Aradhna Vitthu Paradise Building No. 3

by ARADHNA CONSTRUCTION · Vitthalwadi, Thane 421306Registered on MahaRERA as “VITTHU PARADISE BUILDING NO. 3”

What’s in the report? →

Possession date of Aradhna Vitthu Paradise Building No. 3 (MahaRERA P51700015831): 30 March 2027, moved from 28 August 2021 (67 months later). It has 71 homes, 66% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700015831, and currently active.

Source: MahaRERA website — records for P51700015831, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Aradhna Vitthu Paradise Building No. 3?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Aradhna Vitthu Paradise Building No. 3 has moved

  1. 28 August 2021

    Completion date given when the project was registered

  2. 30 September 2023

    Extended at the builder's request (MahaRERA application EXT51700010805)

    Reason the builder gave MahaRERA: “Non availability of labour due to Corona pandemic caused the delay”
  3. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51700019511)

    Reason the builder gave MahaRERA:
    “We would like to inform that the period 2019-2022 was not favourable for real-estate sectors due to the Covid-19 pandemic ,frequent lockdown, shortage of building materials and shortage of skilled staff and due to this construction of proje…” Read the full reason“We would like to inform that the period 2019-2022 was not favourable for real-estate sectors due to the Covid-19 pandemic ,frequent lockdown, shortage of building materials and shortage of skilled staff and due to this construction of project work were largely affected and the project was not able to complete in time and we expect some more delay in completion project. Therefore, we request you to extend the project completion date up to 31/03/2025”
  4. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51700028236)

    Reason the builder gave MahaRERA:
    “Due to the recent changes made by the competent authority .for the development plan road layout , the designated land for the modified D P Road has been handed over to Kalyan Dombivli Municipal Corporation by a DeNo.KLY-2-24484 dated 19/12/…” Read the full reason“Due to the recent changes made by the competent authority .for the development plan road layout , the designated land for the modified D P Road has been handed over to Kalyan Dombivli Municipal Corporation by a DeNo.KLY-2-24484 dated 19/12/2024. But due to some human error in the Deed of Transfer (wrong mentioned of Built-up area than the actual land are) ,the correction deed is pending for registration and expected to be complete the process in the coming days).Copy of draft correction deed and registered transfer deed is uploaded in the other Tab.”
  5. 30 March 2027

    Extended at the builder's request (MahaRERA application EA27042620743)

    Reason the builder gave MahaRERA: “Project work has been completed 98 % and in the process of applying for Occupancy Certificate”

Source: Aradhna Vitthu Paradise Building No. 3’s extension records on MahaRERA (P51700015831), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aradhna Vitthu Paradise Building No. 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700015831
Status
Registered and active
Builder
ARADHNA CONSTRUCTION
Location
Vitthalwadi, Thane · 421306
Project type
Residential / Group Housing
Registered on
27 Mar 2018
Completion date at registration
August 2021
Latest completion date
March 2027
Delay so far
67 months
Homes
71
Sold or booked
66%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Aradhna Vitthu Paradise Building No. 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING100%100%98%98%
B WING100%100%98%98%

Commencement certificate (CC), as filed on MahaRERA

  • A WING: covers 8 floors
  • B WING: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aradhna Vitthu Paradise Building No. 3 every 1–2 months.

Aradhna Vitthu Paradise Building No. 3: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING (9 floors, 41 units) · B WING (12 floors, 30 units)
  • Car parking: 5 covered
  • Land: 5,734 sq m (about 1.4 acres) · sanctioned built-up 4,578 sq m · recreational space 860 sq m
  • Land, as filed: 121,5/7,5/8,5/9,5/10,5/11,5/12
  • Map: Get directions

The builder’s record and reviews

Aaradhana Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 28 months late). No complaints on MahaRERA.

Read Google reviews of Aradhna Vitthu Paradise Building No. 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aradhna Vitthu Paradise Building No. 3: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aradhna Vitthu Paradise Building No. 3

What is the possession date of Aradhna Vitthu Paradise Building No. 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aradhna Vitthu Paradise Building No. 3 in Vitthalwadi, Thane is 30 March 2027 — 67 months later than 28 August 2021, the date given at registration.

