Possession date of SAMRUDDHI FLORA: 30 January 2027, moved from 30 July 2024 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700053740, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAMRUDDHI FLORA?
How the possession date of SAMRUDDHI FLORA has moved
30 July 2024
Completion date given when the project was registered
30 July 2025
Extended at the builder's request (MahaRERA application EXT51700024063)
Reason the builder gave MahaRERA: “Dear Team , All documents submitted, please process our application”
30 January 2026
Extended at the builder's request (MahaRERA application EA24072502182)
Reason the builder gave MahaRERA: “Dear Team, We need 6 month extension for our project , we are already near to our completion of our project.”
30 January 2027
Extended at the builder's request (MahaRERA application EA16062621393)
Reason the builder gave MahaRERA: “Dear Team, we are already near to our completion of our project.Our project is expected to receive its Occupancy Certificate (OC) very soon. Please extend project date.”
Source: SAMRUDDHI FLORA’s extension records on MahaRERA (P51700053740), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAMRUDDHI FLORA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700053740
- Status
- Registered and active
- Builder
- SAMRUDDHI BUILDCON
- Location
- Bhiwandi, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 28 Nov 2023
- Completion date at registration
- July 2024
- Latest completion date
- January 2027
- Delay so far
- 30 months
- Homes
- 38
- Sold or booked
- 74%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of SAMRUDDHI FLORA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAMRUDDHI FLORA | 100% | 100% | 95% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- SAMRUDDHI FLORA: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAMRUDDHI FLORA every month.
SAMRUDDHI FLORA: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 353 | 24 |
| 2 BHK | 457 – 484 | 14 |
| Shops | 124 – 150 | 4 |
- Buildings: SAMRUDDHI FLORA (6 floors, 42 units)
- Car parking: 11 covered
- Land: 1,100 sq m (about 0.3 acres) · sanctioned built-up 1,942 sq m · recreational space 158 sq m
- Boundaries filed include: DEVRUNG PADA ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAMRUDDHI FLORA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAMRUDDHI FLORA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAMRUDDHI FLORA
What is the possession date of SAMRUDDHI FLORA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAMRUDDHI FLORA in Bhiwandi, Thane is 30 January 2027 — 30 months later than 30 July 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SAMRUDDHI FLORA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAMRUDDHI FLORA's builder has filed on MahaRERA, the official one, is 30 January 2027, already 30 months later than the 30 July 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAMRUDDHI FLORA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMRUDDHI FLORA's builder applied to MahaRERA to extend the completion date 3 times: to 30 July 2025, giving the reason "Dear Team , All documents submitted, please process our application"; to 30 January 2026, giving the reason "Dear Team, We need 6 month extension for our project , we are already near to our completion of our project."; to 30 January 2027, giving the reason "Dear Team, we are already near to our completion of our project.Our project is expected to receive its Occupancy Certificate (OC) very soon. Please extend project date.".
What is the RERA number of SAMRUDDHI FLORA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAMRUDDHI FLORA in Bhiwandi, Thane is P51700053740.
Is SAMRUDDHI FLORA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMRUDDHI FLORA is registered as P51700053740 and its status is "Registered and active".
What is the construction status of SAMRUDDHI FLORA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMRUDDHI FLORA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAMRUDDHI FLORA is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does SAMRUDDHI FLORA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SAMRUDDHI FLORA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMRUDDHI FLORA is registered on MahaRERA as P51700053740, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAMRUDDHI FLORA's possession date changes?
The latest dates are on SAMRUDDHI FLORA's MahaRERA page (P51700053740). GharKundli's Kundli Watch sends a free WhatsApp update on SAMRUDDHI FLORA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAMRUDDHI FLORA have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMRUDDHI FLORA has one building filed: SAMRUDDHI FLORA with 6 floors and 42 units.
What are the flat sizes (carpet area) in SAMRUDDHI FLORA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAMRUDDHI FLORA: 1 BHK: 353 sq ft carpet (24 homes); 2 BHK: 457 to 484 sq ft carpet (14 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SAMRUDDHI FLORA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 11 covered car parking spaces for SAMRUDDHI FLORA.
How big is the land of SAMRUDDHI FLORA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMRUDDHI FLORA stands on 1,100 sq m of land (about 0.3 acres), with 1,942 sq m of sanctioned built-up area and 158 sq m of recreational open space.
Where can I read reviews of SAMRUDDHI FLORA?
Google Maps has reviews of SAMRUDDHI FLORA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAMRUDDHI FLORA?
SAMRUDDHI FLORA by SAMRUDDHI BUILDCON is in Bhiwandi, Thane (pincode 421302), Maharashtra, and is registered on MahaRERA as P51700053740, per GharKundli's check of MahaRERA records. Its boundaries filed there include DEVRUNG PADA ROAD.
How many homes are in SAMRUDDHI FLORA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMRUDDHI FLORA has 38 homes in 1 tower registered on MahaRERA, and 74% of them are sold or booked.
When was SAMRUDDHI FLORA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMRUDDHI FLORA was registered on MahaRERA on 28 November 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SAMRUDDHI FLORA?
No court cases are listed for SAMRUDDHI FLORA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAMRUDDHI FLORA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAMRUDDHI BUILDCON, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAMRUDDHI FLORA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Bhiwandi
- SKORA ML GOLDEN PALMS
- NEELKANTH PALMS
- USHA RESIDENCY
- STAR HOMES
- OM SAI ONE PARK
- KALYAN SQUARE
- DEEP LAXMI HEIGHT
- NANDAI RESIDENCY
Other projects by SAMRUDDHI BUILDCON
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.