TYCOONS ORBIS
by M/s. Tycoons Developers · Kalyan, Thane
Possession date of TYCOONS ORBIS: 31 December 2026, moved from 13 June 2023 (42 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700020227. Status: In abeyance (on hold by MahaRERA). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about TYCOONS ORBIS?
GharKundli’s full report on TYCOONS ORBIS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700020227
- Status
- In abeyance (on hold by MahaRERA)
- Builder
- M/s. Tycoons Developers
- Location
- Kalyan, Thane · 421301
- Project type
- Others
- Registered on
- 29 Mar 2019
- Completion date at registration
- June 2023
- Latest completion date
- December 2026
- Delay so far
- 42 months
- Homes
- 231
- Sold or booked
- 51%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of TYCOONS ORBIS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building A | 100% | 13% | 0% | 0% |
| Building B | 100% | 9% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on TYCOONS ORBIS every month.
TYCOONS ORBIS: buildings, flats and land, as filed on MahaRERA
- Buildings: Building A (21 floors) · Building B (22 floors)
- Land: 6,780 sq m (about 1.7 acres) · sanctioned built-up 5,513 sq m · recreational space 1,060 sq m
The builder’s record and reviews
Tycoons Avanti Projects (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 still being built, 3 past the promised date (typically 28 months late); 3 lapsed. 104 complaints on MahaRERA across 7 projects.
Read Google reviews of TYCOONS ORBIS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TYCOONS ORBIS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TYCOONS ORBIS
What is the possession date of TYCOONS ORBIS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TYCOONS ORBIS in Kalyan, Thane is 31 December 2026 — 42 months later than 13 June 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for TYCOONS ORBIS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TYCOONS ORBIS's builder has filed on MahaRERA, the official one, is 31 December 2026, already 42 months later than the 13 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of TYCOONS ORBIS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TYCOONS ORBIS in Kalyan, Thane is P51700020227.
Is TYCOONS ORBIS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TYCOONS ORBIS is registered as P51700020227 and its status is "In abeyance (on hold by MahaRERA)".
What is the construction status of TYCOONS ORBIS?
According to GharKundli's check of MahaRERA records (updated November 2026), TYCOONS ORBIS's status on MahaRERA is "In abeyance (on hold by MahaRERA)". As filed by the builder, slab work ranges from 9% to 13% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does TYCOONS ORBIS have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is TYCOONS ORBIS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), TYCOONS ORBIS is registered on MahaRERA as P51700020227, its MahaRERA status is "In abeyance (on hold by MahaRERA)", its completion date has moved 42 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if TYCOONS ORBIS's possession date changes?
The latest dates are on TYCOONS ORBIS's MahaRERA page (P51700020227). GharKundli's Kundli Watch sends a free WhatsApp update on TYCOONS ORBIS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does TYCOONS ORBIS have?
According to GharKundli's check of MahaRERA records (updated November 2026), TYCOONS ORBIS has 2 buildings filed: Building A with 21 floors; Building B with 22 floors.
How big is the land of TYCOONS ORBIS?
According to GharKundli's check of MahaRERA records (updated November 2026), TYCOONS ORBIS stands on 6,780 sq m of land (about 1.7 acres), with 5,513 sq m of sanctioned built-up area and 1,060 sq m of recreational open space.
What is the track record of TYCOONS ORBIS's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Tycoons Avanti Projects (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 still being built, 3 past the promised date (typically 28 months late); 3 lapsed. 104 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of TYCOONS ORBIS?
Google Maps has reviews of TYCOONS ORBIS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TYCOONS ORBIS?
TYCOONS ORBIS by M/s. Tycoons Developers is in Kalyan, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700020227, per GharKundli's check of MahaRERA records.
How many homes are in TYCOONS ORBIS?
According to GharKundli's check of MahaRERA records (updated November 2026), TYCOONS ORBIS has 231 homes in 2 towers registered on MahaRERA, and 51% of them are sold or booked.
When was TYCOONS ORBIS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TYCOONS ORBIS was registered on MahaRERA on 29 March 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on TYCOONS ORBIS?
No court cases are listed for TYCOONS ORBIS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of TYCOONS ORBIS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/s. Tycoons Developers.
Check it yourself on MahaRERA
- How to check the possession date of TYCOONS ORBIS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in pincode 421301
All 582 projects in Kalyan (421301) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.