LA CENTRUM
by Bhumi Homes (Nakshatra) · Dombivli East, ThaneAlso near Borivali West, Kole, Bhiwandi
Possession date of LA CENTRUM: 30 April 2032, moved from 31 December 2026 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700029282, and currently active. Its completion date has moved from December 2026 to April 2032: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about LA CENTRUM?
How the possession date of LA CENTRUM has moved
31 December 2026
Completion date given when the project was registered
31 December 2031
Extended at the builder's request (MahaRERA application EA09062621295)
Reason the builder gave MahaRERA:
“The development of the project was initially commenced in May-2021. However, due to financial constraints and various technical Challenges, substantial development activities could not be undertaken during the initial period. Subsequently,…” Read the full reason
“The development of the project was initially commenced in May-2021. However, due to financial constraints and various technical Challenges, substantial development activities could not be undertaken during the initial period. Subsequently, in the year 2024, the partnership firm underwent reconstitution, and a revised building plan was submitted to the Municipal Corporation for approval. The revised plan was approved in November-2025, following which construction activities were commenced in accordance with the sanctioned plans. Considering the time consumed in obtaining the revised approval…”30 April 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: LA CENTRUM’s extension records on MahaRERA (P51700029282), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on LA CENTRUM
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700029282
- Status
- Registered and active
- Builder
- Bhumi Homes
- Location
- Dombivli East, Thane · 421203
- Project type
- Residential / Group Housing
- Registered on
- 18 May 2021
- Completion date at registration
- December 2026
- Latest completion date
- April 2032
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 176
- Sold or booked
- 7%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of LA CENTRUM, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BLDG 1 WING A & B | 0% | 0% | 0% | 0% |
| BUILDING 2 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BLDG 1 WING A & B: covers 12 floors
- BUILDING 2: covers 2 floors
Latest CC order on MahaRERA: dated 18/11/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on LA CENTRUM every month.
LA CENTRUM: buildings, flats and land, as filed on MahaRERA
- Buildings: BLDG 1 WING A & B (12 floors, 180 units) · BUILDING 2 (2 floors, 11 units)
- Car parking: 74 covered, 52 open
- Land: 6,410 sq m (about 1.6 acres) · sanctioned built-up 11,243 sq m · recreational space 12 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
LA Homes (a group of 4 linked companies) has 4 projects on MahaRERA since 2021, this one included. Of the 4 GharKundli has checked: 3 still being built, 1 past the promised date (typically 1 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of LA CENTRUM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
LA CENTRUM: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LA CENTRUM
What is the possession date of LA CENTRUM?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LA CENTRUM in Dombivli East, Thane is 30 April 2032 — 60 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for LA CENTRUM?
Builders and listing sites often quote an earlier "target" date for handover. The completion date LA CENTRUM's builder has filed on MahaRERA, the official one, is 30 April 2032, already 60 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of LA CENTRUM extended?
According to GharKundli's check of MahaRERA records (updated October 2026), LA CENTRUM's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "The development of the project was initially commenced in May-2021. However, due to financial constraints and various technical Challenges, substantial development activities could not be undertaken during the initial period. Subsequently, in the year 2024, the partnership firm underwent reconstitution, and a revised building plan was submitted to the Municipal Corporation for approval. The revised plan was approved in November-2025, following which construction activities were commenced in accordance with the sanctioned plans. Considering the time consumed in obtaining the revised approval…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of LA CENTRUM?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LA CENTRUM in Dombivli East, Thane is P51700029282.
Is LA CENTRUM registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LA CENTRUM is registered as P51700029282 and its status is "Registered and active".
What is the construction status of LA CENTRUM?
According to GharKundli's check of MahaRERA records (updated October 2026), LA CENTRUM's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does LA CENTRUM have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is LA CENTRUM safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), LA CENTRUM is registered on MahaRERA as P51700029282, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if LA CENTRUM's possession date changes?
The latest dates are on LA CENTRUM's MahaRERA page (P51700029282). GharKundli's Kundli Watch sends a free WhatsApp update on LA CENTRUM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does LA CENTRUM have?
According to GharKundli's check of MahaRERA records (updated October 2026), LA CENTRUM has 2 buildings filed: BLDG 1 WING A & B with 12 floors and 180 units; BUILDING 2 with 2 floors and 11 units.
How much parking does LA CENTRUM have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 74 covered and 52 open car parking spaces for LA CENTRUM.
How big is the land of LA CENTRUM?
According to GharKundli's check of MahaRERA records (updated October 2026), LA CENTRUM stands on 6,410 sq m of land (about 1.6 acres), with 11,243 sq m of sanctioned built-up area and 12 sq m of recreational open space.
What is the track record of LA CENTRUM's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), LA Homes (a group of 4 linked companies) has 4 projects on MahaRERA since 2021, this one included. Of the 4 GharKundli has checked: 3 still being built, 1 past the promised date (typically 1 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of LA CENTRUM?
Google Maps has reviews of LA CENTRUM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is LA CENTRUM?
LA CENTRUM by Bhumi Homes (Nakshatra) is in Dombivli East, Thane (pincode 421203), near Borivali West, Kole, Bhiwandi, Maharashtra, and is registered on MahaRERA as P51700029282, per GharKundli's check of MahaRERA records.
How many homes are in LA CENTRUM?
According to GharKundli's check of MahaRERA records (updated October 2026), LA CENTRUM has 176 homes in 2 towers registered on MahaRERA, and 7% of them are sold or booked.
When was LA CENTRUM registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LA CENTRUM was registered on MahaRERA on 18 May 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on LA CENTRUM?
No court cases are listed for LA CENTRUM on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of LA CENTRUM?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Bhumi Homes, the company Nakshatra files this project under.
Check it yourself on MahaRERA
- How to check the possession date of LA CENTRUM
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 421203
- LAXMI CASTLE
- USHAKIRAN ENCLAVE
- Trinity
- LA GRANDEUR
- Regency Luxuria Phase II
- VIDHI IMPRESSION
- SHREE EKDANT ENCLAVE
- AMBRIN 3
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.