TEEJADEEP HEIGHTS
by TEEJADEEP DEVELOPERS · Jambli Naka, ThaneAlso near Majiwada, Charai, Chendani
Possession: TEEJADEEP HEIGHTS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700010345. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about TEEJADEEP HEIGHTS?
How the possession date of TEEJADEEP HEIGHTS has moved
30 September 2018
Completion date given when the project was registered
30 September 2019
Extended at the builder's request (MahaRERA application EXT51700000695)
Reason the builder gave MahaRERA:
“Construction work is fully completed . We attach herewith Architect Certificate stating that entire construction is completed. We also attach Commencement Certificate of Competent Authority and there are no restriction on time limit to comp…” Read the full reason
“Construction work is fully completed . We attach herewith Architect Certificate stating that entire construction is completed. We also attach Commencement Certificate of Competent Authority and there are no restriction on time limit to complete the construction.”
Source: TEEJADEEP HEIGHTS’s extension records on MahaRERA (P51700010345), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on TEEJADEEP HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the September 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700010345
- Status
- Completed
- Builder
- TEEJADEEP DEVELOPERS
- Location
- Jambli Naka, Thane · 400601
- Project type
- Residential / Group Housing
- Registered on
- 24 Aug 2017
- Completion date at registration
- September 2018
- Latest completion date
- September 2019
- Delay so far
- 12 months
- Homes
- 35
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of TEEJADEEP HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING G - 5TH - 12 FLR | 100% | 100% | 95% | 60% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on TEEJADEEP HEIGHTS every month.
TEEJADEEP HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING G - 5TH - 12 FLR (11 floors)
- Land: 605 sq m (about 0.1 acres) · sanctioned built-up 1,922 sq m
- Boundaries filed include: LBS RD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of TEEJADEEP HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TEEJADEEP HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TEEJADEEP HEIGHTS
What is the possession date of TEEJADEEP HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TEEJADEEP HEIGHTS in Jambli Naka, Thane is 30 September 2019 — 12 months later than 30 September 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for TEEJADEEP HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TEEJADEEP HEIGHTS's builder has filed on MahaRERA, the official one, is 30 September 2019, already 12 months later than the 30 September 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of TEEJADEEP HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), TEEJADEEP HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 30 September 2019, giving the reason "Construction work is fully completed . We attach herewith Architect Certificate stating that entire construction is completed. We also attach Commencement Certificate of Competent Authority and there are no restriction on time limit to complete the construction.".
What is the RERA number of TEEJADEEP HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TEEJADEEP HEIGHTS in Jambli Naka, Thane is P51700010345.
Is TEEJADEEP HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TEEJADEEP HEIGHTS is registered as P51700010345 and its status is "Completed".
What is the construction status of TEEJADEEP HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), TEEJADEEP HEIGHTS's status on MahaRERA is "Completed". As filed by the builder, slab work on BUILDING G - 5TH - 12 FLR is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does TEEJADEEP HEIGHTS have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is TEEJADEEP HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), TEEJADEEP HEIGHTS is registered on MahaRERA as P51700010345, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if TEEJADEEP HEIGHTS's possession date changes?
The latest dates are on TEEJADEEP HEIGHTS's MahaRERA page (P51700010345). GharKundli's Kundli Watch sends a free WhatsApp update on TEEJADEEP HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does TEEJADEEP HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated November 2026), TEEJADEEP HEIGHTS has one building filed: BUILDING G - 5TH - 12 FLR with 11 floors.
How big is the land of TEEJADEEP HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), TEEJADEEP HEIGHTS stands on 605 sq m of land (about 0.1 acres), with 1,922 sq m of sanctioned built-up area.
Where can I read reviews of TEEJADEEP HEIGHTS?
Google Maps has reviews of TEEJADEEP HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TEEJADEEP HEIGHTS?
TEEJADEEP HEIGHTS by TEEJADEEP DEVELOPERS is in Jambli Naka, Thane (pincode 400601), near Majiwada, Charai, Chendani, Maharashtra, and is registered on MahaRERA as P51700010345, per GharKundli's check of MahaRERA records. Its boundaries filed there include LBS RD.
How many homes are in TEEJADEEP HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), TEEJADEEP HEIGHTS has 35 homes in 1 tower registered on MahaRERA.
When was TEEJADEEP HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TEEJADEEP HEIGHTS was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on TEEJADEEP HEIGHTS?
No court cases are listed for TEEJADEEP HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of TEEJADEEP HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is TEEJADEEP DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of TEEJADEEP HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- BHAKTI PEARL - C
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- MAULI KRUPA
- GURUKRUPA NITYAM
- Panache
- LOTUS
- ASAVARI CO OP HSG SOC LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.