KALYAN SQUARE
by KAGVIN VENTURES · Bhiwandi, Thane
Possession date of KALYAN SQUARE: 31 December 2027, moved from 31 December 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700048508, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about KALYAN SQUARE?
How the possession date of KALYAN SQUARE has moved
31 December 2024
Completion date given when the project was registered
30 November 2025
Extended at the builder's request (MahaRERA application EXT51700025184)
Reason the builder gave MahaRERA:
“We Would like to request you that the Project KALYAN SQUARE which is located at SURVEY NO. 250/5/A/PT at KONGAON (CT), Bhiwandi, Thane, 421301 having its Registration No P51700048508 was mentioned to be completed on 31/12/2024 Due to below…” Read the full reason
“We Would like to request you that the Project KALYAN SQUARE which is located at SURVEY NO. 250/5/A/PT at KONGAON (CT), Bhiwandi, Thane, 421301 having its Registration No P51700048508 was mentioned to be completed on 31/12/2024 Due to below reasons project was not able to get completed on time 1) GOVERNMENT APPROVAL: The said property comes under the limit of Kongaon Grampanchayat and Sanctioning Authority is MMRDA. The Road comes under PWD and due to lack of cordination between both the Government Agencies the Project was not able to complete on time, because of lack of approvals. Even as o…”31 December 2027
Extended at the builder's request (MahaRERA application EA22052621066)
Reason the builder gave MahaRERA:
“We, KAGVIN VENTURES, are the promoters of the real estate project known as "KALYAN SQUARE" bearing Maha RERA Registration No. P51700048508. Reason We would like to respectfully inform you that the reason for applying for the RERA extension…” Read the full reason
“We, KAGVIN VENTURES, are the promoters of the real estate project known as "KALYAN SQUARE" bearing Maha RERA Registration No. P51700048508. Reason We would like to respectfully inform you that the reason for applying for the RERA extension is solely due to the pending Occupation Certificate (OC) process. The construction work is substantially completed, however, the OC application process and issuance of the final OC certificate are still under process with the concerned authority. Therefore, the extension is being sought only to complete the remaining statutory compliances and obtain the f…”
Source: KALYAN SQUARE’s extension records on MahaRERA (P51700048508), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KALYAN SQUARE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700048508
- Status
- Registered and active
- Builder
- KAGVIN VENTURES
- Location
- Bhiwandi, Thane · 421301
- Project type
- Commercial
- Registered on
- 3 Jan 2023
- Completion date at registration
- December 2024
- Latest completion date
- December 2027
- Delay so far
- 36 months
- Homes
- 0
- Sold or booked
- 84%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of KALYAN SQUARE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KALYAN SQUARE | 100% | 54% | 50% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- KALYAN SQUARE: covers GROUND + 6TH UPPER FLOORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KALYAN SQUARE every month.
KALYAN SQUARE: buildings, flats and land, as filed on MahaRERA
- Buildings: KALYAN SQUARE (7 floors, 44 units)
- Land: 1,300 sq m (about 0.3 acres) · sanctioned built-up 2,469 sq m
The builder’s record and reviews
OM Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of KALYAN SQUARE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KALYAN SQUARE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KALYAN SQUARE
What is the possession date of KALYAN SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KALYAN SQUARE in Bhiwandi, Thane is 31 December 2027 — 36 months later than 31 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for KALYAN SQUARE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KALYAN SQUARE's builder has filed on MahaRERA, the official one, is 31 December 2027, already 36 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KALYAN SQUARE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN SQUARE's builder applied to MahaRERA to extend the completion date 2 times: to 30 November 2025, giving the reason "We Would like to request you that the Project KALYAN SQUARE which is located at SURVEY NO. 250/5/A/PT at KONGAON (CT), Bhiwandi, Thane, 421301 having its Registration No P51700048508 was mentioned to be completed on 31/12/2024 Due to below reasons project was not able to get completed on time 1) GOVERNMENT APPROVAL: The said property comes under the limit of Kongaon Grampanchayat and Sanctioning Authority is MMRDA. The Road comes under PWD and due to lack of cordination between both the Government Agencies the Project was not able to complete on time, because of lack of approvals. Even as o…"; to 31 December 2027, giving the reason "We, KAGVIN VENTURES, are the promoters of the real estate project known as "KALYAN SQUARE" bearing Maha RERA Registration No. P51700048508. Reason We would like to respectfully inform you that the reason for applying for the RERA extension is solely due to the pending Occupation Certificate (OC) process. The construction work is substantially completed, however, the OC application process and issuance of the final OC certificate are still under process with the concerned authority. Therefore, the extension is being sought only to complete the remaining statutory compliances and obtain the f…".
What is the RERA number of KALYAN SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KALYAN SQUARE in Bhiwandi, Thane is P51700048508.
Is KALYAN SQUARE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN SQUARE is registered as P51700048508 and its status is "Registered and active".
What is the construction status of KALYAN SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN SQUARE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KALYAN SQUARE is 54% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does KALYAN SQUARE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KALYAN SQUARE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN SQUARE is registered on MahaRERA as P51700048508, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KALYAN SQUARE's possession date changes?
The latest dates are on KALYAN SQUARE's MahaRERA page (P51700048508). GharKundli's Kundli Watch sends a free WhatsApp update on KALYAN SQUARE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KALYAN SQUARE have?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN SQUARE has one building filed: KALYAN SQUARE with 7 floors and 44 units.
How big is the land of KALYAN SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN SQUARE stands on 1,300 sq m of land (about 0.3 acres), with 2,469 sq m of sanctioned built-up area.
What is the track record of KALYAN SQUARE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), OM Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of KALYAN SQUARE?
Google Maps has reviews of KALYAN SQUARE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KALYAN SQUARE?
KALYAN SQUARE by KAGVIN VENTURES is in Bhiwandi, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700048508, per GharKundli's check of MahaRERA records.
How many homes are in KALYAN SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN SQUARE has 0 homes in 1 tower registered on MahaRERA, and 84% of them are sold or booked.
When was KALYAN SQUARE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN SQUARE was registered on MahaRERA on 3 January 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on KALYAN SQUARE?
No court cases are listed for KALYAN SQUARE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of KALYAN SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KAGVIN VENTURES.
Check it yourself on MahaRERA
- How to check the possession date of KALYAN SQUARE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Bhiwandi
- SAMRUDDHI FLORA
- SKORA ML GOLDEN PALMS
- NEELKANTH PALMS
- USHA RESIDENCY
- STAR HOMES
- OM SAI ONE PARK
- DEEP LAXMI HEIGHT
- NANDAI RESIDENCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.