LAXMI CASTLE
by ARIHANT ENTERPRISES · Tukaram Nagar, ThaneAlso near Borivali West, Dombivli East, Bhiwandi
Possession date of LAXMI CASTLE: 28 December 2028, moved from 31 May 2024 (55 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700029322, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about LAXMI CASTLE?
How the possession date of LAXMI CASTLE has moved
31 May 2024
Completion date given when the project was registered
28 December 2028
Extended at the builder's request (MahaRERA application EA26032620391)
Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”
Source: LAXMI CASTLE’s extension records on MahaRERA (P51700029322), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on LAXMI CASTLE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700029322
- Status
- Registered and active
- Builder
- ARIHANT ENTERPRISES
- Location
- Tukaram Nagar, Thane · 421203
- Project type
- Others
- Registered on
- 18 May 2021
- Completion date at registration
- May 2024
- Latest completion date
- December 2028
- Delay so far
- 55 months
- Homes
- 17
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 17
Construction progress of LAXMI CASTLE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| LAXMI CASTLE | 100% | 67% | 47% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- LAXMI CASTLE: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on LAXMI CASTLE every month.
LAXMI CASTLE: buildings, flats and land, as filed on MahaRERA
- Buildings: LAXMI CASTLE (48 floors, 21 units)
- Land: 900 sq m (about 0.2 acres) · sanctioned built-up 847 sq m · recreational space 847 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of LAXMI CASTLE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
LAXMI CASTLE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LAXMI CASTLE
What is the possession date of LAXMI CASTLE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LAXMI CASTLE in Tukaram Nagar, Thane is 28 December 2028 — 55 months later than 31 May 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for LAXMI CASTLE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date LAXMI CASTLE's builder has filed on MahaRERA, the official one, is 28 December 2028, already 55 months later than the 31 May 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of LAXMI CASTLE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI CASTLE's builder applied to MahaRERA to extend the completion date once: to 28 December 2028, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.".
What is the RERA number of LAXMI CASTLE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LAXMI CASTLE in Tukaram Nagar, Thane is P51700029322.
Is LAXMI CASTLE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI CASTLE is registered as P51700029322 and its status is "Registered and active".
What is the construction status of LAXMI CASTLE?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI CASTLE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on LAXMI CASTLE is 67% done and internal work 47%. GharKundli's full report compares construction progress with the deadline.
Does LAXMI CASTLE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is LAXMI CASTLE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI CASTLE is registered on MahaRERA as P51700029322, its completion date has moved 55 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if LAXMI CASTLE's possession date changes?
The latest dates are on LAXMI CASTLE's MahaRERA page (P51700029322). GharKundli's Kundli Watch sends a free WhatsApp update on LAXMI CASTLE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does LAXMI CASTLE have?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI CASTLE has one building filed: LAXMI CASTLE with 48 floors and 21 units.
How big is the land of LAXMI CASTLE?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI CASTLE stands on 900 sq m of land (about 0.2 acres), with 847 sq m of sanctioned built-up area and 847 sq m of recreational open space.
Where can I read reviews of LAXMI CASTLE?
Google Maps has reviews of LAXMI CASTLE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is LAXMI CASTLE?
LAXMI CASTLE by ARIHANT ENTERPRISES is in Tukaram Nagar, Thane (pincode 421203), near Borivali West, Dombivli East, Bhiwandi, Maharashtra, and is registered on MahaRERA as P51700029322, per GharKundli's check of MahaRERA records.
How many homes are in LAXMI CASTLE?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI CASTLE has 17 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was LAXMI CASTLE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI CASTLE was registered on MahaRERA on 18 May 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on LAXMI CASTLE?
No court cases are listed for LAXMI CASTLE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of LAXMI CASTLE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT ENTERPRISES, which has 17 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of LAXMI CASTLE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Kalyan
- Velstand Phase 2 - formerly Kul scapes
- MAJESTY HEIGHTS
- Royal Hills
- VIDHI IMPRESSION
- Mangeshi Dhara
- SWAMI ELITE
- Balaji Govind
- OM TRIMURTI DARSHAN
Other projects by ARIHANT ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.