Mellennium Dreams

by Mellennium Dreams · Dombivli, Thane 421202

What’s in the report? →

Possession date of Mellennium Dreams (MahaRERA P51700051350): 31 July 2027, moved from 31 May 2026 (10 months later). It has 89 homes, 49% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700051350, and currently active. Its completion date has moved from May 2026 to July 2027: 10 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700051350, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Mellennium Dreams?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Mellennium Dreams has moved

  1. 31 May 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA13032620216)

    Reason the builder gave MahaRERA:
    “There were certain development control rules which allowed incentivized FSI for redevelopment of those building which are more than 30 years old. As per the prevalent development control rules at the time of the sanction of Commencement Cer…” Read the full reason“There were certain development control rules which allowed incentivized FSI for redevelopment of those building which are more than 30 years old. As per the prevalent development control rules at the time of the sanction of Commencement Certificate , the promoter got the plan sanctioned from the Competent Authority that is Kalyan Dombivli Municipal Corporation. Interestingly, at the time of grant of Occupancy Certificate, Kalyan Dombivli Municipal Corporation stopped giving incentivized FSI to those buildings which are 30 years old and accordingly stopped giving incentivized FSI to the new…”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Mellennium Dreams’s extension records on MahaRERA (P51700051350), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mellennium Dreams

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700051350
Status
Registered and active
Builder
Mellennium Dreams
Location
Dombivli, Thane · 421202
Project type
Residential / Group Housing
Registered on
8 Jun 2023
Completion date at registration
May 2026
Latest completion date
July 2027
Delay so far
10 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
89
Sold or booked
49%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Mellennium Dreams, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building no 1100%100%90%30%
Building No 2100%100%90%40%

Commencement certificate (CC), as filed on MahaRERA

  • Building no 1: covers 14 floors
  • Building No 2: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mellennium Dreams every 1–2 months.

Mellennium Dreams: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building no 1 (14 floors, 69 units) · Building No 2 (9 floors, 28 units)
  • Land: 1,671 sq m (about 0.4 acres) · sanctioned built-up 6,876 sq m
  • Land, as filed: Plot No 45 46 54 and 55 (part), Old Survey No 326/A part New Survey No 229 part
  • Map: Get directions

The builder’s record and reviews

Mellennium Dreams (a group of 3 linked companies) has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 1 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Mellennium Dreams →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mellennium Dreams: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mellennium Dreams

What is the possession date of Mellennium Dreams?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mellennium Dreams in Dombivli, Thane is 31 July 2027 — 10 months later than 31 May 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 10 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Mellennium Dreams?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mellennium Dreams's builder has filed on MahaRERA, the official one, is 31 July 2027, already 10 months later than the 31 May 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mellennium Dreams extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "There were certain development control rules which allowed incentivized FSI for redevelopment of those building which are more than 30 years old. As per the prevalent development control rules at the time of the sanction of Commencement Certificate , the promoter got the plan sanctioned from the Competent Authority that is Kalyan Dombivli Municipal Corporation. Interestingly, at the time of grant of Occupancy Certificate, Kalyan Dombivli Municipal Corporation stopped giving incentivized FSI to those buildings which are 30 years old and accordingly stopped giving incentivized FSI to the new…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Mellennium Dreams?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mellennium Dreams in Dombivli, Thane is P51700051350.

Is Mellennium Dreams registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams is registered as P51700051350 and its status is "Registered and active".

What is the current construction status of Mellennium Dreams? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Mellennium Dreams have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Mellennium Dreams safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams is registered on MahaRERA as P51700051350, its completion date has moved 10 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mellennium Dreams?

Mellennium Dreams is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Mellennium Dreams?

For a flat in Mellennium Dreams (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Mellennium Dreams received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Mellennium Dreams a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams is a redevelopment: 37 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Mellennium Dreams uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mellennium Dreams was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mellennium Dreams's possession date changes?

The latest dates are on Mellennium Dreams's MahaRERA page (P51700051350). GharKundli's Kundli Watch sends a free WhatsApp update on Mellennium Dreams every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mellennium Dreams have?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams has 2 buildings filed: Building no 1 with 14 floors and 69 units; Building No 2 with 9 floors and 28 units.

How big is the land of Mellennium Dreams?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams stands on 1,671 sq m of land (about 0.4 acres), with 6,876 sq m of sanctioned built-up area.

What is the track record of Mellennium Dreams's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams (a group of 3 linked companies) has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 1 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Mellennium Dreams?

Google Maps has reviews of Mellennium Dreams written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mellennium Dreams?

Mellennium Dreams by Mellennium Dreams is in Dombivli, Thane, pincode 421202, Maharashtra, and is registered on MahaRERA as P51700051350, per GharKundli's check of MahaRERA records. Its land is filed as Plot No 45 46 54 and 55 (part), Old Survey No 326/A part New Survey No 229 part. GharKundli lists all 226 MahaRERA projects in Vishnunagar (421202).

How many flats are in Mellennium Dreams, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams has 89 homes in 2 towers registered on MahaRERA, and 49% of them are sold or booked.

When was Mellennium Dreams registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mellennium Dreams was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.

Does Mellennium Dreams have any legal issues or court cases?

No court cases are listed for Mellennium Dreams on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Mellennium Dreams?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mellennium Dreams.

All projects with possession due in 2027 in Thane →

Other projects in Vishnunagar (421202)

All 226 projects in Vishnunagar (421202) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.