Parth Skyone

by Parth Parikh · MIDC, Thane 421201Also near Dombivli East, Ramnagar, Village- G.B Patharli

What’s in the report? →

Possession date of Parth Skyone (MahaRERA P51700015994): 30 October 2026, moved from 30 December 2023 (30 months later), and it has already passed. It has 160 homes, 52% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700015994, and currently active. Its completion date has moved from December 2023 to October 2026: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700015994, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Parth Skyone?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Parth Skyone has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT51700025529)

    Reason the builder gave MahaRERA:
    “We have recently obtained a new Commencement Certificate (CC) dated 17/10/2024 from the competent authority, which is valid until period of one Year commencing from date of it issue. We are confident that with the new CC, we will be able to…” Read the full reason“We have recently obtained a new Commencement Certificate (CC) dated 17/10/2024 from the competent authority, which is valid until period of one Year commencing from date of it issue. We are confident that with the new CC, we will be able to complete the project within the extended timeframe. We request you to consider our application for extension of registration and grant us the necessary extension to complete the project. We are committed to complying with all the provisions of the RERA Act and rules made there under.”
  3. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Parth Skyone’s extension records on MahaRERA (P51700015994), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Parth Skyone

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700015994
Status
Registered and active
Builder
Parth Parikh
Location
MIDC, Thane · 421201
Project type
Residential / Group Housing
Registered on
11 Apr 2018
Completion date at registration
December 2023
Latest completion date
October 2026
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
160
Sold or booked
52%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Parth Skyone, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PARTH SKY ONE100%100%95%90%

Commencement certificate (CC), as filed on MahaRERA

  • PARTH SKY ONE: covers ZERO FSI

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Parth Skyone every 1–2 months.

Parth Skyone: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Parth Skyone →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Parth Skyone: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Parth Skyone

What is the possession date of Parth Skyone?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Parth Skyone in MIDC, Thane is 30 October 2026 — 30 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

The date has already moved 30 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Parth Skyone?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Parth Skyone's builder has filed on MahaRERA, the official one, is 30 October 2026, already 30 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Parth Skyone extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Parth Skyone's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "We have recently obtained a new Commencement Certificate (CC) dated 17/10/2024 from the competent authority, which is valid until period of one Year commencing from date of it issue. We are confident that with the new CC, we will be able to complete the project within the extended timeframe. We request you to consider our application for extension of registration and grant us the necessary extension to complete the project. We are committed to complying with all the provisions of the RERA Act and rules made there under.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Parth Skyone?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Parth Skyone in MIDC, Thane is P51700015994.

Is Parth Skyone registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Parth Skyone is registered as P51700015994 and its status is "Registered and active".

What is the current construction status of Parth Skyone? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Parth Skyone's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PARTH SKY ONE is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does Parth Skyone have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Parth Skyone safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Parth Skyone is registered on MahaRERA as P51700015994, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Parth Skyone?

Parth Skyone is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Parth Skyone?

For a flat in Parth Skyone (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Parth Skyone received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Parth Skyone is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Parth Skyone uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Parth Skyone was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Parth Skyone's possession date changes?

The latest dates are on Parth Skyone's MahaRERA page (P51700015994). GharKundli's Kundli Watch sends a free WhatsApp update on Parth Skyone every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Parth Skyone have?

According to GharKundli's check of MahaRERA records (updated October 2026), Parth Skyone has one building filed: PARTH SKY ONE with 24 floors and 185 units.

How big is the land of Parth Skyone?

According to GharKundli's check of MahaRERA records (updated October 2026), Parth Skyone stands on 3,200 sq m of land (about 0.8 acres), with 4,800 sq m of sanctioned built-up area and 1,836 sq m of recreational open space.

What are the reviews of Parth Skyone?

Google Maps has reviews of Parth Skyone written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Parth Skyone?

Parth Skyone by Parth Parikh is in MIDC, Thane, pincode 421201 (near Dombivli East, Ramnagar, Village- G.B Patharli), Maharashtra, and is registered on MahaRERA as P51700015994, per GharKundli's check of MahaRERA records. Its land is filed as RH 212 RH213 RH214 RH215. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Parth Skyone, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Parth Skyone has 160 homes in 1 tower registered on MahaRERA, and 52% of them are sold or booked.

When was Parth Skyone registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Parth Skyone was registered on MahaRERA on 11 April 2018. GharKundli did not find a title report on the land on file there.

Does Parth Skyone have any legal issues or court cases?

No court cases are listed for Parth Skyone on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Parth Skyone?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Parth Parikh.

All projects with possession due in 2026 in Thane →

Other projects in Tilaknagar (421201)

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.