Runwal Gardens Phase 4 Bldg No. 31-32

by Runwal Residency Private Limited · Dombivli, ThaneAlso near Bhiwandi, Vidyashram

Possession date of Runwal Gardens Phase 4 Bldg No. 31-32: 31 December 2026, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700029155, and currently active. 8 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Runwal Gardens Phase 4 Bldg No. 31-32?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Runwal Gardens Phase 4 Bldg No. 31-32 has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA31122519194)

    Reason the builder gave MahaRERA:
    “We respectfully submit that the project was registered in April 2021 during the COVID-19 pandemic, and the construction progress was adversely affected due to lockdowns, severe labour shortages, supply-chain disruptions, and mandatory healt…” Read the full reason“We respectfully submit that the project was registered in April 2021 during the COVID-19 pandemic, and the construction progress was adversely affected due to lockdowns, severe labour shortages, supply-chain disruptions, and mandatory health and safety restrictions even after relaxation of lockdown measures. Excavation works were further delayed due to the presence of hard rock, which required controlled blasting and consumed additional time and resources. During basement excavation, we also observed natural water accumulation at the lowest level due to drainage from surrounding phases, req…”

Source: Runwal Gardens Phase 4 Bldg No. 31-32’s extension records on MahaRERA (P51700029155), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Runwal Gardens Phase 4 Bldg No. 31-32

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700029155
Status
Registered and active
Builder
Runwal Residency Private Limited
Location
Dombivli, Thane · 421204
Project type
Residential / Group Housing
Registered on
29 Apr 2021
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
628
Sold or booked
89%
Towers
2
Complaints on MahaRERA
8
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
17

Construction progress of Runwal Gardens Phase 4 Bldg No. 31-32, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Bldg No 31100%100%55%40%
Bldg No 32100%100%50%40%

Commencement certificate (CC), as filed on MahaRERA

  • Bldg No 31: covers 36 floors
  • Bldg No 32: covers 36 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Runwal Gardens Phase 4 Bldg No. 31-32 every month.

Runwal Gardens Phase 4 Bldg No. 31-32: buildings, flats and land, as filed on MahaRERA

  • Buildings: Bldg No 31 (36 floors, 314 units) · Bldg No 32 (36 floors, 314 units)
  • Land: 1,325 sq m (about 0.3 acres) · sanctioned built-up 43,717 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Runwal Gardens Phase 4 Bldg No. 31-32 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Runwal Gardens Phase 4 Bldg No. 31-32: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Runwal Gardens Phase 4 Bldg No. 31-32

What is the possession date of Runwal Gardens Phase 4 Bldg No. 31-32?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Runwal Gardens Phase 4 Bldg No. 31-32 in Dombivli, Thane is 31 December 2026 — 12 months later than 31 December 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Runwal Gardens Phase 4 Bldg No. 31-32?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Runwal Gardens Phase 4 Bldg No. 31-32's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Runwal Gardens Phase 4 Bldg No. 31-32 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 31-32's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We respectfully submit that the project was registered in April 2021 during the COVID-19 pandemic, and the construction progress was adversely affected due to lockdowns, severe labour shortages, supply-chain disruptions, and mandatory health and safety restrictions even after relaxation of lockdown measures. Excavation works were further delayed due to the presence of hard rock, which required controlled blasting and consumed additional time and resources. During basement excavation, we also observed natural water accumulation at the lowest level due to drainage from surrounding phases, req…".

What is the RERA number of Runwal Gardens Phase 4 Bldg No. 31-32?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Runwal Gardens Phase 4 Bldg No. 31-32 in Dombivli, Thane is P51700029155.

Is Runwal Gardens Phase 4 Bldg No. 31-32 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 31-32 is registered as P51700029155 and its status is "Registered and active".

What is the construction status of Runwal Gardens Phase 4 Bldg No. 31-32?

According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 31-32's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Runwal Gardens Phase 4 Bldg No. 31-32 have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Runwal Gardens Phase 4 Bldg No. 31-32 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 31-32 is registered on MahaRERA as P51700029155, its completion date has moved 12 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Runwal Gardens Phase 4 Bldg No. 31-32 have other wings or phases?

Yes. MahaRERA lists 14 other registrations of the same project, each with its own possession date: Runwal Gardens Phase 2 Bldg no 13-17 (P51700025677, possession 30 Jun 2025); Runwal Gardens Phase 2 Bldg no 18-23 (P51700024154, possession 30 Dec 2024); Runwal Gardens Phase 3 Bldg no 24-26 (P51700026228, possession 30 Jun 2025); Runwal Gardens Phase 3 Bldg No 27-28 (P51700026927, possession 30 Jun 2026); Runwal Gardens Phase 3 Bldg No 29-30 (P51700028344, possession 30 Jun 2026); Runwal Gardens Phase 4 Bldg No. 33-34 (P51700030533, possession 31 May 2027); and 8 more. Check that your agreement names the registration of your own wing.

How can I get updates if Runwal Gardens Phase 4 Bldg No. 31-32's possession date changes?

The latest dates are on Runwal Gardens Phase 4 Bldg No. 31-32's MahaRERA page (P51700029155). GharKundli's Kundli Watch sends a free WhatsApp update on Runwal Gardens Phase 4 Bldg No. 31-32 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Runwal Gardens Phase 4 Bldg No. 31-32 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 31-32 has 2 buildings filed: Bldg No 31 with 36 floors and 314 units; Bldg No 32 with 36 floors and 314 units.

How big is the land of Runwal Gardens Phase 4 Bldg No. 31-32?

According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 31-32 stands on 1,325 sq m of land (about 0.3 acres), with 43,717 sq m of sanctioned built-up area.

Where can I read reviews of Runwal Gardens Phase 4 Bldg No. 31-32?

Google Maps has reviews of Runwal Gardens Phase 4 Bldg No. 31-32 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Runwal Gardens Phase 4 Bldg No. 31-32?

Runwal Gardens Phase 4 Bldg No. 31-32 by Runwal Residency Private Limited is in Dombivli, Thane (pincode 421204), near Bhiwandi, Vidyashram, Maharashtra, and is registered on MahaRERA as P51700029155, per GharKundli's check of MahaRERA records.

How many homes are in Runwal Gardens Phase 4 Bldg No. 31-32?

According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 31-32 has 628 homes in 2 towers registered on MahaRERA, and 89% of them are sold or booked.

When was Runwal Gardens Phase 4 Bldg No. 31-32 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Gardens Phase 4 Bldg No. 31-32 was registered on MahaRERA on 29 April 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Runwal Gardens Phase 4 Bldg No. 31-32?

No court cases are listed for Runwal Gardens Phase 4 Bldg No. 31-32 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Runwal Gardens Phase 4 Bldg No. 31-32?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Runwal Residency Private Limited, which has 17 other projects registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Dombivli

All 252 projects in Manpada (421204) →

Other projects by Runwal Residency Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.