RUPAREL LUMINARE
by Shree Sukhakarta Developers Private Limited (Ruparel) · dadar Naigoan, MumbaiAlso near Wadala, Barc, Bhawani Shankar
Possession date of RUPAREL LUMINARE: 30 October 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900034393. Status: Lapsed (registration period ended). Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about RUPAREL LUMINARE?
How the possession date of RUPAREL LUMINARE has moved
30 June 2026
Completion date given when the project was registered
30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RUPAREL LUMINARE’s extension records on MahaRERA (P51900034393), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RUPAREL LUMINARE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 complaints, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900034393
- Status
- Lapsed (registration period ended)
- Builder
- Shree Sukhakarta Developers Private Limited
- Location
- dadar Naigoan, Mumbai · 400014
- Project type
- Residential / Group Housing
- Registered on
- 5 Apr 2022
- Completion date at registration
- June 2026
- Latest completion date
- October 2026
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 210
- Towers
- 2
- Complaints on MahaRERA
- 8
- Court cases listed
- 0
- Appeals at the tribunal
- 7
- Title report on file
- Not found
Construction progress of RUPAREL LUMINARE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A wing | 0% | 0% | 0% | 0% |
| Wing B | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RUPAREL LUMINARE every month.
RUPAREL LUMINARE: buildings, flats and land, as filed on MahaRERA
- Buildings: A wing (32 floors) · Wing B (42 floors)
- Land: 1,525 sq m (about 0.4 acres) · sanctioned built-up 15,949 sq m
- Boundaries filed include: GD Ambedkar marg
The builder’s record and reviews
Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects.
Read Google reviews of RUPAREL LUMINARE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RUPAREL LUMINARE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RUPAREL LUMINARE
What is the possession date of RUPAREL LUMINARE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RUPAREL LUMINARE in dadar Naigoan, Mumbai is 30 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for RUPAREL LUMINARE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RUPAREL LUMINARE's builder has filed on MahaRERA, the official one, is 30 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of RUPAREL LUMINARE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RUPAREL LUMINARE in dadar Naigoan, Mumbai is P51900034393.
Is RUPAREL LUMINARE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL LUMINARE is registered as P51900034393 and its status is "Lapsed (registration period ended)".
What is the construction status of RUPAREL LUMINARE?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL LUMINARE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does RUPAREL LUMINARE have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RUPAREL LUMINARE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL LUMINARE is registered on MahaRERA as P51900034393, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RUPAREL LUMINARE's possession date changes?
The latest dates are on RUPAREL LUMINARE's MahaRERA page (P51900034393). GharKundli's Kundli Watch sends a free WhatsApp update on RUPAREL LUMINARE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RUPAREL LUMINARE have?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL LUMINARE has 2 buildings filed: A wing with 32 floors; Wing B with 42 floors.
How big is the land of RUPAREL LUMINARE?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL LUMINARE stands on 1,525 sq m of land (about 0.4 acres), with 15,949 sq m of sanctioned built-up area.
What is the track record of RUPAREL LUMINARE's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of RUPAREL LUMINARE?
Google Maps has reviews of RUPAREL LUMINARE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RUPAREL LUMINARE?
RUPAREL LUMINARE by Shree Sukhakarta Developers Private Limited (Ruparel) is in dadar Naigoan, Mumbai (pincode 400014), near Wadala, Barc, Bhawani Shankar, Maharashtra, and is registered on MahaRERA as P51900034393, per GharKundli's check of MahaRERA records. Its boundaries filed there include GD Ambedkar marg.
How many homes are in RUPAREL LUMINARE?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL LUMINARE has 210 homes in 2 towers registered on MahaRERA.
When was RUPAREL LUMINARE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL LUMINARE was registered on MahaRERA on 5 April 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on RUPAREL LUMINARE?
No court cases are listed for RUPAREL LUMINARE on MahaRERA, and 7 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RUPAREL LUMINARE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shree Sukhakarta Developers Private Limited, the company Ruparel files this project under.
Check it yourself on MahaRERA
- How to check the possession date of RUPAREL LUMINARE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in pincode 400014
All 61 projects in Dadar (400014) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.