Vishnu Vatika Wing C Phase II

by VISHNU VATIKA · Badlapur Gaon, Thane 421503Also near Kulgaon

What’s in the report? →

Possession date of Vishnu Vatika Wing C Phase II (MahaRERA P51700020130): 31 December 2026, moved from 30 May 2023 (43 months later). It has 103 homes, 82% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700020130, and currently active.

Source: MahaRERA website — records for P51700020130, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Vishnu Vatika Wing C Phase II?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Vishnu Vatika Wing C Phase II has moved

  1. 30 May 2023

    Completion date given when the project was registered

  2. 29 May 2024

    Extended at the builder's request (MahaRERA application EXT51700016637)

    Reason the builder gave MahaRERA: “As per attachment”
  3. 30 May 2025

    Extended at the builder's request (MahaRERA application EXT51700019804)

    Reason the builder gave MahaRERA: “As per the attachment”
  4. 31 March 2026

    Extended at the builder's request (MahaRERA application EA26112518441)

    Reason the builder gave MahaRERA:
    “The main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn result…” Read the full reason“The main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn resulted into delay in completion of the project. Moreover, the contractors appointed for the various work also underperformed due to which overall schedule of construction effected. It may be noted that the project is located at Badlapur. Uncertain operational challenges like heavy rains during rainy season also disrupted regular construction work. The only pe…”
  5. 31 December 2026

    Extended at the builder's request (MahaRERA application EA04072621669)

    Reason the builder gave MahaRERA:
    “The construction work of the project has been completed in all respects. This is duly evidenced by Table A of Form 1, i.e., the Architect’s Certificate. The primary reason for the delay in completion of the project was the slow pace of sale…” Read the full reason“The construction work of the project has been completed in all respects. This is duly evidenced by Table A of Form 1, i.e., the Architect’s Certificate. The primary reason for the delay in completion of the project was the slow pace of sales during the initial phases. Although the number of units sold has improved over time, the earlier sluggish sales adversely impacted on the project’s cash flow, thereby contributing to the delay. Additionally, certain contractors appointed for execution of various works did not perform as expected, which further affected the overall construction schedule.…”

Source: Vishnu Vatika Wing C Phase II’s extension records on MahaRERA (P51700020130), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vishnu Vatika Wing C Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700020130
Status
Registered and active
Builder
VISHNU VATIKA
Location
Badlapur Gaon, Thane · 421503
Project type
Residential / Group Housing
Registered on
29 Mar 2019
Completion date at registration
May 2023
Latest completion date
December 2026
Delay so far
43 months
Homes
103
Sold or booked
82%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Vishnu Vatika Wing C Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Vishnu Vatika Wing C Phase II100%100%100%87.76%

Commencement certificate (CC), as filed on MahaRERA

  • Vishnu Vatika Wing C Phase II: covers 14 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vishnu Vatika Wing C Phase II every 1–2 months.

Vishnu Vatika Wing C Phase II: buildings, flats and land, as filed on MahaRERA

  • Buildings: Vishnu Vatika Wing C Phase II (14 floors, 109 units)
  • Land: 5,390 sq m (about 1.3 acres) · sanctioned built-up 400 sq m · recreational space 519 sq m
  • Land, as filed: Survey No.131, Hissa No. 2 and 4
  • Map: Get directions

The builder’s record and reviews

Vishnu Vatika has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 43 months); 1 still being built, 1 past the promised date (typically 29 months late). No complaints on MahaRERA.

Read Google reviews of Vishnu Vatika Wing C Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vishnu Vatika Wing C Phase II: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vishnu Vatika Wing C Phase II

What is the possession date of Vishnu Vatika Wing C Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vishnu Vatika Wing C Phase II in Badlapur Gaon, Thane is 31 December 2026 — 43 months later than 30 May 2023, the date given at registration.

