Shivaditya Shiv Prarambh
by shivaditya realty llp · Dombivli, Thane 421201Also near Shastri Nagar, Ram Nagar, Ayre VillageRegistered on MahaRERA as “SHIV PRARAMBH”
What’s in the report? →Possession date of Shivaditya Shiv Prarambh (MahaRERA P51700066515): 30 October 2027, moved from 30 June 2026 (12 months later). It has 10 homes, 64% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700066515, and currently active. Its completion date has moved from June 2026 to October 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700066515, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shivaditya Shiv Prarambh?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shivaditya Shiv Prarambh has moved
30 June 2026
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EA26062621560)
Reason the builder gave MahaRERA: “financial constraints, supply chain disruptions and same was effecting booking since last 8-9 months”
30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shivaditya Shiv Prarambh’s extension records on MahaRERA (P51700066515), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shivaditya Shiv Prarambh
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700066515
- Status
- Registered and active
- Builder
- shivaditya realty llp
- Location
- Dombivli, Thane · 421201
- Project type
- Others
- Registered on
- 11 Jun 2024
- Completion date at registration
- June 2026
- Latest completion date
- October 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 10
- Sold or booked
- 64%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shivaditya Shiv Prarambh, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHIV PRARAMBH | 100% | 60% | 30% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHIV PRARAMBH: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shivaditya Shiv Prarambh every 1–2 months.
Shivaditya Shiv Prarambh: buildings, flats and land, as filed on MahaRERA
- Buildings: SHIV PRARAMBH (6 floors, 13 units)
- Car parking: 2 covered, 2 open
- Land: 277 sq m (about 0.1 acres) · sanctioned built-up 524 sq m
- Boundaries filed include: Talcos Wadi Road
- Land, as filed: S.N. 33, old S.N. 123/1(P), H.N. 1/3, 1/D, CTS No. 1139 & 1141(P)
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shivaditya Shiv Prarambh →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shivaditya Shiv Prarambh: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shivaditya Shiv Prarambh
What is the possession date of Shivaditya Shiv Prarambh?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shivaditya Shiv Prarambh in Dombivli, Thane is 30 October 2027 — 12 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shivaditya Shiv Prarambh?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shivaditya Shiv Prarambh's builder has filed on MahaRERA, the official one, is 30 October 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shivaditya Shiv Prarambh extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivaditya Shiv Prarambh's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "financial constraints, supply chain disruptions and same was effecting booking since last 8-9 months". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shivaditya Shiv Prarambh?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shivaditya Shiv Prarambh in Dombivli, Thane is P51700066515.
Is Shivaditya Shiv Prarambh registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivaditya Shiv Prarambh is registered as P51700066515 and its status is "Registered and active".
What is the current construction status of Shivaditya Shiv Prarambh? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivaditya Shiv Prarambh's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHIV PRARAMBH is 60% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does Shivaditya Shiv Prarambh have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shivaditya Shiv Prarambh safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivaditya Shiv Prarambh is registered on MahaRERA as P51700066515, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shivaditya Shiv Prarambh?
Shivaditya Shiv Prarambh is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shivaditya Shiv Prarambh?
For a flat in Shivaditya Shiv Prarambh (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shivaditya Shiv Prarambh received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shivaditya Shiv Prarambh is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shivaditya Shiv Prarambh uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shivaditya Shiv Prarambh was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shivaditya Shiv Prarambh's possession date changes?
The latest dates are on Shivaditya Shiv Prarambh's MahaRERA page (P51700066515). GharKundli's Kundli Watch sends a free WhatsApp update on Shivaditya Shiv Prarambh every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shivaditya Shiv Prarambh have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivaditya Shiv Prarambh has one building filed: SHIV PRARAMBH with 6 floors and 13 units.
How much parking does Shivaditya Shiv Prarambh have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 2 covered and 2 open car parking spaces for Shivaditya Shiv Prarambh.
How big is the land of Shivaditya Shiv Prarambh?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivaditya Shiv Prarambh stands on 277 sq m of land (about 0.1 acres), with 524 sq m of sanctioned built-up area.
What are the reviews of Shivaditya Shiv Prarambh?
Google Maps has reviews of Shivaditya Shiv Prarambh written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shivaditya Shiv Prarambh?
Shivaditya Shiv Prarambh by shivaditya realty llp is in Dombivli, Thane, pincode 421201 (near Shastri Nagar, Ram Nagar, Ayre Village), Maharashtra, and is registered on MahaRERA as P51700066515, per GharKundli's check of MahaRERA records. Its boundaries filed there include Talcos Wadi Road. Its land is filed as S.N. 33, old S.N. 123/1(P), H.N. 1/3, 1/D, CTS No. 1139 & 1141(P). GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).
How many flats are in Shivaditya Shiv Prarambh, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivaditya Shiv Prarambh has 10 homes in 1 tower registered on MahaRERA, and 64% of them are sold or booked.
When was Shivaditya Shiv Prarambh registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivaditya Shiv Prarambh was registered on MahaRERA on 11 June 2024. GharKundli did not find a title report on the land on file there.
Does Shivaditya Shiv Prarambh have any legal issues or court cases?
No court cases are listed for Shivaditya Shiv Prarambh on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shivaditya Shiv Prarambh?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is shivaditya realty llp.
Check it yourself on MahaRERA
- How to check the possession date of Shivaditya Shiv Prarambh
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Tilaknagar (421201)
- Swami Elite
- Mangeshi Dazzle II
- Sagar Kunj Highland
- Om Trimurti Darshan
- Balaji Govind
- Vastu Heritage
- Mangeshi Dhara
- Nav Samidha Co-op HSG Soc LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.