Budhdev Usha Residency

by SHREE BUDHDEV INFRA · Bhiwandi, Thane 421302Also near KaneriRegistered on MahaRERA as “USHA RESIDENCY”

What’s in the report? →

Possession date of Budhdev Usha Residency (MahaRERA P51700053334): 28 February 2027, moved from 31 December 2025 (10 months later). It has 997 homes, 92% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700053334, and currently active. Its completion date has moved from December 2025 to February 2027: 10 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700053334, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Budhdev Usha Residency?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Budhdev Usha Residency has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA08012619357)

    Reason the builder gave MahaRERA:
    “1) Minor finishing works related to the project buildings are currently pending and are in the final stages of completion. 2) Certain internal and external development works associated with the common areas and facility amenities of the pro…” Read the full reason“1) Minor finishing works related to the project buildings are currently pending and are in the final stages of completion. 2) Certain internal and external development works associated with the common areas and facility amenities of the project are pending completion and are being carried out in a phased and systematic manner. 3) We are in the process of preparing and submitting the application for the Occupation Certificate for the project to the concerned statutory authorities, and the same will be pursued in accordance with applicable regulations.”
  3. 30 October 2026

    Extended at the builder's request (MahaRERA application EA24072621863)

    Reason the builder gave MahaRERA:
    “THE PROJECT CONSISTS OF 3 BUILDINGS NAMELY, BUILDING 1 ,2 AND 3 - BUILDING 1 AND 2 HAS RECEIVED PART OCCUPATION CERTIFICATE AS ON DATED 10/06/2026 HAVING NO. EE/BP/PMAY/A/MHADA/E-9153545/2026 - BUILDING 3 - APPLICAION FOR OCCUPATION CERTFIC…” Read the full reason“THE PROJECT CONSISTS OF 3 BUILDINGS NAMELY, BUILDING 1 ,2 AND 3 - BUILDING 1 AND 2 HAS RECEIVED PART OCCUPATION CERTIFICATE AS ON DATED 10/06/2026 HAVING NO. EE/BP/PMAY/A/MHADA/E-9153545/2026 - BUILDING 3 - APPLICAION FOR OCCUPATION CERTFICATE IS IN PROCESS.”
  4. 28 February 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Budhdev Usha Residency’s extension records on MahaRERA (P51700053334), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Budhdev Usha Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700053334
Status
Registered and active
Builder
SHREE BUDHDEV INFRA
Location
Bhiwandi, Thane · 421302
Project type
Others
Registered on
27 Oct 2023
Completion date at registration
December 2025
Latest completion date
February 2027
Delay so far
10 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
997
Sold or booked
92%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Budhdev Usha Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
USHA RESIDENCY BUILDING NO 1100%100%100%100%
USHA RESIDENCY BUILDING NO 2100%100%100%100%
USHA RESIDENCY BUILDING NO 3100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • USHA RESIDENCY BUILDING NO 1: covers 15 floors
  • USHA RESIDENCY BUILDING NO 2: covers 15 floors
  • USHA RESIDENCY BUILDING NO 3: covers 15 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Budhdev Usha Residency every 1–2 months.

Budhdev Usha Residency: buildings, flats and land, as filed on MahaRERA

  • Buildings: USHA RESIDENCY BUILDING NO 1 (15 floors, 360 units) · USHA RESIDENCY BUILDING NO 2 (15 floors, 383 units) · USHA RESIDENCY BUILDING NO 3 (15 floors, 277 units)
  • Car parking: 7 covered
  • Land: 9,850 sq m (about 2.4 acres) · sanctioned built-up 41,939 sq m · recreational space 986 sq m
  • Land, as filed: SURVEY NO 18 HISSA NO 10
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Vidishabuildcon (a group of 3 linked companies) has 3 projects on MahaRERA since 2023, this one included. Of the 3 GharKundli has checked: 3 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA.

