What’s in the report? →Possession date of Sanghvi Nesta (MahaRERA P51700011820): 30 April 2027, moved from 31 December 2020 (72 months later). It has 102 homes, 70% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700011820, and currently active. Its completion date has moved from December 2020 to April 2027: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700011820, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sanghvi Nesta?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sanghvi Nesta has moved
31 December 2020
Completion date given when the project was registered
30 September 2022
Extended at the builder's request (MahaRERA application EXT51700002234)
Reason the builder gave MahaRERA:
“Due to unavoidable circumstances we are facing the issue that, with a huge task of excavating the plot which had a very hardcore tough rock and we were unable to break the stone using the best available machinery. Ultimately we had to use D…” Read the full reason
“Due to unavoidable circumstances we are facing the issue that, with a huge task of excavating the plot which had a very hardcore tough rock and we were unable to break the stone using the best available machinery. Ultimately we had to use Diamond Rock Cutting Machine Technology to slice the rock into smaller size and isolate it from the Mother Rock. This process led to lot of delay by months and it also increased our cost in Excavating Our Planned Basement. We hereby request to kindly extent the possession date of the above-said project to 30th September 2022.”31 December 2024
Extended at the builder's request (MahaRERA application EXT51700016682)
Reason the builder gave MahaRERA:
“Delay due to unnatural reason and beyond our control, we have taken consent of allottees. We are following all the norms of respective department to complete the building and handover the possession to the allottees which will be done very…” Read the full reason
“Delay due to unnatural reason and beyond our control, we have taken consent of allottees. We are following all the norms of respective department to complete the building and handover the possession to the allottees which will be done very soon. For change in possession date we have taken willingly consent of 73.68% Allottees of the abovementioned Project.”31 December 2025
Extended at the builder's request (MahaRERA application EXT51700024868)
Reason the builder gave MahaRERA:
“The project's delay stemmed from the unforeseen impact of the Covid-19 pandemic, which caused construction activities to be suspended. This was compounded by further delays in obtaining approvals for the revised plans and the commencement c…” Read the full reason
“The project's delay stemmed from the unforeseen impact of the Covid-19 pandemic, which caused construction activities to be suspended. This was compounded by further delays in obtaining approvals for the revised plans and the commencement certificate (CC), with the necessary approvals only being granted on 31st March 2023. These regulatory delays significantly extended the overall project timeline. Additionally, the lift installations, a critical aspect of the development, experienced setbacks, further contributing to the delay in completion. However, we assure you that our utmost priority…”31 December 2026
Extended at the builder's request (MahaRERA application EA31122519179)
Reason the builder gave MahaRERA:
“Would like to state that our Project “SANGHVI NESTA” is situated at Mumbai. We are following all the norms of respective department and rules of MahaRERA to complete the building and handover the possession to the allottees which will be do…” Read the full reason
“Would like to state that our Project “SANGHVI NESTA” is situated at Mumbai. We are following all the norms of respective department and rules of MahaRERA to complete the building and handover the possession to the allottees which will be done very soon. We have received Part Occupation Certificate dated 18.03.2025 upto 23rd floor. Due to unavoidable circumstances we are facing the worst labour issue in this time because of that we are unable to go ahead with the final fittings and final outcome of the project. Even the approvals from the department is time consuming and getting delayed at f…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sanghvi Nesta’s extension records on MahaRERA (P51700011820), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sanghvi Nesta
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700011820
- Status
- Registered and active
- Builder
- fortunerpjdevelopers
- Location
- patlipada, Thane · 400607
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- April 2027
- Delay so far
- 72 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 102
- Sold or booked
- 70%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sanghvi Nesta, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SANGHVI NESTA | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- SANGHVI NESTA: covers 28 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sanghvi Nesta every 1–2 months.
Sanghvi Nesta: buildings, flats and land, as filed on MahaRERA
- Buildings: SANGHVI NESTA (29 floors, 102 units)
- Car parking: 1 covered, 5 open
- Land: 2,406 sq m (about 0.6 acres) · sanctioned built-up 2,831 sq m · recreational space 283 sq m
- Land, as filed: 120/14 120/15 A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Naminath Erector And Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 39 months late). No complaints on MahaRERA.
