Runwal Gardens Phase 3 Bldg No 27-28
by Runwal Residency Private Limited · Dombivli, Thane
Possession date of Runwal Gardens Phase 3 Bldg No 27-28: 30 June 2026, moved from 30 December 2025 (6 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700026927. Status: Lapsed (registration period ended). 17 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about Runwal Gardens Phase 3 Bldg No 27-28?
How the possession date of Runwal Gardens Phase 3 Bldg No 27-28 has moved
30 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA22122518910)
Reason the builder gave MahaRERA:
“The Promoter respectfully submits that the project was registered in November 2020, during the COVID-19 pandemic. The prolonged impact of the pandemic, including repeated lockdowns, severe labour shortages, supply-chain disruptions, and res…” Read the full reason
“The Promoter respectfully submits that the project was registered in November 2020, during the COVID-19 pandemic. The prolonged impact of the pandemic, including repeated lockdowns, severe labour shortages, supply-chain disruptions, and restrictions relating to health and safety, adversely affected construction progress. These circumstances were unforeseen and beyond the control of the Promoter. Further delays occurred due to non-performance and inefficiency of appointed civil contractors, resulting in termination, re-tendering, and engagement of new contractors, leading to substantial loss…”
Source: Runwal Gardens Phase 3 Bldg No 27-28’s extension records on MahaRERA (P51700026927), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Runwal Gardens Phase 3 Bldg No 27-28
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 17 complaints, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Runwal Gardens Phase 2 Bldg no 13-17P51700025677 · possession 30 Jun 2025
- Runwal Gardens Phase 2 Bldg no 18-23P51700024154 · possession 30 Dec 2024
- Runwal Gardens Phase 3 Bldg no 24-26P51700026228 · possession 30 Jun 2025
- Runwal Gardens Phase 3 Bldg No 29-30P51700028344 · possession 30 Jun 2026
- Runwal Gardens Phase 4 Bldg No. 31-32P51700029155 · possession 31 Dec 2026
- Runwal Gardens Phase 4 Bldg No. 33-34P51700030533 · possession 31 May 2027
- Runwal Gardens Phase 4 Bldg No. 35-36P51700031319 · possession 30 Mar 2027
- Runwal Gardens Phase 4 Bldg No. 37P51700033206 · possession 30 Jun 2027
- Runwal Gardens Phase 4 Bldg No. 38P51700046550 · possession 30 Dec 2027
- Runwal Gardens Phase 5 Bldg No. 39 to 42P51700031609 · possession 30 Oct 2028
- Runwal Gardens Phase 6A Bldg No. 53-54P51700051346 · possession 2 Jun 2029
- Runwal Gardens Phase 8 Bldg No. 43 and 45P51700052441 · possession 30 Sep 2028
- Runwal Gardens - Phase 8 - Bldg No. 44P51700047512 · possession 31 Dec 2028
- Runwal Gardens Phase IP51700022699 · possession 30 Jun 2025
- MahaRERA registration
- P51700026927
- Status
- Lapsed (registration period ended)
- Builder
- Runwal Residency Private Limited
- Location
- Dombivli, Thane · 421201
- Project type
- Residential / Group Housing
- Registered on
- 3 Nov 2020
- Completion date at registration
- December 2025
- Latest completion date
- June 2026
- Delay so far
- 6 months
- Homes
- 625
- Sold or booked
- 85%
- Towers
- 2
- Complaints on MahaRERA
- 17
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 17
Construction progress of Runwal Gardens Phase 3 Bldg No 27-28, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 27 | 100% | 100% | 95% | 60% |
| Building No 28 | 100% | 100% | 92% | 55% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 27: covers 32 floors
- Building No 28: covers 32 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Runwal Gardens Phase 3 Bldg No 27-28 every month.
Runwal Gardens Phase 3 Bldg No 27-28: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 27 (35 floors, 311 units) · Building No 28 (35 floors, 314 units)
- Land: 1,298 sq m (about 0.3 acres) · sanctioned built-up 33,049 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Runwal Gardens Phase 3 Bldg No 27-28 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Runwal Gardens Phase 3 Bldg No 27-28: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Runwal Gardens Phase 3 Bldg No 27-28
What is the possession date of Runwal Gardens Phase 3 Bldg No 27-28?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Runwal Gardens Phase 3 Bldg No 27-28 in Dombivli, Thane is 30 June 2026 — 6 months later than 30 December 2025, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Runwal Gardens Phase 3 Bldg No 27-28?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Runwal Gardens Phase 3 Bldg No 27-28's builder has filed on MahaRERA, the official one, is 30 June 2026, already 6 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Runwal Gardens Phase 3 Bldg No 27-28 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 3 Bldg No 27-28's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "The Promoter respectfully submits that the project was registered in November 2020, during the COVID-19 pandemic. The prolonged impact of the pandemic, including repeated lockdowns, severe labour shortages, supply-chain disruptions, and restrictions relating to health and safety, adversely affected construction progress. These circumstances were unforeseen and beyond the control of the Promoter. Further delays occurred due to non-performance and inefficiency of appointed civil contractors, resulting in termination, re-tendering, and engagement of new contractors, leading to substantial loss…".
