SKYWARDS REGENCY
by SKYWARDS VISION DEVELOPERS · Mira Village, ThaneAlso near Bhayander, Village Navghar, Borivali West
Possession date of SKYWARDS REGENCY: 31 December 2025, moved from 30 June 2020 (66 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700014068. Status: Lapsed (registration period ended). 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about SKYWARDS REGENCY?
How the possession date of SKYWARDS REGENCY has moved
30 June 2020
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT51700008993)
Reason the builder gave MahaRERA:
“The completion date for the said project was 30/06/2020. But due to the pandemic which is commenced by March 2020, we were unable to complete the project and yet even after the lockdown has been at eased there are difficulties to cope with…” Read the full reason
“The completion date for the said project was 30/06/2020. But due to the pandemic which is commenced by March 2020, we were unable to complete the project and yet even after the lockdown has been at eased there are difficulties to cope with the labours and the material frequency. The project is completed upto 10th floor and maximum interior work has also been completed. We say that the project is 80% completed from our end. We have sold only upto 30% of the project including the shops and the flats. We request you to grant us an extension upto 31st December, 2021. We have full faith we will…”30 December 2024
Extended at the builder's request (MahaRERA application EXT51700012491)
Reason the builder gave MahaRERA: “THE BUILDING IS PARTLY COMPLETED ONLY THE UPPER FLOORS ARE PENDING.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700027156)
Reason the builder gave MahaRERA: “The project is delayed due to pending approvals from Concerned Authorities”
Source: SKYWARDS REGENCY’s extension records on MahaRERA (P51700014068), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SKYWARDS REGENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700014068
- Status
- Lapsed (registration period ended)
- Builder
- SKYWARDS VISION DEVELOPERS
- Location
- Mira Village, Thane · 401104
- Project type
- Residential / Group Housing
- Registered on
- 7 Nov 2017
- Completion date at registration
- June 2020
- Latest completion date
- December 2025
- Delay so far
- 66 months
- Homes
- 150
- Towers
- 2
- Complaints on MahaRERA
- 8
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SKYWARDS REGENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SKYWARDS REGENCY A WING | 100% | 60% | 30% | 0% |
| SKYWARDS REGENCY B WING | 100% | 15% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SKYWARDS REGENCY every month.
SKYWARDS REGENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: SKYWARDS REGENCY A WING (38 floors) · SKYWARDS REGENCY B WING (50 floors)
- Land: 3,690 sq m (about 0.9 acres) · sanctioned built-up 3,690 sq m · recreational space 1,223 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SKYWARDS REGENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SKYWARDS REGENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SKYWARDS REGENCY
What is the possession date of SKYWARDS REGENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SKYWARDS REGENCY in Mira Village, Thane is 31 December 2025 — 66 months later than 30 June 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SKYWARDS REGENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SKYWARDS REGENCY's builder has filed on MahaRERA, the official one, is 31 December 2025, already 66 months later than the 30 June 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SKYWARDS REGENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYWARDS REGENCY's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2021, giving the reason "The completion date for the said project was 30/06/2020. But due to the pandemic which is commenced by March 2020, we were unable to complete the project and yet even after the lockdown has been at eased there are difficulties to cope with the labours and the material frequency. The project is completed upto 10th floor and maximum interior work has also been completed. We say that the project is 80% completed from our end. We have sold only upto 30% of the project including the shops and the flats. We request you to grant us an extension upto 31st December, 2021. We have full faith we will…"; to 30 December 2024, giving the reason "THE BUILDING IS PARTLY COMPLETED ONLY THE UPPER FLOORS ARE PENDING."; to 31 December 2025, giving the reason "The project is delayed due to pending approvals from Concerned Authorities".
What is the RERA number of SKYWARDS REGENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SKYWARDS REGENCY in Mira Village, Thane is P51700014068.
Is SKYWARDS REGENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYWARDS REGENCY is registered as P51700014068 and its status is "Lapsed (registration period ended)".
What is the construction status of SKYWARDS REGENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYWARDS REGENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 15% to 60% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SKYWARDS REGENCY have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SKYWARDS REGENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYWARDS REGENCY is registered on MahaRERA as P51700014068, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 66 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SKYWARDS REGENCY's possession date changes?
The latest dates are on SKYWARDS REGENCY's MahaRERA page (P51700014068). GharKundli's Kundli Watch sends a free WhatsApp update on SKYWARDS REGENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SKYWARDS REGENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYWARDS REGENCY has 2 buildings filed: SKYWARDS REGENCY A WING with 38 floors; SKYWARDS REGENCY B WING with 50 floors.
How big is the land of SKYWARDS REGENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYWARDS REGENCY stands on 3,690 sq m of land (about 0.9 acres), with 3,690 sq m of sanctioned built-up area and 1,223 sq m of recreational open space.
Where can I read reviews of SKYWARDS REGENCY?
Google Maps has reviews of SKYWARDS REGENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SKYWARDS REGENCY?
SKYWARDS REGENCY by SKYWARDS VISION DEVELOPERS is in Mira Village, Thane (pincode 401104), near Bhayander, Village Navghar, Borivali West, Maharashtra, and is registered on MahaRERA as P51700014068, per GharKundli's check of MahaRERA records.
How many homes are in SKYWARDS REGENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYWARDS REGENCY has 150 homes in 2 towers registered on MahaRERA.
When was SKYWARDS REGENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYWARDS REGENCY was registered on MahaRERA on 7 November 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SKYWARDS REGENCY?
No court cases are listed for SKYWARDS REGENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SKYWARDS REGENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SKYWARDS VISION DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of SKYWARDS REGENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
All Thane projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.