Read Google reviews of Budhdev Usha Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Budhdev Usha Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Budhdev Usha Residency

What is the possession date of Budhdev Usha Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Budhdev Usha Residency in Bhiwandi, Thane is 28 February 2027 — 10 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 10 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Budhdev Usha Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Budhdev Usha Residency's builder has filed on MahaRERA, the official one, is 28 February 2027, already 10 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Budhdev Usha Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Budhdev Usha Residency's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "1) Minor finishing works related to the project buildings are currently pending and are in the final stages of completion. 2) Certain internal and external development works associated with the common areas and facility amenities of the project are pending completion and are being carried out in a phased and systematic manner. 3) We are in the process of preparing and submitting the application for the Occupation Certificate for the project to the concerned statutory authorities, and the same will be pursued in accordance with applicable regulations."; to 30 October 2026, giving the reason "THE PROJECT CONSISTS OF 3 BUILDINGS NAMELY, BUILDING 1 ,2 AND 3 - BUILDING 1 AND 2 HAS RECEIVED PART OCCUPATION CERTIFICATE AS ON DATED 10/06/2026 HAVING NO. EE/BP/PMAY/A/MHADA/E-9153545/2026 - BUILDING 3 - APPLICAION FOR OCCUPATION CERTFICATE IS IN PROCESS.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Budhdev Usha Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Budhdev Usha Residency in Bhiwandi, Thane is P51700053334.

Is Budhdev Usha Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Budhdev Usha Residency is registered as P51700053334 and its status is "Registered and active".

What is the current construction status of Budhdev Usha Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Budhdev Usha Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Budhdev Usha Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Budhdev Usha Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Budhdev Usha Residency is registered on MahaRERA as P51700053334, its completion date has moved 10 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Budhdev Usha Residency?

Budhdev Usha Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Budhdev Usha Residency?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Budhdev Usha Residency: gharkundli.com/tools/property-cost-calculator

Has Budhdev Usha Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Budhdev Usha Residency is still under construction, with 28 February 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Budhdev Usha Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Budhdev Usha Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Budhdev Usha Residency's possession date changes?

The latest dates are on Budhdev Usha Residency's MahaRERA page (P51700053334). GharKundli's Kundli Watch sends a free WhatsApp update on Budhdev Usha Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Budhdev Usha Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Budhdev Usha Residency has 3 buildings filed: USHA RESIDENCY BUILDING NO 1 with 15 floors and 360 units; USHA RESIDENCY BUILDING NO 2 with 15 floors and 383 units; USHA RESIDENCY BUILDING NO 3 with 15 floors and 277 units.

How much parking does Budhdev Usha Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 7 covered car parking spaces for Budhdev Usha Residency.

How big is the land of Budhdev Usha Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Budhdev Usha Residency stands on 9,850 sq m of land (about 2.4 acres), with 41,939 sq m of sanctioned built-up area and 986 sq m of recreational open space.

What is the track record of Budhdev Usha Residency's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vidishabuildcon (a group of 3 linked companies) has 3 projects on MahaRERA since 2023, this one included. Of the 3 GharKundli has checked: 3 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Budhdev Usha Residency?

Google Maps has reviews of Budhdev Usha Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Budhdev Usha Residency?

Budhdev Usha Residency by SHREE BUDHDEV INFRA is in Bhiwandi, Thane, pincode 421302 (near Kaneri), Maharashtra, and is registered on MahaRERA as P51700053334, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 18 HISSA NO 10. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Budhdev Usha Residency, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Budhdev Usha Residency has 997 homes in 3 towers registered on MahaRERA, and 92% of them are sold or booked.

When was Budhdev Usha Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Budhdev Usha Residency was registered on MahaRERA on 27 October 2023. GharKundli did not find a title report on the land on file there.

Does Budhdev Usha Residency have any legal issues or court cases?

No court cases are listed for Budhdev Usha Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Budhdev Usha Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE BUDHDEV INFRA.

All projects with possession due in 2027 in Thane →

Other projects in Bhiwandi (421302)

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.