The Icon Phase 1
by Leading Frontier Private Limited · Dhokali, ThaneAlso near Balkum, Badlapur, Naupada
Possession: The Icon Phase 1 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700018370. Status: Completed. 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about The Icon Phase 1?
How the possession date of The Icon Phase 1 has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT51700008479)
Reason the builder gave MahaRERA:
“Impact of COVID 19 is severe more particularly on Real Estate Sector. The major impacts are narrated as under :- 1. Set-back of Migrated Workers resulting in non availability of semi skilled and unskilled workers 2. Social Distancing During…” Read the full reason
“Impact of COVID 19 is severe more particularly on Real Estate Sector. The major impacts are narrated as under :- 1. Set-back of Migrated Workers resulting in non availability of semi skilled and unskilled workers 2. Social Distancing During Construction has slow down the pace of construction 3. Isolation of Outside Workers while resuming on Construction Site 4. Procurement Delays in Material - many anciliary industries providing raw materials to Real estate are not yet functioning on full capacity. 5. Reduction in purchasing power of people - This has affected the demand & delay in decision…”30 June 2024
Revised completion date on MahaRERA
Source: The Icon Phase 1’s extension records on MahaRERA (P51700018370), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Icon Phase 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 complaints and 8 court cases, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- The Icon Phase 2P51700028535 · possession 30 Jun 2026
- THE ICON PHASE 3P51700029059 · possession 30 Apr 2027
- The Icon Phase 4P51700029062 · possession 30 Apr 2027
- The Icon Phase 5P51700033286 · possession 30 Apr 2027
- MahaRERA registration
- P51700018370
- Status
- Completed
- Builder
- Leading Frontier Private Limited
- Location
- Dhokali, Thane · 400608
- Project type
- Others
- Registered on
- 26 Oct 2018
- Completion date at registration
- December 2022
- Latest completion date
- June 2024
- Delay so far
- 18 months
- Homes
- 364
- Towers
- 2
- Complaints on MahaRERA
- 8
- Court cases listed
- 8
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of The Icon Phase 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B1 Madison 1 | 100% | 100% | 100% | 100% |
| A2 Madison 2 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Icon Phase 1 every month.
The Icon Phase 1: buildings, flats and land, as filed on MahaRERA
- Buildings: B1 Madison 1 (29 floors) · A2 Madison 2 (33 floors)
- Land: 6,237 sq m (about 1.5 acres) · sanctioned built-up 24,277 sq m
- Boundaries filed include: Runwal Garden City
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Leading Frontier has 5 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 3 still being built, none past the promised date yet. 11 complaints on MahaRERA across 4 projects.
Read Google reviews of The Icon Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Icon Phase 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about The Icon Phase 1
What is the possession date of The Icon Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Icon Phase 1 in Dhokali, Thane is 30 June 2024 — 18 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for The Icon Phase 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Icon Phase 1's builder has filed on MahaRERA, the official one, is 30 June 2024, already 18 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of The Icon Phase 1 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), The Icon Phase 1's builder applied to MahaRERA to extend the completion date once: to 30 December 2023, giving the reason "Impact of COVID 19 is severe more particularly on Real Estate Sector. The major impacts are narrated as under :- 1. Set-back of Migrated Workers resulting in non availability of semi skilled and unskilled workers 2. Social Distancing During Construction has slow down the pace of construction 3. Isolation of Outside Workers while resuming on Construction Site 4. Procurement Delays in Material - many anciliary industries providing raw materials to Real estate are not yet functioning on full capacity. 5. Reduction in purchasing power of people - This has affected the demand & delay in decision…".
What is the RERA number of The Icon Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Icon Phase 1 in Dhokali, Thane is P51700018370.
Is The Icon Phase 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Icon Phase 1 is registered as P51700018370 and its status is "Completed".
What is the construction status of The Icon Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), The Icon Phase 1's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does The Icon Phase 1 have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is The Icon Phase 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), The Icon Phase 1 is registered on MahaRERA as P51700018370, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does The Icon Phase 1 have other wings or phases?
Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: The Icon Phase 2 (P51700028535, possession 30 Jun 2026); THE ICON PHASE 3 (P51700029059, possession 30 Apr 2027); The Icon Phase 4 (P51700029062, possession 30 Apr 2027); The Icon Phase 5 (P51700033286, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if The Icon Phase 1's possession date changes?
The latest dates are on The Icon Phase 1's MahaRERA page (P51700018370). GharKundli's Kundli Watch sends a free WhatsApp update on The Icon Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Icon Phase 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), The Icon Phase 1 has 2 buildings filed: B1 Madison 1 with 29 floors; A2 Madison 2 with 33 floors.
How big is the land of The Icon Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), The Icon Phase 1 stands on 6,237 sq m of land (about 1.5 acres), with 24,277 sq m of sanctioned built-up area.
What is the track record of The Icon Phase 1's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Leading Frontier has 5 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 3 still being built, none past the promised date yet. 11 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of The Icon Phase 1?
Google Maps has reviews of The Icon Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is The Icon Phase 1?
The Icon Phase 1 by Leading Frontier Private Limited is in Dhokali, Thane (pincode 400608), near Balkum, Badlapur, Naupada, Maharashtra, and is registered on MahaRERA as P51700018370, per GharKundli's check of MahaRERA records. Its boundaries filed there include Runwal Garden City.
How many homes are in The Icon Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), The Icon Phase 1 has 364 homes in 2 towers registered on MahaRERA.
When was The Icon Phase 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Icon Phase 1 was registered on MahaRERA on 26 October 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on The Icon Phase 1?
8 court cases are listed for The Icon Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of The Icon Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Leading Frontier Private Limited, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of The Icon Phase 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Dhokali
- Elanor - Tower 1
- Lodha Kolshet A2 - Tower 3
- Elanor - Tower 2
- HIGHLAND SPRINGS B4- C WING
- Lodha Crown Kolshet - Tower 2
- Lodha Crown Kolshet-Tower 1
- Vakratunda Anantaraa Business Park
- Vakratunda Anantaraa Tower 1
Other projects by Leading Frontier Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.