Possession date of SHUBHAM GARDEN: 30 April 2027, moved from 30 April 2022 (56 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700012672, and currently active. Its completion date has moved from April 2022 to April 2027: 56 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHUBHAM GARDEN?
How the possession date of SHUBHAM GARDEN has moved
30 April 2022
Completion date given when the project was registered
30 April 2023
Extended at the builder's request (MahaRERA application EXT51700011875)
Reason the builder gave MahaRERA: “Due to Covid Pandemic and Recession in Real Estate World their is Slow down in construction of project and therefore we required one year extension as to complete all the compliance's related to the Project”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51700015248)
Reason the builder gave MahaRERA: “Extension of project is applied as we received revised CC . Revised CC along with plan is updated on Rera portal”
31 December 2026
Extended at the builder's request (MahaRERA application EXT51700027136)
Reason the builder gave MahaRERA:
“To, The MahaRERA Authority, Maharashtra Real Estate Regulatory Authority, Mumbai. Subject: Request for Extension of Project Registration for “SHUBHAM GARDEN” (RERA No. P51700012672) under Section 6 of RERA Dear Sir/Madam, We, Shubhamdrishti…” Read the full reason
“To, The MahaRERA Authority, Maharashtra Real Estate Regulatory Authority, Mumbai. Subject: Request for Extension of Project Registration for “SHUBHAM GARDEN” (RERA No. P51700012672) under Section 6 of RERA Dear Sir/Madam, We, Shubhamdrishti Enterprises, hereby request an extension of the registration of our project “SHUBHAM GARDEN”, bearing RERA registration number P51700012672, until 31st December 2026 to complete the development as per the revised Completion Certificate (CC) dated 12th January 2022. The reasons for seeking this extension are as follows: 1. Consent from Sold Allottees: As…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHUBHAM GARDEN’s extension records on MahaRERA (P51700012672), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHUBHAM GARDEN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700012672
- Status
- Registered and active
- Builder
- SHUBHAM DRASHTI ENTERPRISES
- Location
- Mira Road East, Thane · 401101
- Project type
- Others
- Registered on
- 7 Sep 2017
- Completion date at registration
- April 2022
- Latest completion date
- April 2027
- Delay so far
- 56 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 56
- Sold or booked
- 36%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHUBHAM GARDEN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHUBHAM GARDEN BLDG NO 1 | 100% | 0% | 100% | 80% |
| SHUBHAM GARDEN BLDG NO 2 | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHUBHAM GARDEN BLDG NO 1: covers 12 floors
- SHUBHAM GARDEN BLDG NO 2: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHUBHAM GARDEN every month.
SHUBHAM GARDEN: buildings, flats and land, as filed on MahaRERA
- Buildings: SHUBHAM GARDEN BLDG NO 1 (13 floors, 43 units) · SHUBHAM GARDEN BLDG NO 2 (13 floors, 21 units)
- Land: 2,680 sq m (about 0.7 acres) · sanctioned built-up 2,403 sq m · recreational space 54 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shri Hari Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 26 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of SHUBHAM GARDEN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHUBHAM GARDEN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHUBHAM GARDEN
What is the possession date of SHUBHAM GARDEN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHUBHAM GARDEN in Mira Road East, Thane is 30 April 2027 — 56 months later than 30 April 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHUBHAM GARDEN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHUBHAM GARDEN's builder has filed on MahaRERA, the official one, is 30 April 2027, already 56 months later than the 30 April 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHUBHAM GARDEN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBHAM GARDEN's builder applied to MahaRERA to extend the completion date 3 times: to 30 April 2023, giving the reason "Due to Covid Pandemic and Recession in Real Estate World their is Slow down in construction of project and therefore we required one year extension as to complete all the compliance's related to the Project"; to 31 December 2024, giving the reason "Extension of project is applied as we received revised CC . Revised CC along with plan is updated on Rera portal"; to 31 December 2026, giving the reason "To, The MahaRERA Authority, Maharashtra Real Estate Regulatory Authority, Mumbai. Subject: Request for Extension of Project Registration for “SHUBHAM GARDEN” (RERA No. P51700012672) under Section 6 of RERA Dear Sir/Madam, We, Shubhamdrishti Enterprises, hereby request an extension of the registration of our project “SHUBHAM GARDEN”, bearing RERA registration number P51700012672, until 31st December 2026 to complete the development as per the revised Completion Certificate (CC) dated 12th January 2022. The reasons for seeking this extension are as follows: 1. Consent from Sold Allottees: As…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SHUBHAM GARDEN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHUBHAM GARDEN in Mira Road East, Thane is P51700012672.
Is SHUBHAM GARDEN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBHAM GARDEN is registered as P51700012672 and its status is "Registered and active".
What is the construction status of SHUBHAM GARDEN?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBHAM GARDEN's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SHUBHAM GARDEN have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHUBHAM GARDEN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBHAM GARDEN is registered on MahaRERA as P51700012672, its completion date has moved 56 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHUBHAM GARDEN's possession date changes?
The latest dates are on SHUBHAM GARDEN's MahaRERA page (P51700012672). GharKundli's Kundli Watch sends a free WhatsApp update on SHUBHAM GARDEN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHUBHAM GARDEN have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBHAM GARDEN has 2 buildings filed: SHUBHAM GARDEN BLDG NO 1 with 13 floors and 43 units; SHUBHAM GARDEN BLDG NO 2 with 13 floors and 21 units.
How big is the land of SHUBHAM GARDEN?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBHAM GARDEN stands on 2,680 sq m of land (about 0.7 acres), with 2,403 sq m of sanctioned built-up area and 54 sq m of recreational open space.
What is the track record of SHUBHAM GARDEN's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shri Hari Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 26 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHUBHAM GARDEN?
Google Maps has reviews of SHUBHAM GARDEN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHUBHAM GARDEN?
SHUBHAM GARDEN by SHUBHAM DRASHTI ENTERPRISES is in Mira Road East, Thane (pincode 401101), near Bhayander West, Bhayander East, Village Navghar, Maharashtra, and is registered on MahaRERA as P51700012672, per GharKundli's check of MahaRERA records.
How many homes are in SHUBHAM GARDEN?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBHAM GARDEN has 56 homes in 2 towers registered on MahaRERA, and 36% of them are sold or booked.
When was SHUBHAM GARDEN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBHAM GARDEN was registered on MahaRERA on 7 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHUBHAM GARDEN?
No court cases are listed for SHUBHAM GARDEN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHUBHAM GARDEN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHUBHAM DRASHTI ENTERPRISES.
Check it yourself on MahaRERA
- How to check the possession date of SHUBHAM GARDEN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Mira Road East
- URBAN RESERVE WING B
- PALM LANDS
- SHWETA HEIGHTS
- UNIQUE VISTAS MHADA BUILDING NO. 1,2,3
- SHREE SHASHWAT BLDG20
- RUHAAN AVENUE
- SALASAR SHEETAL SANGEET
- Benevolent MB Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.