The date has already moved 67 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Aradhna Vitthu Paradise Building No. 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aradhna Vitthu Paradise Building No. 3's builder has filed on MahaRERA, the official one, is 30 March 2027, already 67 months later than the 28 August 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Aradhna Vitthu Paradise Building No. 3 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Aradhna Vitthu Paradise Building No. 3's builder applied to MahaRERA to extend the completion date 4 times: to 30 September 2023, giving the reason "Non availability of labour due to Corona pandemic caused the delay"; to 31 March 2025, giving the reason "We would like to inform that the period 2019-2022 was not favourable for real-estate sectors due to the Covid-19 pandemic ,frequent lockdown, shortage of building materials and shortage of skilled staff and due to this construction of project work were largely affected and the project was not able to complete in time and we expect some more delay in completion project. Therefore, we request you to extend the project completion date up to 31/03/2025"; to 31 March 2026, giving the reason "Due to the recent changes made by the competent authority .for the development plan road layout , the designated land for the modified D P Road has been handed over to Kalyan Dombivli Municipal Corporation by a DeNo.KLY-2-24484 dated 19/12/2024. But due to some human error in the Deed of Transfer (wrong mentioned of Built-up area than the actual land are) ,the correction deed is pending for registration and expected to be complete the process in the coming days).Copy of draft correction deed and registered transfer deed is uploaded in the other Tab."; to 30 March 2027, giving the reason "Project work has been completed 98 % and in the process of applying for Occupancy Certificate".

What is the RERA number of Aradhna Vitthu Paradise Building No. 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aradhna Vitthu Paradise Building No. 3 in Vitthalwadi, Thane is P51700015831.

Is Aradhna Vitthu Paradise Building No. 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aradhna Vitthu Paradise Building No. 3 is registered as P51700015831 and its status is "Registered and active".

What is the current construction status of Aradhna Vitthu Paradise Building No. 3? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Aradhna Vitthu Paradise Building No. 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Aradhna Vitthu Paradise Building No. 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Aradhna Vitthu Paradise Building No. 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Aradhna Vitthu Paradise Building No. 3 is registered on MahaRERA as P51700015831, its completion date has moved 67 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aradhna Vitthu Paradise Building No. 3?

Aradhna Vitthu Paradise Building No. 3 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aradhna Vitthu Paradise Building No. 3?

For a flat in Aradhna Vitthu Paradise Building No. 3 (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Aradhna Vitthu Paradise Building No. 3 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aradhna Vitthu Paradise Building No. 3 is still under construction, with 30 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Aradhna Vitthu Paradise Building No. 3 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aradhna Vitthu Paradise Building No. 3 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aradhna Vitthu Paradise Building No. 3's possession date changes?

The latest dates are on Aradhna Vitthu Paradise Building No. 3's MahaRERA page (P51700015831). GharKundli's Kundli Watch sends a free WhatsApp update on Aradhna Vitthu Paradise Building No. 3 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aradhna Vitthu Paradise Building No. 3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Aradhna Vitthu Paradise Building No. 3 has 2 buildings filed: A WING with 9 floors and 41 units; B WING with 12 floors and 30 units.

How much parking does Aradhna Vitthu Paradise Building No. 3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 5 covered car parking spaces for Aradhna Vitthu Paradise Building No. 3.

How big is the land of Aradhna Vitthu Paradise Building No. 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Aradhna Vitthu Paradise Building No. 3 stands on 5,734 sq m of land (about 1.4 acres), with 4,578 sq m of sanctioned built-up area and 860 sq m of recreational open space.

What is the track record of Aradhna Vitthu Paradise Building No. 3's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Aaradhana Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 28 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Aradhna Vitthu Paradise Building No. 3?

Google Maps has reviews of Aradhna Vitthu Paradise Building No. 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aradhna Vitthu Paradise Building No. 3?

Aradhna Vitthu Paradise Building No. 3 by ARADHNA CONSTRUCTION is in Vitthalwadi, Thane, pincode 421306, Maharashtra, and is registered on MahaRERA as P51700015831, per GharKundli's check of MahaRERA records. Its land is filed as 121,5/7,5/8,5/9,5/10,5/11,5/12. GharKundli lists all 270 MahaRERA projects in Kalyan East (421306).

How many flats are in Aradhna Vitthu Paradise Building No. 3, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Aradhna Vitthu Paradise Building No. 3 has 71 homes in 2 towers registered on MahaRERA, and 66% of them are sold or booked.

When was Aradhna Vitthu Paradise Building No. 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aradhna Vitthu Paradise Building No. 3 was registered on MahaRERA on 27 March 2018. GharKundli did not find a title report on the land on file there.

Does Aradhna Vitthu Paradise Building No. 3 have any legal issues or court cases?

No court cases are listed for Aradhna Vitthu Paradise Building No. 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Aradhna Vitthu Paradise Building No. 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARADHNA CONSTRUCTION.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan

All 270 projects in Kalyan East (421306) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.