by YASH INFRA · Louisewadi, ThaneAlso near Panchpakhadi, Wagle Estate, Wagle Industrial Estate
Possession date of URBAN Villa: 30 July 2026, moved from 15 December 2022 (43 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700015488. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about URBAN Villa?
How the possession date of URBAN Villa has moved
15 December 2022
Completion date given when the project was registered
15 December 2023
Extended at the builder's request (MahaRERA application EXT51700013597)
Reason the builder gave MahaRERA: “DUE TO COVID PANDEMIC THE PROJECT WAS DELAYED.”
15 December 2024
Extended at the builder's request (MahaRERA application EXT51700018116)
Reason the builder gave MahaRERA: “WE REQUEST YOU TO EXTENT THE RERA DATE AS THE PROJECT IS GETTING EXTENDED DUE TO TOWER PARKING. THE TOWER PARKING HEIGHT WILL BE ABOVE 45 METERS, THE TIME FOR TOWER PARKING IS 8 TO 10 MONTHS. REST ALL THE WORK OF THE BUILDING IS COMPLETED.”
21 December 2025
Extended at the builder's request (MahaRERA application EXT51700027249)
Reason the builder gave MahaRERA:
“WE HAVE COMPLETED THE PROJECT AND WE APPLIED FOR OC ON 3/12/2024 FOR URBAN VILLA PROJECT AND OUR RERA GOT EXPIRED ON 15/12/2024 .SO WE HAVE APPLIED FOR EXTENSION FOR RERA SO WE ARE REQUESTING YOU TO EXTEND THE RERA. THE OC PROCESS IS GOING…” Read the full reason
“WE HAVE COMPLETED THE PROJECT AND WE APPLIED FOR OC ON 3/12/2024 FOR URBAN VILLA PROJECT AND OUR RERA GOT EXPIRED ON 15/12/2024 .SO WE HAVE APPLIED FOR EXTENSION FOR RERA SO WE ARE REQUESTING YOU TO EXTEND THE RERA. THE OC PROCESS IS GOING ON IN TMC AND ONCE WE GET OC WE SHALL UPDATE RERA ACCORDINGLY SO KINDLY RENEW THE RERA .”30 July 2026
Extended at the builder's request (MahaRERA application EA20012619507)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The project has been delayed due to delay in Parking work. The parking work could not be completed within the stipulated timeline due to an unfo…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The project has been delayed due to delay in Parking work. The parking work could not be completed within the stipulated timeline due to an unforeseen and unavoidable circumstance. The contractor originally appointed for the parking work unfortunately demised while the project was in progress. Consequently, the work had to be discontinued and reassigned to a new contractor. Additional time was required for the appointment, mobilization, and resumption of work by the new contractor. Due to this un…”
Source: URBAN Villa’s extension records on MahaRERA (P51700015488), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on URBAN Villa
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700015488
- Status
- Lapsed (registration period ended)
- Builder
- YASH INFRA
- Location
- Louisewadi, Thane · 400604
- Project type
- Residential / Group Housing
- Registered on
- 1 Mar 2018
- Completion date at registration
- December 2022
- Latest completion date
- July 2026
- Delay so far
- 43 months
- Homes
- 78
- Sold or booked
- 78%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 11
Construction progress of URBAN Villa, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Urban Villa | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Urban Villa: covers Ground + Constructed Amenity Area + 16 Upper Floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on URBAN Villa every month.
URBAN Villa: buildings, flats and land, as filed on MahaRERA
- Buildings: Urban Villa (17 floors, 78 units)
- Land: 1,751 sq m (about 0.4 acres) · sanctioned built-up 1,562 sq m · recreational space 1,751 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Yash Infra (a group of 2 linked companies) has 9 projects on MahaRERA since 2018, this one included. Of the 9 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 11 months); 7 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of URBAN Villa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
URBAN Villa: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about URBAN Villa
What is the possession date of URBAN Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for URBAN Villa in Louisewadi, Thane is 30 July 2026 — 43 months later than 15 December 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for URBAN Villa?