What is the RERA number of Runwal Gardens Phase 3 Bldg No 27-28?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Runwal Gardens Phase 3 Bldg No 27-28 in Dombivli, Thane is P51700026927.
Is Runwal Gardens Phase 3 Bldg No 27-28 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 3 Bldg No 27-28 is registered as P51700026927 and its status is "Lapsed (registration period ended)".
What is the construction status of Runwal Gardens Phase 3 Bldg No 27-28?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 3 Bldg No 27-28's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Runwal Gardens Phase 3 Bldg No 27-28 have complaints on MahaRERA?
17 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Runwal Gardens Phase 3 Bldg No 27-28 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 3 Bldg No 27-28 is registered on MahaRERA as P51700026927, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and 17 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Runwal Gardens Phase 3 Bldg No 27-28 have other wings or phases?
Yes. MahaRERA lists 14 other registrations of the same project, each with its own possession date: Runwal Gardens Phase 2 Bldg no 13-17 (P51700025677, possession 30 Jun 2025); Runwal Gardens Phase 2 Bldg no 18-23 (P51700024154, possession 30 Dec 2024); Runwal Gardens Phase 3 Bldg no 24-26 (P51700026228, possession 30 Jun 2025); Runwal Gardens Phase 3 Bldg No 29-30 (P51700028344, possession 30 Jun 2026); Runwal Gardens Phase 4 Bldg No. 31-32 (P51700029155, possession 31 Dec 2026); Runwal Gardens Phase 4 Bldg No. 33-34 (P51700030533, possession 31 May 2027); and 8 more. Check that your agreement names the registration of your own wing.
How can I get updates if Runwal Gardens Phase 3 Bldg No 27-28's possession date changes?
The latest dates are on Runwal Gardens Phase 3 Bldg No 27-28's MahaRERA page (P51700026927). GharKundli's Kundli Watch sends a free WhatsApp update on Runwal Gardens Phase 3 Bldg No 27-28 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Runwal Gardens Phase 3 Bldg No 27-28 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 3 Bldg No 27-28 has 2 buildings filed: Building No 27 with 35 floors and 311 units; Building No 28 with 35 floors and 314 units.
How big is the land of Runwal Gardens Phase 3 Bldg No 27-28?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 3 Bldg No 27-28 stands on 1,298 sq m of land (about 0.3 acres), with 33,049 sq m of sanctioned built-up area.
Where can I read reviews of Runwal Gardens Phase 3 Bldg No 27-28?
Google Maps has reviews of Runwal Gardens Phase 3 Bldg No 27-28 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 17 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Runwal Gardens Phase 3 Bldg No 27-28?
Runwal Gardens Phase 3 Bldg No 27-28 by Runwal Residency Private Limited is in Dombivli, Thane (pincode 421201), Maharashtra, and is registered on MahaRERA as P51700026927, per GharKundli's check of MahaRERA records.
How many homes are in Runwal Gardens Phase 3 Bldg No 27-28?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 3 Bldg No 27-28 has 625 homes in 2 towers registered on MahaRERA, and 85% of them are sold or booked.
When was Runwal Gardens Phase 3 Bldg No 27-28 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 3 Bldg No 27-28 was registered on MahaRERA on 3 November 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on Runwal Gardens Phase 3 Bldg No 27-28?
No court cases are listed for Runwal Gardens Phase 3 Bldg No 27-28 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Runwal Gardens Phase 3 Bldg No 27-28?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Runwal Residency Private Limited, which has 17 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Runwal Gardens Phase 3 Bldg No 27-28
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in pincode 421201
- MANGESHI DAZZLE II
- Balaji Govind
- SAGAR KUNJ HIGHLAND
- Mangeshi Dhara
- VASTU HERITAGE
- NAV SAMIDHA CO-OP HSG SOC LTD
- OM TRIMURTI DARSHAN
- SWAMI ELITE
Other projects by Runwal Residency Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.