Regency Anantam NXT Phase I

by REGENCY NIRMAN LTD · Dombivli, Thane 421203

What’s in the report? →

Possession date of Regency Anantam NXT Phase I (MahaRERA P51700055848): 30 April 2029, moved from 31 December 2027 (12 months later). It has 832 homes, 58% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700055848, and currently active. Its completion date has moved from December 2027 to April 2029: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700055848, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Regency Anantam NXT Phase I?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Regency Anantam NXT Phase I has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA11032620185)

    Reason the builder gave MahaRERA:
    “We hereby apply for extension under Section 6 of the RERA Act, 2016 seeking extension till 31/12/2028. The delay in completion of the Project/seeking extension of the timeline, has occurred primarily on account of delay in obtaining the Env…” Read the full reason“We hereby apply for extension under Section 6 of the RERA Act, 2016 seeking extension till 31/12/2028. The delay in completion of the Project/seeking extension of the timeline, has occurred primarily on account of delay in obtaining the Environmental Clearance (“EC”) which arose due to regulatory changes and judicial directions issued during the approval process, which were entirely beyond our control. The events leading to the said delay is detailed in the submitted documents for the kind consideration of the Authority.”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Regency Anantam NXT Phase I’s extension records on MahaRERA (P51700055848), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Regency Anantam NXT Phase I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700055848
Status
Registered and active
Builder
REGENCY NIRMAN LTD
Location
Dombivli, Thane · 421203
Project type
Residential / Group Housing
Registered on
23 Apr 2024
Completion date at registration
December 2027
Latest completion date
April 2029
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
832
Sold or booked
58%
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
28

Construction progress of Regency Anantam NXT Phase I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1100%9.4%0%0%
BUILDING NO 2100%6.24%0%0%
BUILDING NO 790%0%0%0%
BUILDING NO 8100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING NO 1: covers 28 floors
  • BUILDING NO 2: covers 28 floors
  • BUILDING NO 7: covers 24 floors
  • BUILDING NO 8: covers 24 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Regency Anantam NXT Phase I every 1–2 months.

Regency Anantam NXT Phase I: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 1 (32 floors, 224 units) · BUILDING NO 2 (32 floors, 224 units) · BUILDING NO 7 (28 floors, 192 units) · BUILDING NO 8 (28 floors, 192 units)
  • Car parking: 508 covered, 7 open
  • Land: 33,691 sq m (about 8.3 acres) · sanctioned built-up 67,842 sq m · recreational space 3,638 sq m
  • Land, as filed: Survey No 64, 65/3, 65/4, 65/5, 66/1, 67/4B, 102/5A, 102/5B, 102/7, 102/9,102/10
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Regency Nirman (a group of 2 linked companies) has 33 projects on MahaRERA since 2017, this one included. Of the 33 GharKundli has checked: 25 finished, 20 within the promised date and 5 needed more time (typically 12 months); 6 still being built, 1 past the promised date (typically 10 months late); 2 lapsed. 9 complaints on MahaRERA across 8 projects.

Read Google reviews of Regency Anantam NXT Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Regency Anantam NXT Phase I: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Regency Anantam NXT Phase I

What is the possession date of Regency Anantam NXT Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Regency Anantam NXT Phase I in Dombivli, Thane is 30 April 2029 — 12 months later than 31 December 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Regency Anantam NXT Phase I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Regency Anantam NXT Phase I's builder has filed on MahaRERA, the official one, is 30 April 2029, already 12 months later than the 31 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Regency Anantam NXT Phase I extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Anantam NXT Phase I's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "We hereby apply for extension under Section 6 of the RERA Act, 2016 seeking extension till 31/12/2028. The delay in completion of the Project/seeking extension of the timeline, has occurred primarily on account of delay in obtaining the Environmental Clearance (“EC”) which arose due to regulatory changes and judicial directions issued during the approval process, which were entirely beyond our control. The events leading to the said delay is detailed in the submitted documents for the kind consideration of the Authority.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Regency Anantam NXT Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Regency Anantam NXT Phase I in Dombivli, Thane is P51700055848.

Is Regency Anantam NXT Phase I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Anantam NXT Phase I is registered as P51700055848 and its status is "Registered and active".

What is the current construction status of Regency Anantam NXT Phase I? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Anantam NXT Phase I's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 9.4% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Regency Anantam NXT Phase I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Regency Anantam NXT Phase I safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Anantam NXT Phase I is registered on MahaRERA as P51700055848, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Regency Anantam NXT Phase I?

Regency Anantam NXT Phase I is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Regency Anantam NXT Phase I?

For a flat in Regency Anantam NXT Phase I (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Regency Anantam NXT Phase I received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Regency Anantam NXT Phase I is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Regency Anantam NXT Phase I uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Regency Anantam NXT Phase I was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Regency Anantam NXT Phase I's possession date changes?

The latest dates are on Regency Anantam NXT Phase I's MahaRERA page (P51700055848). GharKundli's Kundli Watch sends a free WhatsApp update on Regency Anantam NXT Phase I every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Regency Anantam NXT Phase I have?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Anantam NXT Phase I has 4 buildings filed: BUILDING NO 1 with 32 floors and 224 units; BUILDING NO 2 with 32 floors and 224 units; BUILDING NO 7 with 28 floors and 192 units; BUILDING NO 8 with 28 floors and 192 units.

How much parking does Regency Anantam NXT Phase I have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 508 covered and 7 open car parking spaces for Regency Anantam NXT Phase I.

How big is the land of Regency Anantam NXT Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Anantam NXT Phase I stands on 33,691 sq m of land (about 8.3 acres), with 67,842 sq m of sanctioned built-up area and 3,638 sq m of recreational open space.

What is the track record of Regency Anantam NXT Phase I's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Nirman (a group of 2 linked companies) has 33 projects on MahaRERA since 2017, this one included. Of the 33 GharKundli has checked: 25 finished, 20 within the promised date and 5 needed more time (typically 12 months); 6 still being built, 1 past the promised date (typically 10 months late); 2 lapsed. 9 complaints on MahaRERA across 8 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Regency Anantam NXT Phase I?

Google Maps has reviews of Regency Anantam NXT Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Regency Anantam NXT Phase I?

Regency Anantam NXT Phase I by REGENCY NIRMAN LTD is in Dombivli, Thane, pincode 421203, Maharashtra, and is registered on MahaRERA as P51700055848, per GharKundli's check of MahaRERA records. Its land is filed as Survey No 64, 65/3, 65/4, 65/5, 66/1, 67/4B, 102/5A, 102/5B, 102/7, 102/9,102/10. GharKundli lists all 98 MahaRERA projects in Dombivali (421203).

How many flats are in Regency Anantam NXT Phase I, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Anantam NXT Phase I has 832 homes in 4 towers registered on MahaRERA, and 58% of them are sold or booked.

When was Regency Anantam NXT Phase I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Anantam NXT Phase I was registered on MahaRERA on 23 April 2024. GharKundli did not find a title report on the land on file there.

Does Regency Anantam NXT Phase I have any legal issues or court cases?

No court cases are listed for Regency Anantam NXT Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Regency Anantam NXT Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is REGENCY NIRMAN LTD, which has 28 other projects registered on MahaRERA.

All projects with possession due in 2029 in Thane →

Other projects in Dombivali (421203)

All 98 projects in Dombivali (421203) →

Other projects by REGENCY NIRMAN LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.