Read Google reviews of Sanghvi Nesta →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sanghvi Nesta: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sanghvi Nesta
What is the possession date of Sanghvi Nesta?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sanghvi Nesta in patlipada, Thane is 30 April 2027 — 72 months later than 31 December 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 72 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sanghvi Nesta?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sanghvi Nesta's builder has filed on MahaRERA, the official one, is 30 April 2027, already 72 months later than the 31 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sanghvi Nesta extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Nesta's builder applied to MahaRERA to extend the completion date 4 times: to 30 September 2022, giving the reason "Due to unavoidable circumstances we are facing the issue that, with a huge task of excavating the plot which had a very hardcore tough rock and we were unable to break the stone using the best available machinery. Ultimately we had to use Diamond Rock Cutting Machine Technology to slice the rock into smaller size and isolate it from the Mother Rock. This process led to lot of delay by months and it also increased our cost in Excavating Our Planned Basement. We hereby request to kindly extent the possession date of the above-said project to 30th September 2022."; to 31 December 2024, giving the reason "Delay due to unnatural reason and beyond our control, we have taken consent of allottees. We are following all the norms of respective department to complete the building and handover the possession to the allottees which will be done very soon. For change in possession date we have taken willingly consent of 73.68% Allottees of the abovementioned Project."; to 31 December 2025, giving the reason "The project's delay stemmed from the unforeseen impact of the Covid-19 pandemic, which caused construction activities to be suspended. This was compounded by further delays in obtaining approvals for the revised plans and the commencement certificate (CC), with the necessary approvals only being granted on 31st March 2023. These regulatory delays significantly extended the overall project timeline. Additionally, the lift installations, a critical aspect of the development, experienced setbacks, further contributing to the delay in completion. However, we assure you that our utmost priority…"; to 31 December 2026, giving the reason "Would like to state that our Project “SANGHVI NESTA” is situated at Mumbai. We are following all the norms of respective department and rules of MahaRERA to complete the building and handover the possession to the allottees which will be done very soon. We have received Part Occupation Certificate dated 18.03.2025 upto 23rd floor. Due to unavoidable circumstances we are facing the worst labour issue in this time because of that we are unable to go ahead with the final fittings and final outcome of the project. Even the approvals from the department is time consuming and getting delayed at f…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sanghvi Nesta?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sanghvi Nesta in patlipada, Thane is P51700011820.
Is Sanghvi Nesta registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Nesta is registered as P51700011820 and its status is "Registered and active".
What is the current construction status of Sanghvi Nesta? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Nesta's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SANGHVI NESTA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Sanghvi Nesta have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sanghvi Nesta safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Nesta is registered on MahaRERA as P51700011820, its completion date has moved 72 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sanghvi Nesta?
Sanghvi Nesta is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sanghvi Nesta?
For a flat in Sanghvi Nesta (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sanghvi Nesta received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Nesta is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sanghvi Nesta uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sanghvi Nesta was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sanghvi Nesta's possession date changes?
The latest dates are on Sanghvi Nesta's MahaRERA page (P51700011820). GharKundli's Kundli Watch sends a free WhatsApp update on Sanghvi Nesta every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sanghvi Nesta have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Nesta has one building filed: SANGHVI NESTA with 29 floors and 102 units.
How much parking does Sanghvi Nesta have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 5 open car parking spaces for Sanghvi Nesta.
How big is the land of Sanghvi Nesta?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Nesta stands on 2,406 sq m of land (about 0.6 acres), with 2,831 sq m of sanctioned built-up area and 283 sq m of recreational open space.
What is the track record of Sanghvi Nesta's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Naminath Erector And Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 39 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sanghvi Nesta?
Google Maps has reviews of Sanghvi Nesta written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sanghvi Nesta?
Sanghvi Nesta by fortunerpjdevelopers (Naminath) is in patlipada, Thane, pincode 400607 (near Kolshet, brahmand, Chakala, Andheri East), Maharashtra, and is registered on MahaRERA as P51700011820, per GharKundli's check of MahaRERA records. Its land is filed as 120/14 120/15 A. GharKundli lists all 218 MahaRERA projects in Sandozbaugh (400607).
How many flats are in Sanghvi Nesta, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Nesta has 102 homes in 1 tower registered on MahaRERA, and 70% of them are sold or booked.
When was Sanghvi Nesta registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Nesta was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Sanghvi Nesta have any legal issues or court cases?
No court cases are listed for Sanghvi Nesta on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sanghvi Nesta?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is fortunerpjdevelopers, the company Naminath files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Sanghvi Nesta
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Thane
- Platinum Heritage
- Raj Tattva Phase 1 Commercial
- Veer Square (Thane)
- Gurukrupa Nityam
- Mauli Krupa
- Centurion
- Asavari Co Op HSG Soc LTD
- Lotus
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.