SHREE EKDANT ENCLAVE

by SHREE OM SG ENTERPRISES · Panchanand, Thane

Possession date of SHREE EKDANT ENCLAVE: 31 March 2028, moved from 30 September 2025 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700055740, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHREE EKDANT ENCLAVE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREE EKDANT ENCLAVE has moved

  1. 30 September 2025

    Completion date given when the project was registered

  2. 31 March 2028

    Extended at the builder's request (MahaRERA application EA28042620764)

    Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”

Source: SHREE EKDANT ENCLAVE’s extension records on MahaRERA (P51700055740), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREE EKDANT ENCLAVE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700055740
Status
Registered and active
Builder
SHREE OM SG ENTERPRISES
Location
Panchanand, Thane · 421203
Project type
Residential / Group Housing
Registered on
16 Apr 2024
Completion date at registration
September 2025
Latest completion date
March 2028
Delay so far
30 months
Homes
16
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHREE EKDANT ENCLAVE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE EKDANT ENCLAVE100%30%20%0%

Commencement certificate (CC), as filed on MahaRERA

  • SHREE EKDANT ENCLAVE: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE EKDANT ENCLAVE every month.

SHREE EKDANT ENCLAVE: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE EKDANT ENCLAVE (4 floors, 16 units)
  • Car parking: 1 covered
  • Land: 430 sq m (about 0.1 acres) · sanctioned built-up 722 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHREE EKDANT ENCLAVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREE EKDANT ENCLAVE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREE EKDANT ENCLAVE

What is the possession date of SHREE EKDANT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE EKDANT ENCLAVE in Panchanand, Thane is 31 March 2028 — 30 months later than 30 September 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHREE EKDANT ENCLAVE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE EKDANT ENCLAVE's builder has filed on MahaRERA, the official one, is 31 March 2028, already 30 months later than the 30 September 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREE EKDANT ENCLAVE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE EKDANT ENCLAVE's builder applied to MahaRERA to extend the completion date once: to 31 March 2028, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.".

What is the RERA number of SHREE EKDANT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREE EKDANT ENCLAVE in Panchanand, Thane is P51700055740.

Is SHREE EKDANT ENCLAVE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE EKDANT ENCLAVE is registered as P51700055740 and its status is "Registered and active".

What is the construction status of SHREE EKDANT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE EKDANT ENCLAVE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE EKDANT ENCLAVE is 30% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.

Does SHREE EKDANT ENCLAVE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHREE EKDANT ENCLAVE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE EKDANT ENCLAVE is registered on MahaRERA as P51700055740, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREE EKDANT ENCLAVE's possession date changes?

The latest dates are on SHREE EKDANT ENCLAVE's MahaRERA page (P51700055740). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE EKDANT ENCLAVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREE EKDANT ENCLAVE have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE EKDANT ENCLAVE has one building filed: SHREE EKDANT ENCLAVE with 4 floors and 16 units.

How much parking does SHREE EKDANT ENCLAVE have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for SHREE EKDANT ENCLAVE.

How big is the land of SHREE EKDANT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE EKDANT ENCLAVE stands on 430 sq m of land (about 0.1 acres), with 722 sq m of sanctioned built-up area.

Where can I read reviews of SHREE EKDANT ENCLAVE?

Google Maps has reviews of SHREE EKDANT ENCLAVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREE EKDANT ENCLAVE?

SHREE EKDANT ENCLAVE by SHREE OM SG ENTERPRISES is in Panchanand, Thane (pincode 421203), Maharashtra, and is registered on MahaRERA as P51700055740, per GharKundli's check of MahaRERA records.

How many homes are in SHREE EKDANT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE EKDANT ENCLAVE has 16 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was SHREE EKDANT ENCLAVE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE EKDANT ENCLAVE was registered on MahaRERA on 16 April 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREE EKDANT ENCLAVE?

No court cases are listed for SHREE EKDANT ENCLAVE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHREE EKDANT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE OM SG ENTERPRISES.

All projects with possession due in 2028 in Thane →

Other projects in Kalyan

All 98 projects in Dombivali (421203) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.