Builders and listing sites often quote an earlier "target" date for handover. The completion date URBAN Villa's builder has filed on MahaRERA, the official one, is 30 July 2026, already 43 months later than the 15 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of URBAN Villa extended?
According to GharKundli's check of MahaRERA records (updated October 2026), URBAN Villa's builder applied to MahaRERA to extend the completion date 4 times: to 15 December 2023, giving the reason "DUE TO COVID PANDEMIC THE PROJECT WAS DELAYED."; to 15 December 2024, giving the reason "WE REQUEST YOU TO EXTENT THE RERA DATE AS THE PROJECT IS GETTING EXTENDED DUE TO TOWER PARKING. THE TOWER PARKING HEIGHT WILL BE ABOVE 45 METERS, THE TIME FOR TOWER PARKING IS 8 TO 10 MONTHS. REST ALL THE WORK OF THE BUILDING IS COMPLETED."; to 21 December 2025, giving the reason "WE HAVE COMPLETED THE PROJECT AND WE APPLIED FOR OC ON 3/12/2024 FOR URBAN VILLA PROJECT AND OUR RERA GOT EXPIRED ON 15/12/2024 .SO WE HAVE APPLIED FOR EXTENSION FOR RERA SO WE ARE REQUESTING YOU TO EXTEND THE RERA. THE OC PROCESS IS GOING ON IN TMC AND ONCE WE GET OC WE SHALL UPDATE RERA ACCORDINGLY SO KINDLY RENEW THE RERA ."; to 30 July 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The project has been delayed due to delay in Parking work. The parking work could not be completed within the stipulated timeline due to an unforeseen and unavoidable circumstance. The contractor originally appointed for the parking work unfortunately demised while the project was in progress. Consequently, the work had to be discontinued and reassigned to a new contractor. Additional time was required for the appointment, mobilization, and resumption of work by the new contractor. Due to this un…".
What is the RERA number of URBAN Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of URBAN Villa in Louisewadi, Thane is P51700015488.
Is URBAN Villa registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), URBAN Villa is registered as P51700015488 and its status is "Lapsed (registration period ended)".
What is the construction status of URBAN Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), URBAN Villa's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Urban Villa is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does URBAN Villa have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is URBAN Villa safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), URBAN Villa is registered on MahaRERA as P51700015488, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 43 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if URBAN Villa's possession date changes?
The latest dates are on URBAN Villa's MahaRERA page (P51700015488). GharKundli's Kundli Watch sends a free WhatsApp update on URBAN Villa every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does URBAN Villa have?
According to GharKundli's check of MahaRERA records (updated October 2026), URBAN Villa has one building filed: Urban Villa with 17 floors and 78 units.
How big is the land of URBAN Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), URBAN Villa stands on 1,751 sq m of land (about 0.4 acres), with 1,562 sq m of sanctioned built-up area and 1,751 sq m of recreational open space.
What is the track record of URBAN Villa's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Yash Infra (a group of 2 linked companies) has 9 projects on MahaRERA since 2018, this one included. Of the 9 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 11 months); 7 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of URBAN Villa?
Google Maps has reviews of URBAN Villa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is URBAN Villa?
URBAN Villa by YASH INFRA is in Louisewadi, Thane (pincode 400604), near Panchpakhadi, Wagle Estate, Wagle Industrial Estate, Maharashtra, and is registered on MahaRERA as P51700015488, per GharKundli's check of MahaRERA records.
How many homes are in URBAN Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), URBAN Villa has 78 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.
When was URBAN Villa registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), URBAN Villa was registered on MahaRERA on 1 March 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on URBAN Villa?
No court cases are listed for URBAN Villa on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of URBAN Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is YASH INFRA, which has 11 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of URBAN Villa
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Thane
- YASH REALTORS
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- MAULI KRUPA
- GURUKRUPA NITYAM
- Panache
- LOTUS
- ASAVARI CO OP HSG SOC LTD
Other projects by YASH INFRA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.