LotuAai Darshan Wing B
by LOTUAAI CONSTRUCTION CO · Dombivali, Thane
Possession date of LotuAai Darshan Wing B: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700077567, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about LotuAai Darshan Wing B?
How the possession date of LotuAai Darshan Wing B has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA13112518318)
Reason the builder gave MahaRERA:
“Following are the explanatory reasons setting out grounds and reasons for delay in completion of our said project: 1. Our project Lotuaai Darshan Wing B has been physically completed in all respects, which is duly supported by the latest up…” Read the full reason
“Following are the explanatory reasons setting out grounds and reasons for delay in completion of our said project: 1. Our project Lotuaai Darshan Wing B has been physically completed in all respects, which is duly supported by the latest uploaded Form–1 Architect Certificate. 2. However, due to procedural delays at the competent authority’s end, the Full OC is still pending. We have submitted all requisite documents and compliances within the prescribed timelines, but the clearance process is yet to be finalized by the authority. 3. Consequently, we are unable to complete the formalities wi…”31 December 2026
Extended at the builder's request (MahaRERA application EA07072621685)
Reason the builder gave MahaRERA:
“1)The construction of Lotuaai Darshan Wing B has been fully completed. 2)However, the Full Occupancy Certificate (OC) has not yet been issued due to procedural delays at the competent authority. 3) In view of this and since the Full OC is s…” Read the full reason
“1)The construction of Lotuaai Darshan Wing B has been fully completed. 2)However, the Full Occupancy Certificate (OC) has not yet been issued due to procedural delays at the competent authority. 3) In view of this and since the Full OC is still pending we request an extension of the project RERA registration period to allow completion of the remaining statutory formalities and issuance of the Full Occupancy Certificate. 4)This request is made solely due to administrative delays at the competent authority end and not due to any pending construction work at the project site.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: LotuAai Darshan Wing B’s extension records on MahaRERA (P51700077567), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on LotuAai Darshan Wing B
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700077567
- Status
- Registered and active
- Builder
- LOTUAAI CONSTRUCTION CO
- Location
- Dombivali, Thane · 421202
- Project type
- Residential / Group Housing
- Registered on
- 11 Oct 2024
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 49
- Sold or booked
- 50%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of LotuAai Darshan Wing B, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| LotuAai Darshan Wing B | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- LotuAai Darshan Wing B: covers 13 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on LotuAai Darshan Wing B every month.
LotuAai Darshan Wing B: buildings, flats and land, as filed on MahaRERA
- Buildings: LotuAai Darshan Wing B (13 floors, 52 units)
- Land: 2,100 sq m (about 0.5 acres) · sanctioned built-up 3,530 sq m
- Boundaries filed include: Reti Bunder Cross Road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of LotuAai Darshan Wing B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
LotuAai Darshan Wing B: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LotuAai Darshan Wing B
What is the possession date of LotuAai Darshan Wing B?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LotuAai Darshan Wing B in Dombivali, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for LotuAai Darshan Wing B?
Builders and listing sites often quote an earlier "target" date for handover. The completion date LotuAai Darshan Wing B's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of LotuAai Darshan Wing B extended?
According to GharKundli's check of MahaRERA records (updated October 2026), LotuAai Darshan Wing B's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "Following are the explanatory reasons setting out grounds and reasons for delay in completion of our said project: 1. Our project Lotuaai Darshan Wing B has been physically completed in all respects, which is duly supported by the latest uploaded Form–1 Architect Certificate. 2. However, due to procedural delays at the competent authority’s end, the Full OC is still pending. We have submitted all requisite documents and compliances within the prescribed timelines, but the clearance process is yet to be finalized by the authority. 3. Consequently, we are unable to complete the formalities wi…"; to 31 December 2026, giving the reason "1)The construction of Lotuaai Darshan Wing B has been fully completed. 2)However, the Full Occupancy Certificate (OC) has not yet been issued due to procedural delays at the competent authority. 3) In view of this and since the Full OC is still pending we request an extension of the project RERA registration period to allow completion of the remaining statutory formalities and issuance of the Full Occupancy Certificate. 4)This request is made solely due to administrative delays at the competent authority end and not due to any pending construction work at the project site.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of LotuAai Darshan Wing B?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LotuAai Darshan Wing B in Dombivali, Thane is P51700077567.
Is LotuAai Darshan Wing B registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LotuAai Darshan Wing B is registered as P51700077567 and its status is "Registered and active".
What is the construction status of LotuAai Darshan Wing B?
According to GharKundli's check of MahaRERA records (updated October 2026), LotuAai Darshan Wing B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on LotuAai Darshan Wing B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does LotuAai Darshan Wing B have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is LotuAai Darshan Wing B safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), LotuAai Darshan Wing B is registered on MahaRERA as P51700077567, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if LotuAai Darshan Wing B's possession date changes?
The latest dates are on LotuAai Darshan Wing B's MahaRERA page (P51700077567). GharKundli's Kundli Watch sends a free WhatsApp update on LotuAai Darshan Wing B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does LotuAai Darshan Wing B have?
According to GharKundli's check of MahaRERA records (updated October 2026), LotuAai Darshan Wing B has one building filed: LotuAai Darshan Wing B with 13 floors and 52 units.
How big is the land of LotuAai Darshan Wing B?
According to GharKundli's check of MahaRERA records (updated October 2026), LotuAai Darshan Wing B stands on 2,100 sq m of land (about 0.5 acres), with 3,530 sq m of sanctioned built-up area.
Where can I read reviews of LotuAai Darshan Wing B?
Google Maps has reviews of LotuAai Darshan Wing B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is LotuAai Darshan Wing B?
LotuAai Darshan Wing B by LOTUAAI CONSTRUCTION CO is in Dombivali, Thane (pincode 421202), Maharashtra, and is registered on MahaRERA as P51700077567, per GharKundli's check of MahaRERA records. Its boundaries filed there include Reti Bunder Cross Road.
How many homes are in LotuAai Darshan Wing B?
According to GharKundli's check of MahaRERA records (updated October 2026), LotuAai Darshan Wing B has 49 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.
When was LotuAai Darshan Wing B registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LotuAai Darshan Wing B was registered on MahaRERA on 11 October 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on LotuAai Darshan Wing B?
No court cases are listed for LotuAai Darshan Wing B on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of LotuAai Darshan Wing B?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LOTUAAI CONSTRUCTION CO.
Check it yourself on MahaRERA
- How to check the possession date of LotuAai Darshan Wing B
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Dombivali
- Runwal Gardens Phase 4 Bldg No. 33-34
- Lodha Panacea II
- Runwal Gardens Phase 4 Bldg No. 38
- Runwal Gardens - Phase 8 - Bldg No. 44
- Runwal Garden City Cluster 6 Tower 6 to 9
- Runwal Edge
- Runwal Gardens Phase 8 Bldg No. 43 and 45
- Runwal Gardens Phase 6A Bldg No. 53-54
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.