Bhagwati Sky Avenue
by Bhagwati Infrastructure · Waldhuni, Thane 421301Registered on MahaRERA as “Sky Avenue”
What’s in the report? →Possession date of Bhagwati Sky Avenue (MahaRERA P51700017501): 31 March 2026, moved from 30 December 2024 (15 months later), and it has already passed. It has 71 homes, 55% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700017501. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700017501, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (March 2026) has passed.
What do you want to know about Bhagwati Sky Avenue?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Bhagwati Sky Avenue has moved
30 December 2024
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EA10122518589)
Reason the builder gave MahaRERA:
“We are seeking an extension for the project as the completion date of the project in MAHARERA was 30/12/2024. Due to certain administrative issues, we were unable to apply for the extension on or before 30th December 2024. We have now obtai…” Read the full reason
“We are seeking an extension for the project as the completion date of the project in MAHARERA was 30/12/2024. Due to certain administrative issues, we were unable to apply for the extension on or before 30th December 2024. We have now obtained the Full Occupancy Certificate (OC) as on date and wish to apply for the completion of the project. Therefore, we kindly request MAHARERA to grant an extension of the project due date till 31st March 2026 to enable us to complete the necessary formalities and ensure full compliance with the regulatory requirements.”
Source: Bhagwati Sky Avenue’s extension records on MahaRERA (P51700017501), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bhagwati Sky Avenue
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700017501
- Status
- Lapsed (registration period ended)
- Builder
- Bhagwati Infrastructure
- Location
- Waldhuni, Thane · 421301
- Project type
- Others
- Registered on
- 23 Aug 2018
- Completion date at registration
- December 2024
- Latest completion date
- March 2026
- Delay so far
- 15 months
- Homes
- 71
- Sold or booked
- 55%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Bhagwati Sky Avenue, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sky Avenue Wing A | 100% | 100% | 100% | 100% |
| Sky Avenue Wing B | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Sky Avenue Wing A: covers 18 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhagwati Sky Avenue every 1–2 months.
Bhagwati Sky Avenue: buildings, flats and land, as filed on MahaRERA
- Buildings: Sky Avenue Wing A (20 floors, 85 units)
- Car parking: 10 covered
- Land: 1,363 sq m (about 0.3 acres) · sanctioned built-up 3,500 sq m
- Boundaries filed include: Katemanivali shiv and Ganesh Colony
- Land, as filed: Survey No 176/A Pt at village kalyan, Survety No94A/6, Survey No 94B at villagekatermanivali
- Map: Get directions
The builder’s record and reviews
Oscar Infrastructure (a group of 6 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 7 still being built, 5 past the promised date (typically 18 months late); 2 lapsed. 21 complaints on MahaRERA across 2 projects.
Read Google reviews of Bhagwati Sky Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bhagwati Sky Avenue: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Bhagwati Sky Avenue
What is the possession date of Bhagwati Sky Avenue?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bhagwati Sky Avenue in Waldhuni, Thane is 31 March 2026 — 15 months later than 30 December 2024, the date given at registration. That date has already passed.
The date has already moved 15 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Bhagwati Sky Avenue?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhagwati Sky Avenue's builder has filed on MahaRERA, the official one, is 31 March 2026, already 15 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Bhagwati Sky Avenue extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue's builder applied to MahaRERA to extend the completion date once: to 31 March 2026, giving the reason "We are seeking an extension for the project as the completion date of the project in MAHARERA was 30/12/2024. Due to certain administrative issues, we were unable to apply for the extension on or before 30th December 2024. We have now obtained the Full Occupancy Certificate (OC) as on date and wish to apply for the completion of the project. Therefore, we kindly request MAHARERA to grant an extension of the project due date till 31st March 2026 to enable us to complete the necessary formalities and ensure full compliance with the regulatory requirements.".
What is the RERA number of Bhagwati Sky Avenue?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bhagwati Sky Avenue in Waldhuni, Thane is P51700017501.
Is Bhagwati Sky Avenue registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue is registered as P51700017501 and its status is "Lapsed (registration period ended)".
What is the current construction status of Bhagwati Sky Avenue? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Bhagwati Sky Avenue have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Bhagwati Sky Avenue safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue is registered on MahaRERA as P51700017501, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Bhagwati Sky Avenue?
Bhagwati Sky Avenue isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Bhagwati Sky Avenue?
For a flat in Bhagwati Sky Avenue (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Bhagwati Sky Avenue received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 March 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Bhagwati Sky Avenue?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 March 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Bhagwati Sky Avenue uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Bhagwati Sky Avenue was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Bhagwati Sky Avenue's possession date changes?
The latest dates are on Bhagwati Sky Avenue's MahaRERA page (P51700017501). GharKundli's Kundli Watch sends a free WhatsApp update on Bhagwati Sky Avenue every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bhagwati Sky Avenue have?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue has one building filed: Sky Avenue Wing A with 20 floors and 85 units.
How much parking does Bhagwati Sky Avenue have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 covered car parking spaces for Bhagwati Sky Avenue.
How big is the land of Bhagwati Sky Avenue?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue stands on 1,363 sq m of land (about 0.3 acres), with 3,500 sq m of sanctioned built-up area.
What is the track record of Bhagwati Sky Avenue's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Oscar Infrastructure (a group of 6 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 7 still being built, 5 past the promised date (typically 18 months late); 2 lapsed. 21 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Bhagwati Sky Avenue?
Google Maps has reviews of Bhagwati Sky Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Bhagwati Sky Avenue?
Bhagwati Sky Avenue by Bhagwati Infrastructure is in Waldhuni, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700017501, per GharKundli's check of MahaRERA records. Its boundaries filed there include Katemanivali shiv and Ganesh Colony. Its land is filed as Survey No 176/A Pt at village kalyan, Survety No94A/6, Survey No 94B at villagekatermanivali. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Bhagwati Sky Avenue, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue has 71 homes in 2 towers registered on MahaRERA, and 55% of them are sold or booked.
When was Bhagwati Sky Avenue registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagwati Sky Avenue was registered on MahaRERA on 23 August 2018. GharKundli did not find a title report on the land on file there.
Does Bhagwati Sky Avenue have any legal issues or court cases?
No court cases are listed for Bhagwati Sky Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Bhagwati Sky Avenue?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Bhagwati Infrastructure.
Check it yourself on MahaRERA
- How to check the possession date of Bhagwati Sky Avenue
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan
- Medhekar Heights
- Senwin Residency
- Royal Hills
- Majesty Heights
- Vidhi Impression
- Mangeshi Dhara
- Swami Elite
- Om Trimurti Darshan
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.