Possession date of Arihantcity Phase-i - D3 - Building (MahaRERA P51700022743): 31 December 2027, moved from 30 December 2025 (24 months later). It has 195 homes, 71% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700022743, and currently active.

Source: MahaRERA website — records for P51700022743, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Arihantcity Phase-i - D3 - Building?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Arihantcity Phase-i - D3 - Building has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA09122518583)

    Reason the builder gave MahaRERA:
    “Due to dispute between the partners of our firm a crime register number 775/2023 has been lodged by erstwhile partner Mr. Parakumar Jain with the Shantinagar Police Station Bhiwandi against the continuing partners namely Mr. Dansing Mawri a…” Read the full reason“Due to dispute between the partners of our firm a crime register number 775/2023 has been lodged by erstwhile partner Mr. Parakumar Jain with the Shantinagar Police Station Bhiwandi against the continuing partners namely Mr. Dansing Mawri and two others and the Hon’ble Sessions Judge Thane granted interim bail thereof. All the bank accounts of our firm have been freezed during the course of investigation and the investigation officer has prevented us from doing any correspondence for and on behalf of firm and also not to execute and register any documents and to do any work related to the p…”

Source: Arihantcity Phase-i - D3 - Building’s extension records on MahaRERA (P51700022743), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Arihantcity Phase-i - D3 - Building

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700022743
Status
Registered and active
Builder
ARIHANT ENTERPRISES
Location
Bhiwandi, Thane · 421302
Project type
Residential / Group Housing
Registered on
16 Oct 2019
Completion date at registration
December 2025
Latest completion date
December 2027
Delay so far
24 months
Homes
195
Sold or booked
71%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
17

Construction progress of Arihantcity Phase-i - D3 - Building, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
D-3 BUILDING100%70%35%0%

Commencement certificate (CC), as filed on MahaRERA

  • D-3 BUILDING: covers 28 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Arihantcity Phase-i - D3 - Building every 1–2 months.

Arihantcity Phase-i - D3 - Building: buildings, flats and land, as filed on MahaRERA

  • Buildings: D-3 BUILDING (30 floors, 207 units)
  • Land: 3,415 sq m (about 0.8 acres) · sanctioned built-up 7,684 sq m · recreational space 685 sq m
  • Boundaries filed include: 60 M WDP ROAD
  • Land, as filed: 116/1P 116/2P 118/7 118/9 118/11P 119/1P 119/1P 119/2P 119/2P 119/4 119/8P
  • Map: Get directions

The builder’s record and reviews

Arihant Enterprises has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 1 past the promised date (typically 4 months late); 2 lapsed. 6 complaints on MahaRERA across 1 project.

Read Google reviews of Arihantcity Phase-i - D3 - Building →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Arihantcity Phase-i - D3 - Building: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Arihantcity Phase-i - D3 - Building

What is the possession date of Arihantcity Phase-i - D3 - Building?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Arihantcity Phase-i - D3 - Building in Bhiwandi, Thane is 31 December 2027 — 24 months later than 30 December 2025, the date given at registration.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Arihantcity Phase-i - D3 - Building?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Arihantcity Phase-i - D3 - Building's builder has filed on MahaRERA, the official one, is 31 December 2027, already 24 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Arihantcity Phase-i - D3 - Building extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihantcity Phase-i - D3 - Building's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Due to dispute between the partners of our firm a crime register number 775/2023 has been lodged by erstwhile partner Mr. Parakumar Jain with the Shantinagar Police Station Bhiwandi against the continuing partners namely Mr. Dansing Mawri and two others and the Hon’ble Sessions Judge Thane granted interim bail thereof. All the bank accounts of our firm have been freezed during the course of investigation and the investigation officer has prevented us from doing any correspondence for and on behalf of firm and also not to execute and register any documents and to do any work related to the p…".

What is the RERA number of Arihantcity Phase-i - D3 - Building?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Arihantcity Phase-i - D3 - Building in Bhiwandi, Thane is P51700022743.

Is Arihantcity Phase-i - D3 - Building registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihantcity Phase-i - D3 - Building is registered as P51700022743 and its status is "Registered and active".

What is the current construction status of Arihantcity Phase-i - D3 - Building? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihantcity Phase-i - D3 - Building's status on MahaRERA is "Registered and active". As filed by the builder, slab work on D-3 BUILDING is 70% done and internal work 35%. GharKundli's full report compares construction progress with the deadline.

Does Arihantcity Phase-i - D3 - Building have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Arihantcity Phase-i - D3 - Building safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihantcity Phase-i - D3 - Building is registered on MahaRERA as P51700022743, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Arihantcity Phase-i - D3 - Building?

Arihantcity Phase-i - D3 - Building is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Arihantcity Phase-i - D3 - Building?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Arihantcity Phase-i - D3 - Building: gharkundli.com/tools/property-cost-calculator

Has Arihantcity Phase-i - D3 - Building received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Arihantcity Phase-i - D3 - Building is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Arihantcity Phase-i - D3 - Building uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Arihantcity Phase-i - D3 - Building was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Arihantcity Phase-i - D3 - Building's possession date changes?

The latest dates are on Arihantcity Phase-i - D3 - Building's MahaRERA page (P51700022743). GharKundli's Kundli Watch sends a free WhatsApp update on Arihantcity Phase-i - D3 - Building every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Arihantcity Phase-i - D3 - Building have?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihantcity Phase-i - D3 - Building has one building filed: D-3 BUILDING with 30 floors and 207 units.

How big is the land of Arihantcity Phase-i - D3 - Building?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihantcity Phase-i - D3 - Building stands on 3,415 sq m of land (about 0.8 acres), with 7,684 sq m of sanctioned built-up area and 685 sq m of recreational open space.

What is the track record of Arihantcity Phase-i - D3 - Building's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihant Enterprises has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 1 past the promised date (typically 4 months late); 2 lapsed. 6 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Arihantcity Phase-i - D3 - Building?

Google Maps has reviews of Arihantcity Phase-i - D3 - Building written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Arihantcity Phase-i - D3 - Building?

Arihantcity Phase-i - D3 - Building by ARIHANT ENTERPRISES is in Bhiwandi, Thane, pincode 421302, Maharashtra, and is registered on MahaRERA as P51700022743, per GharKundli's check of MahaRERA records. Its boundaries filed there include 60 M WDP ROAD. Its land is filed as 116/1P 116/2P 118/7 118/9 118/11P 119/1P 119/1P 119/2P 119/2P 119/4 119/8P. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Arihantcity Phase-i - D3 - Building, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihantcity Phase-i - D3 - Building has 195 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.

When was Arihantcity Phase-i - D3 - Building registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihantcity Phase-i - D3 - Building was registered on MahaRERA on 16 October 2019. GharKundli did not find a title report on the land on file there.

Does Arihantcity Phase-i - D3 - Building have any legal issues or court cases?

No court cases are listed for Arihantcity Phase-i - D3 - Building on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Arihantcity Phase-i - D3 - Building?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT ENTERPRISES, which has 17 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Bhiwandi (421302)

All 382 projects in Bhiwandi (421302) →

Other projects by ARIHANT ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.