The date has already moved 43 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Vishnu Vatika Wing C Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vishnu Vatika Wing C Phase II's builder has filed on MahaRERA, the official one, is 31 December 2026, already 43 months later than the 30 May 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vishnu Vatika Wing C Phase II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika Wing C Phase II's builder applied to MahaRERA to extend the completion date 4 times: to 29 May 2024, giving the reason "As per attachment"; to 30 May 2025, giving the reason "As per the attachment"; to 31 March 2026, giving the reason "The main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn resulted into delay in completion of the project. Moreover, the contractors appointed for the various work also underperformed due to which overall schedule of construction effected. It may be noted that the project is located at Badlapur. Uncertain operational challenges like heavy rains during rainy season also disrupted regular construction work. The only pe…"; to 31 December 2026, giving the reason "The construction work of the project has been completed in all respects. This is duly evidenced by Table A of Form 1, i.e., the Architect’s Certificate. The primary reason for the delay in completion of the project was the slow pace of sales during the initial phases. Although the number of units sold has improved over time, the earlier sluggish sales adversely impacted on the project’s cash flow, thereby contributing to the delay. Additionally, certain contractors appointed for execution of various works did not perform as expected, which further affected the overall construction schedule.…".

What is the RERA number of Vishnu Vatika Wing C Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vishnu Vatika Wing C Phase II in Badlapur Gaon, Thane is P51700020130.

Is Vishnu Vatika Wing C Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika Wing C Phase II is registered as P51700020130 and its status is "Registered and active".

What is the current construction status of Vishnu Vatika Wing C Phase II? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika Wing C Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vishnu Vatika Wing C Phase II is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Vishnu Vatika Wing C Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vishnu Vatika Wing C Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika Wing C Phase II is registered on MahaRERA as P51700020130, its completion date has moved 43 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vishnu Vatika Wing C Phase II?

Vishnu Vatika Wing C Phase II is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vishnu Vatika Wing C Phase II?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vishnu Vatika Wing C Phase II: gharkundli.com/tools/property-cost-calculator

Has Vishnu Vatika Wing C Phase II received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika Wing C Phase II is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Vishnu Vatika Wing C Phase II uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vishnu Vatika Wing C Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Vishnu Vatika Wing C Phase II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: VISHNU VATIKA WING A AND B PHASE I (P51700009860, possession 31 May 2023). Check that your agreement names the registration of your own wing.

How can I get updates if Vishnu Vatika Wing C Phase II's possession date changes?

The latest dates are on Vishnu Vatika Wing C Phase II's MahaRERA page (P51700020130). GharKundli's Kundli Watch sends a free WhatsApp update on Vishnu Vatika Wing C Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vishnu Vatika Wing C Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika Wing C Phase II has one building filed: Vishnu Vatika Wing C Phase II with 14 floors and 109 units.

How big is the land of Vishnu Vatika Wing C Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika Wing C Phase II stands on 5,390 sq m of land (about 1.3 acres), with 400 sq m of sanctioned built-up area and 519 sq m of recreational open space.

What is the track record of Vishnu Vatika Wing C Phase II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 43 months); 1 still being built, 1 past the promised date (typically 29 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Vishnu Vatika Wing C Phase II?

Google Maps has reviews of Vishnu Vatika Wing C Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vishnu Vatika Wing C Phase II?

Vishnu Vatika Wing C Phase II by VISHNU VATIKA is in Badlapur Gaon, Thane, pincode 421503 (near Kulgaon), Maharashtra, and is registered on MahaRERA as P51700020130, per GharKundli's check of MahaRERA records. Its land is filed as Survey No.131, Hissa No. 2 and 4. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).

How many flats are in Vishnu Vatika Wing C Phase II, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika Wing C Phase II has 103 homes in 1 tower registered on MahaRERA, and 82% of them are sold or booked.

When was Vishnu Vatika Wing C Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika Wing C Phase II was registered on MahaRERA on 29 March 2019. GharKundli did not find a title report on the land on file there.

Does Vishnu Vatika Wing C Phase II have any legal issues or court cases?

No court cases are listed for Vishnu Vatika Wing C Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Vishnu Vatika Wing C Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VISHNU VATIKA, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Kulgaon (421503)

All 938 projects in Kulgaon (421503) →

Other projects by VISHNU VATIKA

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.