- Latest completion date
- May 2027
- Delay so far
- 23 months
- Homes
- 564
- Sold or booked
- 84%
- Towers
- 2
- Complaints on MahaRERA
- 8
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 17
Construction progress of Runwal Gardens Phase 4 Bldg No. 33-34, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bldg No 33 | 100% | 93% | 25% | 10% |
| Bldg No 34 | 100% | 70% | 18% | 5% |
Commencement certificate (CC), as filed on MahaRERA
- Bldg No 33: covers 34 floors
- Bldg No 34: covers 34 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Runwal Gardens Phase 4 Bldg No. 33-34 every month.
Runwal Gardens Phase 4 Bldg No. 33-34: buildings, flats and land, as filed on MahaRERA
- Buildings: Bldg No 33 (36 floors, 282 units) · Bldg No 34 (36 floors, 282 units)
- Land: 1,476 sq m (about 0.4 acres) · sanctioned built-up 47,787 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Runwal Gardens Phase 4 Bldg No. 33-34 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Runwal Gardens Phase 4 Bldg No. 33-34: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Runwal Gardens Phase 4 Bldg No. 33-34
What is the possession date of Runwal Gardens Phase 4 Bldg No. 33-34?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Runwal Gardens Phase 4 Bldg No. 33-34 in Dombivali, Thane is 31 May 2027 — 23 months later than 30 June 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Runwal Gardens Phase 4 Bldg No. 33-34?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Runwal Gardens Phase 4 Bldg No. 33-34's builder has filed on MahaRERA, the official one, is 31 May 2027, already 23 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Runwal Gardens Phase 4 Bldg No. 33-34 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 33-34's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2026, giving the reason "There is no deliberate delay in completion of the said Project. The cascading impact of the Covid 19 pandemic and the other issues explained hereinbelow have impacted work completion. The Hon’ble High Court has in paragraphs 106 to 114 of its judgement passed in the case of Neelkamal Realtors and Developers & Anr. Vs Union of India (2017 SCC Online Bom 9302) held that in the event the promoter establishes that there are compelling circumstances and reasons for the promoter in failing to complete the project, the Authority will be entitled to grant an extension and allow the promoter to cont…"; to 31 May 2027, giving the reason "The delay in the completion of the project has primarily occurred due to the persistent non-performance and frequent transitions of multiple civil contractors, beginning with the initial contractor, SAC Paradise, whose consistent failure to meet execution milestones necessitated their de-scoping and caused an unavoidable work stoppage. Furthermore, the project faced successive setbacks with the underperformance and subsequent termination of the replacement contractor, RAK, which required onboarding a third contractor, Nagnechi Construction. The cumulative effect of these frequent transition…".
What is the RERA number of Runwal Gardens Phase 4 Bldg No. 33-34?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Runwal Gardens Phase 4 Bldg No. 33-34 in Dombivali, Thane is P51700030533.
Is Runwal Gardens Phase 4 Bldg No. 33-34 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 33-34 is registered as P51700030533 and its status is "Registered and active".
What is the construction status of Runwal Gardens Phase 4 Bldg No. 33-34?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 33-34's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 70% to 93% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Runwal Gardens Phase 4 Bldg No. 33-34 have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Runwal Gardens Phase 4 Bldg No. 33-34 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 33-34 is registered on MahaRERA as P51700030533, its completion date has moved 23 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Runwal Gardens Phase 4 Bldg No. 33-34 have other wings or phases?
Yes. MahaRERA lists 14 other registrations of the same project, each with its own possession date: Runwal Gardens Phase 2 Bldg no 13-17 (P51700025677, possession 30 Jun 2025); Runwal Gardens Phase 2 Bldg no 18-23 (P51700024154, possession 30 Dec 2024); Runwal Gardens Phase 3 Bldg no 24-26 (P51700026228, possession 30 Jun 2025); Runwal Gardens Phase 3 Bldg No 27-28 (P51700026927, possession 30 Jun 2026); Runwal Gardens Phase 3 Bldg No 29-30 (P51700028344, possession 30 Jun 2026); Runwal Gardens Phase 4 Bldg No. 31-32 (P51700029155, possession 31 Dec 2026); and 8 more. Check that your agreement names the registration of your own wing.
How can I get updates if Runwal Gardens Phase 4 Bldg No. 33-34's possession date changes?
The latest dates are on Runwal Gardens Phase 4 Bldg No. 33-34's MahaRERA page (P51700030533). GharKundli's Kundli Watch sends a free WhatsApp update on Runwal Gardens Phase 4 Bldg No. 33-34 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Runwal Gardens Phase 4 Bldg No. 33-34 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 33-34 has 2 buildings filed: Bldg No 33 with 36 floors and 282 units; Bldg No 34 with 36 floors and 282 units.
How big is the land of Runwal Gardens Phase 4 Bldg No. 33-34?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 33-34 stands on 1,476 sq m of land (about 0.4 acres), with 47,787 sq m of sanctioned built-up area.
Where can I read reviews of Runwal Gardens Phase 4 Bldg No. 33-34?
Google Maps has reviews of Runwal Gardens Phase 4 Bldg No. 33-34 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Runwal Gardens Phase 4 Bldg No. 33-34?
Runwal Gardens Phase 4 Bldg No. 33-34 by Runwal Residency Private Limited is in Dombivali, Thane (pincode 421204), near Kole, Bhiwandi, Vidyashram, Maharashtra, and is registered on MahaRERA as P51700030533, per GharKundli's check of MahaRERA records.
How many homes are in Runwal Gardens Phase 4 Bldg No. 33-34?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 33-34 has 564 homes in 2 towers registered on MahaRERA, and 84% of them are sold or booked.
When was Runwal Gardens Phase 4 Bldg No. 33-34 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 33-34 was registered on MahaRERA on 30 August 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Runwal Gardens Phase 4 Bldg No. 33-34?
No court cases are listed for Runwal Gardens Phase 4 Bldg No. 33-34 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Runwal Gardens Phase 4 Bldg No. 33-34?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Runwal Residency Private Limited, which has 17 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Runwal Gardens Phase 4 Bldg No. 33-34
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Dombivali
- LotuAai Darshan Wing B
- Runwal Garden City Cluster 6 Tower 6 to 9
- Runwal Edge
- Runwal Gardens Phase 8 Bldg No. 43 and 45
- Runwal Gardens - Phase 8 - Bldg No. 44
- Runwal Gardens Phase 4 Bldg No. 38
- Lodha Panacea II
- Runwal Gardens Phase 6A Bldg No. 53-54
Other projects by Runwal Residency Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.